Warwick Photo Gallery 5 (September 2015 Through February 2016)
In this photo gallery, see how the work progressed on the new world headquarters of
Jehovah’s Witnesses and how volunteers supported the construction work between
September 2015 and February 2016.
Rendering of the completed Warwick complex. Clockwise from top left:
1. Vehicle Maintenance Building
2. Visitor Parking
3. Maintenance Building/Resident Parking
4. Residence B
5. Residence D
6. Residence C
7. Residence A
8. Offices/Services Building
![Page 2: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/2.jpg)
October 7, 2015—Warwick site
An arch for a wetlands bridge is transported to the bridge foundation. Tires cushioned the arch
when it was first unloaded from a truck. The bridge protects environmentally sensitive wetlands.
![Page 3: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/3.jpg)
October 13, 2015—Offices/Services Building
A green roof covered with a type of succulent vegetation called sedum changes color before
going dormant in winter. Sixteen varieties of sedum are planted on the roofs.
Green roofs, which help the environment by controlling stormwater,
reduce energy expenses and need only weeding to remain healthy.
![Page 4: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/4.jpg)
October 13, 2015—Residence D
A carpenter installs scribe molding in the kitchen of a residential room.
The Carpentry Department had installed more than 60 percent of all kitchen cabinets
by the end of February 2016.
![Page 5: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/5.jpg)
October 16, 2015—Offices/Services Building
Electricians install light-emitting diode (LED) lamps to illuminate
the Watch Tower logo on the courtyard tower.
![Page 6: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/6.jpg)
October 21, 2015—Offices/Services Building
The Offices/Services Building, with its courtyard tower and entrance lobby, is illuminated at
night. The tower will offer visitors a unique view of the Warwick site and its surroundings.
![Page 7: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/7.jpg)
October 22, 2015—Warwick site
Construction workers prepare an access road for emergency vehicles by laying
subgrade and pouring concrete.
The temporary burlap cover in the background reduces erosion during construction.
![Page 8: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/8.jpg)
November 9, 2015—Offices/Services Building
Workers install a prefabricated skylight above an elevator lobby.
Eleven skylights in the Offices/Services Building allow natural light into interior spaces.
![Page 9: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/9.jpg)
November 16, 2015—Maintenance Building/Resident Parking
Using an oxygen-acetylene beveling machine,
a welder cuts carbon steel pipe for the chilled water system.
![Page 10: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/10.jpg)
November 30, 2015—Offices/Services Building
A carpenter installs a window subsill.
After the subsill is leveled and the drywall is secured, a finished windowsill will be installed.
![Page 11: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/11.jpg)
December 17, 2015—Warwick site
Pavers are installed on a rainy day. At the right center of the photo,
a white screed grades two layers of aggregate to a level plane. In the foreground,
an excavator fitted with a hydraulic installation clamp lowers pavers into place.
On the left, a plastic tarp covers topsoil to prevent erosion.
![Page 12: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/12.jpg)
December 24, 2015—Warwick site
Workers pull medium-voltage wire to an electrical substation,
which supplies power to the Warwick complex.
![Page 13: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/13.jpg)
January 5, 2016—Offices/Services Building
A worker completes the frame of a walkway cover between Visitor Parking and
the Offices/Services Building. The cover will protect visitors from rain and snow.
![Page 14: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/14.jpg)
January 5, 2016—Maintenance Building/Resident Parking
A technician adjusts boiler settings at a control panel.
All four boilers at the Warwick complex are now installed.
![Page 15: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/15.jpg)
February 8, 2016—Offices/Services Building
Mechanics install dryers in the Laundry Department.
The dryers have capacities ranging from 6 to 45 kilograms (15 to 100 lbs).
Washing machines will be installed along the left wall.
![Page 16: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/16.jpg)
February 8, 2016—Tuxedo complex
Gerrit Lösch, a member of the Governing Body, conducts the Bethel family Watchtower Study.
The program is broadcast to other locations where Warwick workers are housed.
![Page 17: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/17.jpg)
February 19, 2016—Residence A
The Interiors Department delivers carpet to one of the residence buildings.
Over 65,000 square meters (78,000 sq yds) of carpet were ordered for the Warwick complex.
![Page 18: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/18.jpg)
February 22, 2016—Warwick site
Between September 2015 and February 2016, certificates of occupancy were received for
Residences C and D, allowing workers to be accommodated there.
All building elevators were installed.
Construction on Residence Drive, including the laying of pavers, was completed.
Because of the mild winter, landscaping proceeded ahead of schedule.
![Page 19: (September 2015 Through February 2016)da-ip.getmyip.com/pdf/Photos/Warwick Photo Gallery... · February 22, 2016—Warwick site Between September 2015 and February 2016, certificates](https://reader036.vdocuments.mx/reader036/viewer/2022070900/5f3c3904841a8a60b423d790/html5/thumbnails/19.jpg)
February 24, 2016—Maintenance Building/Resident Parking
A member of the suspended-ceiling crew walks on stilts to install the ceiling grid.
The Walls/Ceilings Department cares for framing, insulating, hanging and finishing drywall,
and plastering, as well as installing firestopping in wall penetrations.