1 DAVID PARR MEng CEng MICE MSc MAPM Director ROSS MCWHA MEng CEng MICE Design Manager PIANC PRESENTATION SEAFORTH PASSAGE PORT OF LIVERPOOL

Upload: lamhanh

Post on 28-Aug-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

1

DAVID PARR MEng CEng MICE MSc MAPM

Director

ROSS MCWHA MEng CEng MICE

Design Manager

PIANC

PRESENTATION

SEAFORTH PASSAGE

PORT OF LIVERPOOL

2

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

60 Million tonnes of cargo per annum

16,000 Shipping movements annually

UK’s Second largest port operator

MERSEY PORTS MASTER PLAN - 20 YEAR STRATEGY FOR GROWTH

3

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING RIVER MERSEY

LIVERPOOL

ROYAL SEAFORTH CONTAINER TERMINAL

GLADSTONE DOCK

SEAFORTH PASSAGE

SEAFORTH DOCK

Seaforth Docks constructed in early 1970’s

Impounded dock with access from Mersey via Gladstone Lock

ROYAL SEAFORTH DOCKS – LOCATION & HISTORY

4

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

RIVER MERSEY

ROYAL SEAFORTH DOCKS – LOCATION & HISTORY

SEAFORTH DOCK

RSCT

SEAFORTH PASSAGE

GLADSTONE LOCK

GLADSTONE DOCK

5

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

INTRODUCTION

STAGE 1 TENDER

STAGE 2 TENDER

ENABLING WORKS

CONTRACT

FINAL

PRICE

CONSTRUCTION CONTRACT

TENDER PROCESS & PROCUREMENT

6

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

ENABLING

CONTRACT

ASSET

CONDITION

SURVEY

INVESTIGATE

SERVICES AND

STRUCTURES

CHECK

CONDITION OF

EXISTING

SIPHON

GROUND

INVESTIGATION

STAKEHOLDER

CONSULTATION

FURTHER

DESIGN &

VALUE

ENGINEERING

SEAFORTH PASSAGE WIDENING ENABLING CONTRACT

7

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

40m

BACKGROUND –

Port of Liverpool – Royal Seaforth Container Terminal

40m

CONTRACT DETAILS

8

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

BACKGROUND –

Port of Liverpool – Royal Seaforth Container Terminal

20m 40m

CLIENT: PEEL PORTS

CONTRACT: NEC OPTION A

VALUE: £11M

PROGRAMME: NOVEMBER 2013 – AUGUST 2015

CONTRACT DETAILS

9

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

ORGANISATION

10

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 1 – SECTOR GATE REMOVAL

PHASE 2 – SIPHON EXTENSION

PHASE 3 – SERVICES U TUBE

PHASE 4 – MAIN COMBI WALL

PHASE 5 – DEMOLITION

KEY PHASES

11

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 1 –SECTOR GATE REMOVAL

SECTOR GATE

12

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 1 –SECTOR GATE REMOVAL

13

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

18m

30m

25m

PHASE 1 –SECTOR GATE REMOVAL

• TOTAL WEIGHT = 420T

• BURIED IN 11m OF SILT

• SILT REMOVED VIA AIRLIFT AND SILT PUMPS

14

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

Stage 2: Sector Gate Removal

PHASE 1 –SECTOR GATE REMOVAL

• 3D MODEL BUILT FROM RECORD DRAWINGS TO PLAN DEMOLITION

• GATE CUT AND REMOVED IN 6 SECTIONS RANGING FROM 40-160T

• BRONCO OXY CUTTING USED FOR MAJORITY OF CUTS

• FINAL CUTS COMPLETED REMOTELY USING SHAPED CHARGES

• TEMPORARY WORKS INSTALLED TO SECURE GATE

15

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 1 –SECTOR GATE REMOVAL

16

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 1 –SECTOR GATE REMOVAL

17

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 2 – SIPHON EXTENSION

3m DIAMETER SEWER

SIPHON BELOW PASSAGE

18

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 2 – SIPHON EXTENSION

20m EXTENSION AND TIE-INS

REQUIRED TO FACILITATE

