SeminarObjectives
1) IPD and its impact on team behavior
2) Lean and its role in a collaborative process.
3) Pre-Fabrication
4) How Lean, BIM and collaborative processes impact project value.
![Page 2: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/2.jpg)
The Project
Texas Health Resources, Methodist Alliance Hospital, Fort Worth, Texas.
Hospital;188,000 s.f. $46.5m58 beds with growth potential of 300 beds
MOB;74,000 s.f. $10m
Project of identical scale completed within the last year set the base budget number.
![Page 3: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/3.jpg)
The Project
TextTextTextTextText
THR Presbyterian Hospital, Flower Mound, TexasFinal Cost $43,500,000
![Page 4: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/4.jpg)
The Project
![Page 5: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/5.jpg)
The Project
![Page 6: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/6.jpg)
The Project
![Page 7: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/7.jpg)
The Project
![Page 8: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/8.jpg)
Contractual IssuesPerkins + Will in Dallas is the architect, no IPD experience, no Lean experience.
Beck is the contractor, internal integrated experience, but no IPD experience, no Lean experience
Owner representative, Denton Wilson, had become a national spokesman for IPD and Lean, left halfway through the project.
Unique selection process
![Page 9: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/9.jpg)
The ProjectInitial Budget; $43,500,00
Budget with Additional Scope; $46,500,000
Initial Design Estimate; $49,500,000
Mechanical Upgrades; $2,500,000-Heat pump chillers-Additional Generator-Fanwall technology
Final Cost; $46,500,000
![Page 10: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/10.jpg)
Contractual IssuesAIA C191 contract-multi party agreement, similar to C195 but does not require the formation of an LLC.
Owner/Architect/Contractor agree to waive all claims.
Not operating under a true C191 ‘cost-plus’ model;Architect has a fixed feeContractor has a GMP
Project began $3m above baseline goal, project ended $800,000 below budget, with $2.5m in added value. No accounting for added value.
![Page 11: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/11.jpg)
Incentive PlanFee at risk;Beck $230,000 (.05%)P+W $230,000 (.05%)
Savings incentive;Beck $230,000 (.05%)P+W $230,000 (.05%)
THR retained savings; $460,000
Any additional savings beyond $1,380,000 will be split equally between the owner, architect, and contractor.
![Page 12: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/12.jpg)
![Page 13: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/13.jpg)
Incentive PlanFee at risk recovered with four factors;
1-Overall client satisfaction achieved2-Final cost less than target cost3-Substantial completion achieved4-Quality meets owner standards
![Page 14: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/14.jpg)
Incentive PlanProject Savings Incentive Distribution based on the average survey score from a 20 question survey taken by the team. A sample;
-Team members demonstrate trust and respect across all levels within the Team
-Project participant's time is used wisely and productively
-Team successfully incorporates and executes Building Information Modeling for the betterment of the project.
-The project team uses LEAN principles for making project decisions that are based upon current relevant data and are for the betterment of the PROJECT.
![Page 15: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/15.jpg)
Incentive Plan
![Page 16: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/16.jpg)
Incentive Plan
![Page 17: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/17.jpg)
Incentive Plan
![Page 18: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/18.jpg)
Incentive Plan
![Page 19: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/19.jpg)
Project Budget vs. EstimateTexas Health Harris Methodist Alliance HospitalBudget Tracking1/24/2011
�$40,000,000
�$40,500,000
�$41,000,000
�$41,500,000
�$42,000,000
�$42,500,000
�$43,000,000
�$43,500,000
�$44,000,000
�$44,500,000
�$45,000,000
�$45,500,000
�$46,000,000
�$46,500,000
�$47,000,000
�$47,500,000
�$48,000,000
�$48,500,000
�$49,000,000
�$49,500,000
�$50,000,000
�$50,500,000
6/24/2010 7/19/2010 8/13/2010 9/7/2010 10/2/2010 10/27/2010 11/21/2010 12/16/2010 1/10/2011
Texas�Health�HM�Alliance�Ͳ TARGET�COSTBase�Budget Approved�Alternates Approved�Cost�Benefit�Analysis Pending�Cost�Benefit�Analysis TARGET�COST Current�Estimate
![Page 20: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/20.jpg)
Project Savings Distribution
![Page 21: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/21.jpg)
Contractual LessonsThe reward structure has to be sufficient to compensate the architect for the additional work.
