seaonc presentation
DESCRIPTION
Vibration pile geoTRANSCRIPT
![Page 1: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/1.jpg)
1
AN INTRODUCTION TO BUILDING FOUNDATIONS AND SOIL IMPROVEMENT METHODS
SEAONC 2008 Spring SeminarSan Francisco, 16 April 2008
Hadi J. Yap, PhD, PE, GE
![Page 2: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/2.jpg)
2
General Foundation Types
• Shallow Foundations– Spread footings: isolated, continuous– grid or waffle– Post-Tensioned Slabs (PT Slabs)– Mats
• Deep Foundations
![Page 3: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/3.jpg)
3
Factors to be Considered in Selecting Foundation Type
• Subsurface conditions• Column loads and spacing, basements• Site constraints
– noise– vibrations– proximity to existing improvements, slope, channel
• Economics
![Page 4: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/4.jpg)
4
Shallow Foundations
• Suitable where underlying material is strong
• Can be used in engineered fill if building load is light to moderate
• Mats can be used to span localized weak areas
• Mats can be used on weaker soil for structure with basements where net load (weight of structure minus weight of soil removed) is low
![Page 5: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/5.jpg)
5
Sources of Settlement• Immediate Settlement (sand and clay)
Occurs as the load is applied• Consolidation (saturated clay)
A slow process of squeezing water out of the pores in soft clay when loaded
• Liquefaction (saturated sand) Temporary loss of shear strength in loose sand due to a rise in excess pore water pressure during cyclic loading such as seismic
• Seismic Densification (dry/moist sand)Densification of loose sand above the groundwater level due to ground shaking
![Page 6: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/6.jpg)
6
Total and Differential Settlement
• Building can tolerate large total settlement if the differential settlement is within tolerable limits
• Where the total settlement is large, flexible connections should be provided to underground utilities where they enter the building
![Page 7: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/7.jpg)
7
Allowable Differential Settlement for Buildings
Angular Distortion = Differential settlement/Distance
Angular Distortion Limits (Bjerrum, 1963):
• 1/500 – safe limit where cracking is not permissible• 1/300 – limit where first cracking in panel walls is to
be expected• 1/150 – limit where structural damage to general
buildings is to be feared
![Page 8: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/8.jpg)
8
Design Parameters for Spread Footings
• Minimum width• Minimum embedment depth• Allowable bearing pressure• Allowable passive pressure• Allowable base friction coefficient
![Page 9: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/9.jpg)
9
Spread Footing Excavations
![Page 10: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/10.jpg)
10
When mat is to be considered
• When total footprint area of spread footings is more than, say, 50% of building footprint
• To reduce total and differential settlement
• To bridge areas of weak subgrade
![Page 11: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/11.jpg)
11
Design Parameters for Mat Foundations
• Minimum embedment depth • Allowable bearing pressures• Allowable passive pressure• Allowable base friction coefficient• Subgrade modulus
![Page 12: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/12.jpg)
12
Mat Subgrade and Mud Slab
![Page 13: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/13.jpg)
13
Mat Rebars
![Page 14: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/14.jpg)
14
Deep Foundation Types
• Drilled Piers/Cast-In-situ-Drilled-Hole [CIDH] Piles
• Driven Piles (Concrete, Steel H)• Tubex Piles• Auger Cast Piles• Torque Down Piles• Micropiles
![Page 15: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/15.jpg)
15
Drilled Piers
• Can use one large diameter pier in lieu of several smaller, driven piles
• Lengths can be adjusted in the field – reduce waste/build-up
• Derive axial capacity mainly from skin friction• Need to use casing and/or drilling fluid if
groundwater and/or loose soil is present
![Page 16: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/16.jpg)
16
Drilled Pier Installation
![Page 17: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/17.jpg)
17
Driven Precast, Prestressed, Concrete Piles
• Economical in San Francisco Bay Area
• Can be used where soft soil, non-engineered fill, or high groundwater level, is present
• Fabricated at yard – good quality control
• Moderately high capacity – up to 344 kips for 14”square piles using 6,000 psi concrete
![Page 18: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/18.jpg)
18
Concrete and Steel Piles
![Page 19: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/19.jpg)
19
Driven Steel H-Piles• More expensive than driven concrete piles• Suitable where depth to bearing soil layer
varies; can conveniently be cut and spliced• Design must consider corrosion• Moderate to high capacity – up to 456 kips
for HP14X89 using 50 ksi steel• Lateral resistance varies with load direction
relative to pile axis
![Page 20: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/20.jpg)
20
Soil Improvement
If poor soil conditions are encountered:
• Bypass poor soil, use deep foundations• Remove poor soil, replace with engineered fill• Improve soil properties in place
![Page 21: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/21.jpg)
21
