Page 1: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Seminary Road Intersection

Improvements

Project Briefing

Page 2: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

MCDOT would like to brief the community on the ongoing work on the

Seminary Road Intersection Improvement project

Project Team

Project Description

Project Phasing

Schedule

Status

Q&A

Page 3: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 4: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 5: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 6: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 7: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 8: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 9: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 10: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 11: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 12: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4
Page 13: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Construction Schedule

Start of Construction - March 2020

Combined Phases 1, 2 - July 2020

Phase 3 - September 2020

Phase 4 – December 2020

Phase 5 – February 2021

Phase 6 – March 2021

Intersection Seminary Rd and 2nd Ave - April 2021

Substantial Completion - April 2021

Page 14: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Project Status

Currently working on Phases 1, 2

Completed storm drain, rough grading on Seminary Place ongoing

Curb and gutter, driveways and sidewalks along Seminary Place will be completed soon

Phase 3 will start next

Page 15: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Seminary Place road closure

Page 16: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Storm drain installation at Seminary Place

Page 17: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Grading at Seminary Place and 2nd Ave

Page 18: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Grading at Seminary Place

Page 19: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

Contact

Field Office: Tom Kidwell

301-328-5819 or 301-328-5810

[email protected]

Area Engineer: Bill Sittinger

[email protected]

Chief Construction: Marcelo Cortez

[email protected]

Page 20: Seminary Road Intersection Improvements · 5/7/2020  · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4

For more information and regular updates please visit our website or follow us on twitter

https://www.montgomerycountymd.gov/dot-dte/projects/seminary/index.html

https://twitter.com/MoCo_DTE #SeminaryRd

Q&A