Day Date Work Area Roadway Lane/Shoulder Start Finish Work to Be Completed Section 1 Township of Mansfield, Burlington County Traffic slowdowns and short term road closures are subject to "weather permitting" Section 1 - Notice of Local Road Closures and Detours State Police slowdowns & escorts: MO 5/14/2012 Sect. 1, NJT Milepost 51.1 - Int. 6 Toll-North Ramp Northbound (5) 15 Min Slowdowns 10:00 PM 5:00 AM Slowdowns to repair inlets in TN Ramp TU 5/15/2012 Sect. 1, NJT Milepost 51.1 - Int. 6 Toll-North Ramp Northbound (5) 15 Min Slowdowns 10:00 PM 5:00 AM Slowdowns to repair inlets in TN Ramp Local Road & Lane Closings (Lane & road closings are subject to weather): WE 5/16/2012 Section 1, Columbus-Florence Road (Cr-543) bridge, East & West Bound Alternating traffic 7:00 PM 6:00 AM demolition work on bridge structure TH 5/17/2012 Section 1, Columbus-Florence Road (Cr-543) bridge, East & West Bound Alternating traffic 9:00 AM 3:30 PM demolition work on bridge structure Lane Closings (Lane & road closings are subject to weather): MO 5/14/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound LT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R TU 5/15/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound RT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R Notice of Construction Activity: Columbus-Florence Road (County Road 543) bridge, Mansfield Township, Burlington County, NJ. From Wed. May 16, 7PM - 6AM, & Thurs. May 17, 9AM - 3:30PM, the contractor will be demolishing a portion of the Columbus- Florence Road/CR-543 bridge over the NJ Turnpike. The road will REMAIN OPEN to alternating two-way traffic during this demolition. Jacksonville-Hedding Road Bridge, Mansfield Township, Burlington County, NJ. Effective on or about Feb. 2, 2011, the bridge over the NJ Turnpike on Jacksonville-Hedding Road will be closed for approximately 17 months for construction. Please see the Jacksonville-Hedding Road bridge detour map for more information. TU 5/15/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound RT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R MO & TU 5/14 & 5/15 Sect. 1, NJT Milepost 53.3 - Int. 6 - 50.8 Southbound LT/CTR LN 11:00 PM 6:00 AM Shielding & Overhang on SIT / ST MO - TH 5/14 - 5/17/12 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT LN 6:00 AM 4:30 PM Median Barrier Work 48.98, 49.97, and 50.39 WE 5/16/2012 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT/CTR LN 7:00 PM 6:00 AM Demo Structure 49.15R WE 5/16/2012 Sect. 1, NJT Milepost 48.4 - Int. 6 - 51.0 Northbound LT/CTR LN 7:00 PM 6:00 AM Shielding & Overhang on SIT / ST (2nd Taper @ 49.9) WE 5/16/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound LT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R TH 5/17/2012 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT/CTR LN 9:00 PM 5:00 AM Demo Structure 49.15R TH 5/17/2012 Sect. 1, NJT Milepost 48.8 - Int. 6 - 51.0 Northbound LT/CTR LN 9:00 PM 6:00 AM Shielding & Overhang on SIT / ST (2nd Taper @ 49.9) TH 5/17/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound LT/CTR LN 10:00 PM 6:00 AM Demo Structure 49.15R FR 5/18/2012 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT LN 6:00 AM 2:00 PM Median Barrier Work 48.98, 49.97, and 50.39 FR & SU 5/18 & 5/20 Sect. 1, NJT Milepost 53.3 - Int. 6 - 50.8 Southbound LT/CTR LN 11:59 PM 6:00 AM Shielding & Overhang on SIT / ST (2nd Taper @ 52.2)

Upload: others

Post on 03-Feb-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Day Date Work Area Roadway Lane/Shoulder Start Finish Work to Be Completed

Section 1 Township of Mansfield, Burlington County

Traffic slowdowns and short term road closures are subject to "weather permitting"

Section 1 - Notice of Local Road Closures and Detours

State Police slowdowns & escorts:

MO 5/14/2012 Sect. 1, NJT Milepost 51.1 - Int. 6 Toll-North Ramp Northbound (5) 15 Min Slowdowns 10:00 PM 5:00 AM Slowdowns to repair inlets in TN Ramp

TU 5/15/2012 Sect. 1, NJT Milepost 51.1 - Int. 6 Toll-North Ramp Northbound (5) 15 Min Slowdowns 10:00 PM 5:00 AM Slowdowns to repair inlets in TN Ramp

Local Road & Lane Closings (Lane & road closings are subject to weather):

WE 5/16/2012 Section 1, Columbus-Florence Road (Cr-543) bridge, East & West Bound Alternating traffic 7:00 PM 6:00 AM demolition work on bridge structureTH 5/17/2012 Section 1, Columbus-Florence Road (Cr-543) bridge, East & West Bound Alternating traffic 9:00 AM 3:30 PM demolition work on bridge structure

Lane Closings (Lane & road closings are subject to weather):

MO 5/14/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound LT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R

TU 5/15/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound RT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R

Notice of Construction Activity: Columbus-Florence Road (County Road 543) bridge, Mansfield Township, Burlington County, NJ. From Wed. May 16, 7PM - 6AM, & Thurs. May 17, 9AM - 3:30PM, the contractor will be demolishing a portion of the Columbus-Florence Road/CR-543 bridge over the NJ Turnpike. The road will REMAIN OPEN to alternating two-way traffic during this demolition.

Jacksonville-Hedding Road Bridge, Mansfield Township, Burlington County, NJ. Effective on or about Feb. 2, 2011, the bridge over the NJ Turnpike on Jacksonville-Hedding Road will be closed for approximately 17 months for construction. Please see theJacksonville-Hedding Road bridge detour map for more information.

TU 5/15/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound RT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R

MO & TU 5/14 & 5/15 Sect. 1, NJT Milepost 53.3 - Int. 6 - 50.8 Southbound LT/CTR LN 11:00 PM 6:00 AM Shielding & Overhang on SIT / ST

MO - TH 5/14 - 5/17/12 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT LN 6:00 AM 4:30 PM Median Barrier Work 48.98, 49.97, and 50.39

WE 5/16/2012 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT/CTR LN 7:00 PM 6:00 AM Demo Structure 49.15R

WE 5/16/2012 Sect. 1, NJT Milepost 48.4 - Int. 6 - 51.0 Northbound LT/CTR LN 7:00 PM 6:00 AM Shielding & Overhang on SIT / ST (2nd Taper @ 49.9)

WE 5/16/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound LT/CTR LN 8:00 PM 7:00 AM Demo Structure 49.15R

TH 5/17/2012 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT/CTR LN 9:00 PM 5:00 AM Demo Structure 49.15R

TH 5/17/2012 Sect. 1, NJT Milepost 48.8 - Int. 6 - 51.0 Northbound LT/CTR LN 9:00 PM 6:00 AM Shielding & Overhang on SIT / ST (2nd Taper @ 49.9)

TH 5/17/2012 Sect. 1, NJT Milepost 51.1 - 49.0 Southbound LT/CTR LN 10:00 PM 6:00 AM Demo Structure 49.15R

FR 5/18/2012 Sect. 1, NJT Milepost 48.4 - 50.5 Northbound LT LN 6:00 AM 2:00 PM Median Barrier Work 48.98, 49.97, and 50.39

FR & SU 5/18 & 5/20 Sect. 1, NJT Milepost 53.3 - Int. 6 - 50.8 Southbound LT/CTR LN 11:59 PM 6:00 AM Shielding & Overhang on SIT / ST (2nd Taper @ 52.2)