INSTALLATION OF MAIN WALL

19

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

EXISTING SEAFORTH

PASSAGE SILL FLOOR

= - 6m CD

25

m

de

ep

PHASE 2 – SIPHON EXTENSION

EXISTING 3m DIAMETER SIPHON

NEW RC UPSHAFT

PROPOSED 3m DIAMETER EXTENSION

20

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 2 – SIPHON EXTENSION

EXISTING RC DIAPHRAGM WALLS

TEMPORARY DIVERSION CHANNEL

COFFERDAM

21

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 2 – SIPHON EXTENSION

22

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 2 –SIPHON EXTENSION – LINER PIPE

23

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 3 – SERVICES U TUBE

ROUTE OF EXISTING SERVICE

CULVERT AND LINK DUCT

UNDER PASSAGE

24

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 3 – SERVICES U TUBE

PROPOSED U TUBE

DIVERSION ROUTE

25

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 3 – SERVICES U TUBE

COMPLETED U TUBE

DIVERSION ROUTE

COMPLETION OF DIVERSION PERMITS

INSTALLATION OF MAIN WALL

26

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

63m Straight

Section

11m Western

Vertical Bend

12m Western

Vertical Riser

15m Eastern

Vertical Riser

9.5m Eastern

Horizontal Bend

11m Eastern

Vertical Bend

120m LONG

1020mm DIAMETER

TOTAL WEIGHT = 97.5T

PHASE 3 – SERVICES U TUBE

27

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

SERVICES WITHIN U-TUBE:

EXISTING NETWORK:

• 11kV HV RING

• FIBRE OPTIC/COMMS

• LV AND DOCK LEVELLER

• WATERMAIN

FUTURE PROVISION:

• 33kV HV RING

• ASSOCIATED FIBRE OPTICS AND COMMS

PHASE 3 – SERVICES U TUBE

28

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 3 – SERVICES U TUBE

STAGE 1 PRE-FABRICATION ON WEST ALEXANDRA DOCK

WEST ALEXANDRA DOCK

SEAFORTH PASSAGE

29

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

U-Tube Fabrication and Installation Overview PHASE 3 – SERVICES U TUBE

STAGE 2 ROTATION THROUGH 90 DEGREES

Youtube Link: https://www.youtube.com/watch?v=SdDWgSNcN8M

30

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

U-Tube Fabrication and Installation Overview PHASE 3 – SERVICES U TUBE

STAGE 3 U TUBE POSITIONED

31

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

TRENCH EXCAVATED IN MARCH 2014

EXCAVATED EARLY TO UTILISE 200T

BACKHOE DREDGER – CAPABLE OF

EXCAVATING TO THE FULL 19m DEPTH

4000m3 OF MATERIAL REMOVED IN 3 DAYS

SILT FLOWED INTO TRENCH AS HARD

MATERIAL WAS EXCAVATED

PHASE 3 – SERVICES U TUBE

32

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

TRENCH EXCAVATED TO - 8.8m CD

PHASE 3 – SERVICES U TUBE TRENCH EXCAVATED MARCH 2014

33

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 3 – SERVICES U TUBE

TRENCH SILTED TO - 6.0m CD

34

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 4 – MAIN COMBI WALL

COMBI WALL

35

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 4 – MAIN COMBI WALL

ANCHOR WALL

36

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 4 – MAIN COMBI WALL

TIE RODS

37

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 4 – MAIN COMBI WALL

COPE

38

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

20m

40m

PHASE 5 – DEMOLITION

39

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

PHASE 5 – DEMOLITION

VOLUME TO BE REMOVED 20,000m3

EXISTING QUAY LEVEL + 13m CD

WATER LEVEL + 10m CD

CUT OFF LEVEL - 6.5m CD

COMPLETION SUMMER 2015

40

INTRODUCTION

ENABLING

DELIVERY

TENDER

SEAFORTH

PASSAGE

WIDENING

[email protected]

[email protected]

www.farrans.com