sct - brief overview

6
14/15 February 2 002 SCT/Pixel RODDAQ Workshop 1 SCT - brief overview Current situation: barrel module production will start very soon. Significant number of modules available by the summer forward module production delayed by problems with hybrid. Possibly 9-12 months before production of modules begins? Hence critical time on schedule is when assembly of the first production barrel (innermost = barrel 3) begins will be at Oxford assembly due to start in Q3 2002 and take ~9 months complete barrel has 384 modules (=8 fully populated RODs)

Upload: sienna

Post on 22-Jan-2016

31 views

Category:

Documents


0 download

DESCRIPTION

SCT - brief overview. Current situation: barrel module production will start very soon. Significant number of modules available by the summer forward module production delayed by problems with hybrid. Possibly 9-12 months before production of modules begins? - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SCT - brief overview

14/15 February 2002 SCT/Pixel RODDAQ Workshop 1

SCT - brief overview• Current situation:

– barrel module production will start very soon. Significant number of modules available by the summer

– forward module production delayed by problems with hybrid. Possibly 9-12 months before production of modules begins?

• Hence critical time on schedule is when assembly of the first production barrel (innermost = barrel 3) begins

– will be at Oxford

– assembly due to start in Q3 2002 and take ~9 months

– complete barrel has 384 modules (=8 fully populated RODs)

Page 2: SCT - brief overview

14/15 February 2002 SCT/Pixel RODDAQ Workshop 2

• Prior to the assembly of the first barrel:

– need user evaluation of hardware and software (systemtest?)

– Oxford wish to receive kit a couple of months before assembly begins

• Hence want to have initial, working system ~May 2002.

• Hardware schedule:

– 4 (pre-)production RODs built. Up to 13 in total could be made by summer 2002.

– 2 pre-production BOCs assembled in early March. Up to 11 could be made by summer 2002.

– Caveat: minimal optical components are available at present (hoping for 10 opto plug-ins (120 channels) each of RX and TX by mid-March, but main supply not available until (mid-?)May.). Until then, BOCs will be partially populated with optical components.

– 4 prototype TIMs made. Up to 10 in total could be made by summer 2002.

Page 3: SCT - brief overview

14/15 February 2002 SCT/Pixel RODDAQ Workshop 3

• Hardware schedule continued:

– all extra RODs, BOCs, TIMs would need 2 months to manufacture

– design work on production RODs, BOCs and TIMs should be completed by July 2002. PRR ~August 2002. Then production would start ~September 2002.

– numbers of modules and current schedule is not incompatible with needs

• ~4 RODs in May 2002

• ~6 RODs in July 2002

• Post September 2002 - should move into production and hence be able to cover all needs

Page 4: SCT - brief overview

14/15 February 2002 SCT/Pixel RODDAQ Workshop 4

• Possible way forward:

– first working setup ~April/May 2002 - this would logically go in the CERN systemtest

– in parallel, kit build-up at Oxford, especially to allow them to develop software especially needed for macro-assembly work (e.g. DAQ-DCS, special equipment).

– setup suitable for routine module readout during macro-assembly ~June/July 2002. Initially would only need to readout 1 ROD, but relatively quickly would be required to handle 2 RODs.

– system for reading-out multiple RODs would develop during Autumn/Winter 2002.

• Test beam - not considered to be on critical path. No NEED for ROD-based readout in 2002 test beam, but it would in principle be a useful extra test bed.

– However, shortage of resources probably excludes it as an option. Could be considered in 2003 or 2004 as part of combined Inner Detector tests - but then wouldn’t be a test bed.

Page 5: SCT - brief overview

14/15 February 2002 SCT/Pixel RODDAQ Workshop 5

• What does a working setup need?

– see Requirements Document of GFM and PWP!

– following is not a definitive list:

• (re)configure and readout module or groups of modules

• recovery from power supply trips/module hangups

• event data retrieval, analysis and storage (via VME backplane)

• historgram booking,filling and storage

• (re)characterisation of modules - including a variety of possible parameter scans

• handle an increasing number of modules, up to O(103)

– implies

• DAQ and DCS must interact reliably and coherently

• control interface must allow great flexibility

– some functions may be developed on the RCC and migrate to ROD DSPs

Page 6: SCT - brief overview

14/15 February 2002 SCT/Pixel RODDAQ Workshop 6

Summary• April/May 2002 - 1st DAQ required (systemtest and Oxford), with

developing functionality towards...

• July 2002 - DAQ with most of required functionality, capable of supporting macro-assembly activities, though initially with only 1 or 2 RODs, but expanding with time to...

• ~March 2003 - completion of first barrel - DAQ can read out ~8 RODS (400 detectors).

• Up to this point, only single-crate arrangements with no use of S-link are assumed. This is probably necessary at macro-assembly sites to minimise complexity.

• Further in the future - multi-crate DAQ, when >1 barrel are brought together. Timeframe for this is less clear. Also at what stage do we need to integrate T/DAQ equipment (start of 2004, when should have all 4 barrels together?).