Factors to be Considered in Selecting Soil Improvement Method
• Soil type; fines content (silt- and clay-size)• Area and depth of treatment• Soil properties – strength, compressibility• Proposed structure and settlement criteria• Availability of skills, equipment, materials• Adjacent improvements• Economics
![Page 22: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/22.jpg)
22
Primary objectives of soil improvement
CLAY– Increase bearing capacity or slope stability– Reduce foundation settlement
SAND- Reduce liquefaction potential- Increase bearing capacity- Reduce foundation settlement
![Page 23: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/23.jpg)
23
Mechanisms of Soil Improvement for Clay
• Consolidation- Preloading
• Reinforcement- Soil-Cement Columns- Vibro-Replacement Stone Columns- Geopiers® and Vibro Piers™
• Mixing- Soil-cement columns
![Page 24: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/24.jpg)
24
Mechanisms of Soil Improvement for Sand• By vibration
– Impacts at surface: Dynamic compaction– Depth vibrator: Vibro-compaction
• By vibration and displacement of backfill- Vibro-replacement stone columns- Vibro Piers™
• By displacement of backfill material- Compaction grouting
• By binding particles- Permeation grouting (e.g. ultra-fine cement)
• By mixing– Soil-cement columns
![Page 25: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/25.jpg)
25
Soil Improvement Methods
XPermeation GroutingXCompaction GroutingXXGeopiers® and Vibro Piers™XXStone ColumnsXVibro-CompactionXXSoil-Cement ColumnsXDynamic Compaction
XPreloading
SandClayMethod
![Page 26: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/26.jpg)
26
Preloading
• Performed by placing fill over soft clay• Improve foundation soil for buildings,
embankments, runways, bridge abutments• Type of preloads: earth fill, water, vacuum • Use prefabricated vertical (wick) drains to
reduce preloading time • Wick drains: plastic core wrapped in
geotextile; generally 4” wide and 1/8” to 3/8”thick
![Page 27: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/27.jpg)
27
Wick Drain Installation
![Page 28: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/28.jpg)
28
Preloading (cont’d)• Typical wick drain spacing is 3 to 6 feet,
depending on soil permeability and time available
• Typical preloading period is 3 to 6 months, depending on soil permeability and degree of consolidation to be achieved
• Construction monitoring: settlement (settlement plates/probes), pore water pressure (piezometers), lateral movement (inclinometers)
![Page 29: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/29.jpg)
29
Source: ASCE, Geotechnical Special Publication No. 69, 1997
Preloading with Wick Drains and Instrumentation
![Page 30: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/30.jpg)
30
Dynamic Compaction• Involves repeated dropping of heavy weights
onto ground surface• Effective for sand, waste, and rubble fills• Pounders: concrete blocks, steel plates, or
thick steel shells filled with concrete/sand• Typical weight of pounders: 6 to 30 tons,
depending on the depth of soil to be improved
• Typical drop heights: 40 to 100 feet
![Page 31: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/31.jpg)
31
Dynamic CompactionSource: Hayward Baker
![Page 32: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/32.jpg)
32
Dynamic Compaction (cont’d)
• Most effective for soil with less than 25% fines (silt- and clay-size particles; material passing #200 sieve [0.075 mm opening])
• Typical improvement depth is 10 to 30 feetD ≈ 0.5 √(WH)
where:D = improvement depth in mW = pounder weight in metric tonH = drop height in m
![Page 33: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/33.jpg)
33
Dynamic Compaction (cont’d)
• Ground Vibrations< 0.5 inch/sec to prevent cracks in walls< 2.0 inch/sec to prevent structural damage
• Construction monitoring– Induced settlement– Ground vibration– Ground heave – Pore water pressure– Verification testing (SPT, CPT)
![Page 34: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/34.jpg)
34
Scaled Energy Factor versus Particle Velocity
Source: FHWA, Dynamic Compaction, 1995
![Page 35: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/35.jpg)
35
Soil-Cement Columns• Mixing in-situ soil with cementitious materials using
mixing shafts consisting of auger cutting heads, auger flights, or mixing paddles
• Produce soil-cement columns with higher strength, lower compressibility, and lower permeability than the native soil
• Used to improve bearing capacity and slope stability, and as shoring walls
• Typical compressive strength of cylinders ranges from 15 to 300 psi
• Typical permeability of mix ranges from 10-6 to 10-7
cm/sec
![Page 36: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/36.jpg)
36
Soil-Cement ColumnInstallation
![Page 37: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/37.jpg)
37
Soil-Cement Shoring Wall
![Page 38: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/38.jpg)
38
Soil-Cement Wall Installation
![Page 39: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/39.jpg)
39
Steel Beam Installation
![Page 40: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/40.jpg)
40
Vibro-Compaction
• Densifying granular soil by inserting a vibrating probe into the ground
• Probe spacing ranges from 6 to 14 feet• Suitable for sand with less than 15% fines (silt- and
clay-size particles) • Vibrator is a torpedo shaped horizontally vibrating
probe, 10 to 15 feet long, and weighs about 2 tons. The probe penetrates to the design depth under its own weight assisted by water jetting
