2012/6/14 2
Purpose
2012/6/14 2
You are expected to master the following
knowledge after this course:
Know how to make preparations for UMTS SDR
commissioning
Get familiar with data configuration of UMTS
SDR
Get familiar with UMTS SDR version
management
Know the standard workflow of commissioning
Note: the interfaces may be different for different
software versions.
内部公开 Internal Only▲
Contents
Introduction
Preparations
Power-on Check
Data Configuration and Version Management
Test after Commissioning
内部公开 Internal Only▲
UMTS SDR commissioning procedure
Preparations
Start
Install LMT
Need to
upgrade
NodeB version
Power on/off
equipment
End
No need to
upgrade
NodeB version
Online logonUpgrade LMT
version
Configure all
tables
Iub interface
integration
Service
verification
Configure data
offline
内部公开 Internal Only▲
General cares in commissioning
1. Anti-static protection: please wear anti-static wrist strap
when checking equipment.
2. Please follow the instructions described in engineering
specifications to perform operations on modules. For
redundant modules, please pack them with anti-static bags.
3. The engineers participating UMTS SDR commissioning
must get the following documents at least:
****** represents SDR type, such as B8200+R8840, BS8800
and BS8900.
ZXSDR ****** Installation Manual.pdf
ZXSDR ****** O&M Manual.pdf
ZXSDR ****** Commissioning and Configuration Manual.pdf
ZXSDR ****** Hardware Manual.pdf
ZXSDR ****** Technical Manual.pdf
内部公开 Internal Only▲
Contents
Introduction
Preparations
Power-on Check
Data Configuration and Version Management
Test after Commissioning
内部公开 Internal Only▲
UMTS SDR commissioning preparation flow
Get information (sites for commissioning and contacts)
Get information about equipment configuration and networking
Prepare spare parts, tools and technical documents required for commissioning
Estimated time
Contact the person in charge to decide when to start
内部公开 Internal Only▲
Preparing tools
Prepare software
Prepare documents
Data configuration
Preparations for UMTS SDR Commissioning
内部公开 Internal Only▲
UMTS SDR commissioning preparations - tools
PC configuration requirements: CPU main frequency: PIII 800 or higher
Memory > 256MB;
Hard disk > 10GB;
OS: Windows XP professional
Others
Screwdriver, power socket and
multi-meter
内部公开 Internal Only▲
UMTS SDR commissioning preparations - software
LMT software – match to the SDR version
SDR software package
内部公开 Internal Only▲
UMTS SDR commissioning preparations - documents
Installation acceptance report (ensure the
installation has been completed and passed
the acceptance)
Unpacking acceptance report (ensure
boards and all hardware equipment are
available)
内部公开 Internal Only▲
UMTS SDR commissioning preparations - data
Node B configuration file, for example:
SDR No-IP S101 B1001.xml
内部公开 Internal Only▲
Contents
Introduction
Preparations
Power-on Check
Data Configuration and Version Management
Test after Commissioning
内部公开 Internal Only▲
Checking boards
Checking input
power supply
Checking cable
connection
Start
Check
the in
ternal
jum
per sw
itch o
f the
SA
Check
the in
ternal
jum
per sw
itch o
f oth
er
board
s
Check
ing co
nnectio
n
of L
MT
Check
ing co
nnectio
n
of Iu
b in
terface
Power on/off
equipment
End
Check
ing co
nnectio
n
of rack
s
Power-on procedure
内部公开 Internal Only▲
UMTS SDR power-on check
Checking boards
Checking input power supply
Checking cable connections
Power-on the equipment
内部公开 Internal Only▲
Check whether the SDR has been configured with the
right quantity of boards as planned.
Check whether boards have been inserted into the
correct slots.
Check the internal jumper DIP switch of the SA board
Power-on procedure – checking boards
X5 jumper status [3, 2] Mode
[open circuit, open circuit] Uplink short cable, downlink short cable
[short circuit, short circuit] Uplink long cable, downlink long cable
[open circuit, short circuit] Uplink short cable, downlink long cable
[short circuit, open circuit] Uplink long cable, downlink short cable
内部公开 Internal Only▲
Power-on procedure – checking boards
X6 jumper status [2, 1, 0] BBU Cabinet No.