The reward structure modified the architect’s behavior, but they felt that they would prefer to collaborate without the fee incentive.
Not including Structural and MEP engineers in the reward structure caused problems on the team.
Without an active and supportive owner the process will not succeed.
![Page 22: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/22.jpg)
Contractual LessonsThe waiver of liability was valuable in creating an environment of collaboration and BIM sharing.
On another project with the same owner rep and ambition, but without the contract, the collaboration has been different.
![Page 23: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/23.jpg)
Contractual Lessons
![Page 24: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/24.jpg)
Contractual Lessons
![Page 25: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/25.jpg)
LEAN Process
![Page 26: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/26.jpg)
LEAN ProcessTHR hired a Lean consultant to assist on the project. He was an Industrial Engineer with experience on refineries and industrial projects.
The processes used were;A3; suggestions fit onto an 11x17 piece of paperScorecards; the team’s monthly self-ratingPull schedule; starting at the end resultWeekly Work Plan; review tasks at the start of each week, PPC was not consistently carried out.Target value design; designing to a set budgetRetrospective; a one month review of process
![Page 27: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/27.jpg)
LEAN Process- Big Room
![Page 28: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/28.jpg)
LEAN Process
![Page 29: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/29.jpg)
LEAN Process-Promise Wall
![Page 30: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/30.jpg)
LEAN ProcessTarget Value Design
![Page 31: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/31.jpg)
LEAN ProcessTarget Value Design
Hospital building structural steel system using target value design; .05% over budget
MOB structural steel not using target based design; 8.0% over budget. Engineer was out of fee to continue meetings.
Fabricator completed the steel detailing to minimize tube and angle steel, minimizing the labor while adding slightly to the tonnage.
![Page 32: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/32.jpg)
Lean LessonsVery difficult to match the flow between architecture and construction.
Architect felt financially challenged because of the process. 25% more hours than in a traditional process, half of those hours based on owner decisions.
Architectural team found the process rewarding, architectural management not so much.
Architectural management struggled with the risk and inability to predict profit on the job.
![Page 33: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/33.jpg)
LEAN LessonsLEAN does not mesh with typical efficient architectural processes; ‘go slow to go fast’, ‘target based design’, many more meetings.
‘If I had to do this on every project we would go broke.’ P+W Associate Principal..........?
Be careful when selecting a consultant, begin by implementing a few key processes; PPC, Last Planner, Pull Scheduling.....
‘The greatest benefits accrued to the owner’
![Page 34: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/34.jpg)
Pre-fabrication Strategy
Reduction in Project Schedule– Reduction of peak manpower by leveling resources
– Significant reduction on labor (50-55%)
– Productivity loss due to weather
Quality– Controlled environment
– Repetition
– Quality control
Safety
Value Proposition for Pre-fab Strategies
![Page 35: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/35.jpg)
Pre-fabrication Strategy
MEP Corridor Racks– Typical rack length is 16 feet but total length is 20 feet
– Maximizes the use of stock length for piping, conduits, etc.
– Reduces material waste
– Work is done in somewhat controlled environment
– Work is also done at table height rather than on ladders, reduces hazards
– Prefabricating system offsite reduces the peak manpower on the project
Patient Room Headwalls– The quality of the work produced is high and consistent
– The coordination allows each system to be perfectly located on the wall
– The amount of rework is virtually eliminated
Patient Room Toilets– Finishes can be installed (ie. wall or floor tiles.)
– Coordination of everything in a toilet room is conducted resulting in consistent location of accessories, outlets, sinks, mirrors, etc.
– The efficiency of the process produces significant savings in labor
Prefabrication – What systems were targeted?