![Page 41: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/41.jpg)
41
Vibrator and Water Jets
![Page 42: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/42.jpg)
42
Vibro-Compaction (cont’d)
• The action of vibrator and water jetting reduce inter-granular forces between soil particles allowing them to become denser
• The vibrator starts at the bottom of the hole and raised to treat the next interval; the procedure is repeated as backfill sand is added
• If backfill is not added, craters with diameters of 10 to 15 feet can form around vibrator
![Page 43: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/43.jpg)
43
Vibro-Replacement Stone Columns
• Extends the range of soil types that can be improved to silt and clay
• The probe is penetrated to design depth and gravel/crushed rock is placed in the hole as the probe is withdrawn in vertical increments of 2 to 5 feet
• A stone column is formed with the stone laterally compacted against the surrounding soil
![Page 44: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/44.jpg)
44
Vibro-Replacement Stone Columns (Cont’d)
• Three primary methods– Wet, top feed method: hole is saturated with
jetting water – Dry, top feed method: hole formed by probe
remains open without water– Dry, bottom feed: stone backfill is fed through a
hopper and tube to the bottom of the hole• Construction Monitoring
– Settlement and ground heave– Amount of stone backfill used– Verification testing (SPT, CPT)
![Page 45: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/45.jpg)
45
Wet Top Feed MethodSource: Bauer
![Page 46: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/46.jpg)
46
Dry Bottom Feed Method
![Page 47: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/47.jpg)
47
Geopiers® (Rammed Aggregate Piers)
• Locally installed by Farrell Design-Build Company• Typically 24 to 36 inches in diameter and 6 to 30 feet
deep, constructed by drilling and ramming crushed rock in 12-inch lifts
• The ramming equipment consists of excavators equipped with 2,000 to 4,000 lbs hydraulic hammers with beveled tampers
• The ultimate bearing capacity of a pier ranges from 100 to 300 kips in compression and 100-150 kips in uplift (with steel anchor). Allowable bearing capacity range from 5 to 8 ksf
![Page 48: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/48.jpg)
48
Completed Geopiers®
![Page 49: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/49.jpg)
49
Geopiers®
![Page 50: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/50.jpg)
50
![Page 51: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/51.jpg)
51
Vibro Piers™• Installed using displacement and vibratory energy to
depths of 10 to 30 feet by Hayward Baker• Installation methods:
– Dry top feed method: stone is placed in pre-augered hole, densified in 6 to 12-inch lifts with a vibrator
– Dry bottom feed method: for high groundwater level. The vibrator with tremie pipe attachment are penetrated to the design depth to install and densify the stone in place. Little or no waste results from this method.
![Page 52: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/52.jpg)
52
Dry Top Feed Method
Source: Hayward Baker Inc.Dry Bottom Feed
![Page 53: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/53.jpg)
53
Compaction Grouting
• To compact loose soil or to produce control displacement to lift structure
• Involves injection of low-slump (less than 2 inches) grout (soil-cement mixture) which does not enter soil pores but remain in a homogeneous mass
• Grout material may consist of fine sand mixed with 12% cement and water to produce stiff, mortar-like mixture
• Grout pipe is installed to maximum treatment depth and grout is injected at high pump pressure as the pipe is withdrawn incrementally, forming a column of interconnected grout bulb
![Page 54: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/54.jpg)
54
Compaction Grouting
![Page 55: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/55.jpg)
55
Compaction Grouting (cont’d)
• Can be performed “stage down” or, more commonly, in a “stage up” process, as follows:– Advancing the grout pipe to the bottom of
treatment depth– Injecting the grout until refusal criteria is
achieved, based on injected grout volume, injection pressure, or ground heave
– Extracting the grout pipe to the next depth interval and injecting the grout
– Repeat the process until reaching the upper limit of treatment zone
![Page 56: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/56.jpg)
56
Compaction Grouting
Source: Hayward Baker
![Page 57: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/57.jpg)
57
Compaction Grouting (cont’d)
• Construction monitoring:– Injected grout volume– Pressure loss/ground surface heave– Verification testing: pre- and post-grouting
SPT/CPT
![Page 58: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/58.jpg)
58
Ultra-Fine Cement Grouting
• Uses micro-fine cement (particle size ranges from 1 to 10 microns); can penetrate fine sand
• Used to increase bearing capacity of sand under existing footings and/or reduce potential settlement
• Can be used to retain shallow excavation in loose sand
• Unconfined compressive strength can exceed 100 psi
![Page 59: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/59.jpg)
59
Ultra-Cement Grouting
![Page 60: SEAONC Presentation](https://reader031.vdocuments.mx/reader031/viewer/2022020311/577cc5a01a28aba7119ce5f3/html5/thumbnails/60.jpg)
60
Elevator Pit Excavation