Seattle Design Commission
September 6, 2012
![Page 2: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/2.jpg)
“Foundation” of the Waterfront Program
2
![Page 3: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/3.jpg)
Seawall Project Area
Central Waterfront Team
![Page 4: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/4.jpg)
Current Project Schedule
![Page 5: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/5.jpg)
2012 2013 2014 2015 2016
Project Milestones
Environmental Process
Design Development
GC/CM Procurement
Construction
Construction begins
Start final
design
60% 100%
Construction complete
Permits received DEIS Public notice
NTP
Pre-construction
![Page 6: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/6.jpg)
Project Purpose and Need
![Page 7: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/7.jpg)
• Reduce the risks of coastal
storm and seismic damages
• Protect public safety, critical
infrastructure, and associated
economic activities along
Seattle’s central waterfront
• Improve the degraded
ecosystem functions and
processes of the Elliott Bay
nearshore in the vicinity of the
existing seawall
Project Purpose
![Page 8: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/8.jpg)
Sample Seawall Cross-Section
Type B
Seawall
(Madison
to Union)
![Page 9: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/9.jpg)
Seawall Location: Eastern Extent
Type A
Seawall
(Union to
Broad) 9
![Page 10: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/10.jpg)
Structural Elements of the Wall
Relieving
Platform
Soil
Wall
![Page 11: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/11.jpg)
Seawall Repairs and Vulnerability
1954 failure, Clay Street
(above/at right)
2002 relieving platform
repairs (to right)
![Page 12: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/12.jpg)
Result of a Seawall Failure
![Page 13: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/13.jpg)
What’s at Risk?
• Public safety
• Transportation corridor
• Critical utilities
• Residential and commercial
structures
• Public recreation
• Tourism and local attractions
• Seattle’s front porch
![Page 14: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/14.jpg)
• Migratory corridor
– Depth
– Light
• Nearshore ecosystem productivity
– Aquatic and riparian vegetation
– Macroinvertebrates
– Substrate diversity
Degraded Nearshore Habitats
![Page 15: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/15.jpg)
• Salmon
• Trout
• Puget Sound Rockfish
Threatened and Endangered Species
![Page 16: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/16.jpg)
Developing Alternatives
![Page 17: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/17.jpg)
Public Engagement Themes
• For those most affected, the project is well-known and they
are ready to get construction started
• Seize the habitat opportunity by using innovative and
science-based enhancements
• Maintain a responsible project budget
• Create more physical access to water and public gathering
space
• Maintain transportation routes, including continuous non-
motorized pathways
• Consider construction impacts to businesses and tourism
• Preserve historical and cultural significance
![Page 18: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/18.jpg)
Recommended Design Features
• Face of wall: 10-15 feet inland
• Soil stabilization with jet grouting
• Continuous migration corridor and nearshore restoration
• Restored Alaskan Way and pedestrian/bicycle facilities
• Early program wins
![Page 19: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/19.jpg)
Soil Stabilization: Jet Grouting
• Standards – 1,000 year seismic event
– 75-year design life
• Structure – Directly addresses soil
liquefaction problem
• Time – Potentially faster
construction
• Cost – Lower than other options
![Page 20: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/20.jpg)
Potential Habitat
Enhancements
• New seawall
• Intertidal corridor
• Lighting
• Riparian vegetation
• Textured wall
• Substrate
enhancement
• Cobble reefs
Potential Habitat Enhancement Measures
![Page 21: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/21.jpg)
Existing – Zone 1
![Page 22: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/22.jpg)
Proposed – Zone 1
![Page 23: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/23.jpg)
Existing – Zone 1
![Page 24: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/24.jpg)
Proposed – Zone 1
15’
![Page 25: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/25.jpg)
Existing – Zone 2
![Page 26: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/26.jpg)
15’
Proposed – Zone 2
![Page 27: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/27.jpg)
Existing – Zone 3
![Page 28: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/28.jpg)
Proposed – Zone 3
10-15’
![Page 29: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/29.jpg)
Existing – Zone 4
![Page 30: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/30.jpg)
Proposed – Zone 4
10’
![Page 31: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/31.jpg)
Existing – Zone 4
![Page 32: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/32.jpg)
Proposed – Zone 4
10’ 10’
![Page 33: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/33.jpg)
Breakdown of 35% Cost Estimate
Design and Environmental
16%
Soil Stabilization
72%
Ecosystem Restoration
4% Roadway and Access
8%
7/30/2012
Phase 1 Cost: $300M
![Page 34: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/34.jpg)
Delivering Final Design
![Page 35: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/35.jpg)
Key Design and Cost Questions after 35%
Structural:
Do we have the most streamlined, elegant structure, with few redundant elements?
Work sequence:
Can we maximize access and minimize impact for:
• Businesses
• Users
• Environment
• Utilities
![Page 36: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/36.jpg)
Moving to Final Design
35% Design Preliminary Approach to Final Design
![Page 37: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/37.jpg)
Design Team Organization
![Page 38: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/38.jpg)
Systems Approach
• Waterfront vision
• Transportation
• Seawall structure
• Utilities
• Habitat
• Public realm
![Page 39: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/39.jpg)
Defining the Public Realm
![Page 40: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/40.jpg)
Zones 1 & 2: Washington St & Colman Dock
![Page 41: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/41.jpg)
Zone 1 – Plan View
![Page 42: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/42.jpg)
Zone 1 – Cross Section
![Page 43: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/43.jpg)
Zone 3: Historic Piers
![Page 44: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/44.jpg)
Outfalls and Habitat Benches
![Page 45: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/45.jpg)
Light Penetrating Surfaces (LPS)
Glass blocks Glass plank panels
Solar tubes Grating
![Page 46: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/46.jpg)
Zone 4: Seattle Aquarium
![Page 47: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/47.jpg)
Zone 4 – Plan View
![Page 48: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/48.jpg)
Zone 4 – Cross Section
![Page 49: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/49.jpg)
Upcoming Fall Events and Outreach
• Light penetrating surfaces
study on Pier 62/63
• Habitat/fish migration
studies
• Habitat education
• Fairs, festivals, events
• Briefings
• Collaboration with
Waterfront Seattle activities
![Page 50: Seattle Design Commission September 6, 2012 · 2015. 1. 7. · September 6, 2012 “Foundation” of the Waterfront Program 2 . Seawall Project Area ... 7/30/2012 Phase 1 Cost: $300M](https://reader033.vdocuments.mx/reader033/viewer/2022051922/600fa68ba5d6e354a1175485/html5/thumbnails/50.jpg)
Contact Information
• Email: [email protected]
• Website: http://www.seattle.gov/transportation/seawall.htm
• Phone: Jennifer Wieland, SDOT: 206-733-9970
50