[open circuit, open circuit, open circuit] 0
[open circuit, open circuit, short circuit] 1
[open circuit, short circuit, open circuit] 2
[open circuit, short circuit, short circuit] 3
[short circuit, open circuit, open circuit] 4
[short circuit, open circuit, short circuit] 5
[short circuit, short circuit, open circuit] 6
[short circuit, short circuit, short circuit] 7
X5 jumper status [1, 0] E1/T1 mode
[short circuit, short circuit] Reserved
[short circuit, open circuit] T1, 100 Ω
[open circuit, short circuit] E1, 120 Ω
[open circuit, open circuit] E1, 75 Ω (by default)
内部公开 Internal Only▲
Check whether the polarities of the power supply are
correctly connected.
Check whether the input power range of the DC power
cabinet is within the range of - 40VDC - -57VDC.
If 220V-AC power supply is adopted, B8200 must be
used together with the PSU. Check whether the single-
phase voltage is within the range of 200V AC – 240V AC,
and whether the frequency is span is within the range of
47 Hz – 53 Hz.
Power-on procedure – check input power supply
内部公开 Internal Only▲
Power-on procedure – check cable connection
If fibers are used for the Iub interface connection, check whether fibers are correctly connected from RNC and B8200 to the CC board.
If E1 cables are used for the Iub interface connection, check whether the E1 cables between the DDF and B8200 are correctly connected.
If FE cables are used for the Iub interface connection, check whether the FE cables between the Switch and B8200 are correctly connected.
Check whether the fibers between the B8200 FS board and RRU are correctly connected
Check whether the LMT port on the CC board is normal. Connect to the LMT port on the CC board and the PC debugging port with cables
Check whether cables to dry contacts, the 232 serial port and the 485 serial port are correctly connected.
内部公开 Internal Only▲
Power-on procedure – power on/off BBU
Power-on steps
Check whether the equipment is grounded
Plug out all of the boards of B8200 except the PM.
Set the switch connecting B8200 in the DC power cabinet to ON position.
Check whether the RUN LED on the PM board flashes at the frequency of
1Hz, and whether the ALM LED is OFF.
Check whether the RUN LED on the FA board flashes at the frequency of
1Hz, and whether the ALM LED is OFF. After the PM is powered on
normally and the fan runs normally, insert the CC, BPC, SA and FS boards
to see whether they are powered on normally, and whether every LED is in
normal status.
Power-off steps
Set the switch connecting B8200 in the DC power cabinet to OFF position.
内部公开 Internal Only▲
Power-on steps Check whether the equipment is grounded
After confirming the power cables are correctly connected, set the
switch connecting R8840 in the DC power cabinet to ON position.
Observe whether the LED status is normal.
If there is an indoor lightning protection box, set the switch connecting
R8840 in the indoor lightning protection box to ON position. Observe
whether the LED status is normal.
If there is a power distribution box providing multiple DC-outputs, set
the switch connecting R8840 in that lightning protection box to ON
position. Observe whether the LED status is normal.
Power-off steps If there is an indoor lightning protection box, then set the
corresponding switch in the indoor lightning protection box to OFF
position.
If there is no indoor lightning protection box, then set the
corresponding switch in the DC power cabinet to OFF position.
Power-on procedure – power-on/off RSU
内部公开 Internal Only▲
Power-on step
Switch on the power supply of the RSU
Power off step
Switch off the power supply of the RSU
Power-on procedure – power-on/off RSU
内部公开 Internal Only▲
Contents
Introduction
Preparations
Power-on Check
Data Configuration and Version Management
Test after Commissioning
内部公开 Internal Only▲
Start the PC LMT software (installed already)
When EOMS is starting, select data
configuration of the SDR and import them
(the file is ready, *.xml)
Import UMTS SDR data configuration
内部公开 Internal Only▲
UMTS SDR Version Management
Import the version and download it
Activate the version
内部公开 Internal Only▲
UMTS SDR version management-import and download
内部公开 Internal Only▲
UMTS SDR version management - activate
内部公开 Internal Only▲
Contents
Introduction
Preparations
Power-on Check
Data Configuration and Version Management
Test after Commissioning
内部公开 Internal Only▲
UMTS SDR service test
Speech service
Data service
Other services
For test items, please refer to ZXSDR ****** Test
Guide
内部公开 Internal Only▲
Review
事后追溯
1. Commissioning procedure
2. Commissioning preparations
3. How to configure and manage
version information
4. Service test
5. Q&A
内部公开 Internal Only▲