![Page 36: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/36.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 37: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/37.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 38: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/38.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 39: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/39.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 40: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/40.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 41: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/41.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 42: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/42.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 43: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/43.jpg)
MEP Corridor Racks
Pre-fabrication Strategy
![Page 44: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/44.jpg)
Patient Room Headwalls
Pre-fabrication Strategy
![Page 45: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/45.jpg)
Patient Room Headwalls
Pre-fabrication Strategy
![Page 46: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/46.jpg)
Patient Room Headwalls
Pre-fabrication Strategy
![Page 47: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/47.jpg)
Patient Room Headwalls
Pre-fabrication Strategy
![Page 48: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/48.jpg)
Patient Room Headwalls
Pre-fabrication Strategy
![Page 49: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/49.jpg)
Patient Room Headwalls
Pre-fabrication Strategy
![Page 50: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/50.jpg)
Sequence of Headwalls and Pods
Pre-fabrication Strategy
![Page 51: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/51.jpg)
Modeling – Studs with piping
Pre-fabrication Strategy
![Page 52: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/52.jpg)
Restroom Mock-Ups
Pre-fabrication Strategy
![Page 53: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/53.jpg)
Restroom pre-fabrication shop
Pre-fabrication Strategy
![Page 54: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/54.jpg)
Pre-fabrication Strategy
QntyEstimated
MH's Actual MH's MH Reduction Estimated Labor $ Actual Labor $ SavingsSavings /
Unit
Patient Rest Room 35 3,945 1,474 2,471 $96,653 $36,113 $60,540 $1,730
63%
Headwalls 28 1,700 877 823 $47,318 $21,538 $25,780 $921
48%
MEP System Racks* 35 1,120 861 259 $32,122 $24,693 $7,428 $212
23%
TOTAL: 3,553 $93,748
53%
Waste Reduction 19k lbs 9k lbs 10k lbs over 50% reduction in waste generationover 50% reduction in waste generationover 50% reduction in waste generation
![Page 55: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/55.jpg)
Baseline vs. First-Run Study vs. ActualPre-fabrication Strategy
![Page 56: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/56.jpg)
Pre-fabrication Strategy Pre-fabrication Strategy; it will be very
difficult without strong owner commitment. Implementation must start in design
– Early Approvals
– Detailed Planning
Mind shift: Construction to Manufacturing– Supply Chain
– Assemble the units do not “build them”
Coordination of Shops (Navis)
![Page 57: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/57.jpg)
Pre-fabrication Strategy Location– Warehouse
– Shipping
– Storage
Buy-out Strategy– Self Perform
– “Pod” Manufacturer
Timing!
![Page 58: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/58.jpg)
BIM in IPDSigned the AIA E202 but referred to the P+W BIM protocol for more detail.
Model is no longer primarily for 2D documentation, it is now a tool for estimating, coordination, and phasing.
Everything gets modeled, eliminate 2D content in the 3D model.
Accuracy of model is critical, floor and roof slopes modeled, walls modeled to correct height.
![Page 59: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/59.jpg)
BIM in IPDP+W agreed to follow some key BIM standards from Beck, these have now been adopted for all their projects.
![Page 60: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/60.jpg)
BIM in IPD 2.0Separation of model elements into objects that match estimating elements.
Coding all library items into cost database.
Focus on model not drawings as building tool to minimize notation.
Generating datapoints to feed directly into Trimble for layout.
Model generated by the team for the team.
![Page 61: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/61.jpg)
BIM final thoughtsBIM is not a substitute for an experienced estimator.
Without the IPD liability waiver true BIM cooperation becomes more challenging.
He/she who controls the model controls the process.
The general standard of architectural documentation is currently low, this will hurt the profession. How to get paid for higher quality?
![Page 62: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/62.jpg)
Completed Project
![Page 63: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/63.jpg)
Completed Project
![Page 64: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/64.jpg)
Completed Project
![Page 65: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/65.jpg)
Completed Project
![Page 66: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/66.jpg)
Completed Project
![Page 67: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/67.jpg)
Completed Project
![Page 68: Seminar Objectives - AGC Impact of Lean and IPD on Prefab.pdf · BIM in IPD Signed the AIA E202 but referred to the P+W BIM protocol for more detail. Model is no longer primarily](https://reader035.vdocuments.mx/reader035/viewer/2022071008/5fc63c20299831196c5e0965/html5/thumbnails/68.jpg)
Final result
Compared to the comparable building used to set the base budget, this project was;
-Delivered in three months less time.
-Cost the owner $584,000 less.
-Contained $2,500,000 of upgraded mechanical.
-Significantly upgraded design.