scrumday chile - value estimation and prioritization using cost of delay

83
VALUE estimation and prioritization using Cost of Delay (CoD) Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Upload: carlos-letelier-pardo

Post on 13-Apr-2017

551 views

Category:

Software


5 download

TRANSCRIPT

Page 1: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

VALUE estimation and prioritization using Cost of Delay (CoD)

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 2: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

http://homebodyandsoulblog.com/wp-content/uploads/2014/05/yashow-4.jpg

Disclaimer! This is an original copy! A LOT of the content comes from Joshua Arnold and César Idrovo’s materials

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 3: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 4: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

1

The DON Hello, my name is

If you only quantify one thing, quantify the

cost of delay

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 5: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

2 Value is rare and extreme

$0 $200,000 $400,000 $600,000 $800,000

$1,000,000 $1,200,000 $1,400,000 $1,600,000 $1,800,000 $2,000,000 $2,200,000 $2,400,000 $2,600,000 $2,800,000

0 10 20 30 40 50 60 70 80

A small number of features have a very high

Cost of Delay

Cost

of D

elay

/ w

eek

Requirements sorted by Cost of Delay Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 6: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Top vs bottom quartile: 1,000x

$230,000/wk $220/wk

Bottom 25%

Top 25% of RQs

$18,600/wk

Next 25%

$5,200/wk

Next 25%

Average $ Benefits Per Requirement

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 7: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Without information about

VALUE

the system optimizes for other things

3

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 8: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

4 examples that you will have to be able to explain…

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 9: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

h"ps://leopardsolu.ons.files.wordpress.com/2015/04/group-­‐decision-­‐making-­‐in-­‐communi.es-­‐peytonbolin5.jpg  

#1 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 10: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

MoSCoW

Must Have

Should Have

Could Have

Won’t Have

ROI

Relative Cost of Delay

Class of Service

Benefit-to-cost ratio

4:1

h"p://lightbulb2live.com/wp/wp-­‐content/uploads/2014/03/safe.png   h"p://blog.businessefficacy.com/image?fileID=19174&file=GeOngRtnonSalesInvest.png   h"p://ra.olegal.biz/wp-­‐content/uploads/2013/12/bigstock-­‐important-­‐very-­‐high-­‐priority-­‐i-­‐46052392.jpg  

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 11: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Let’s prioritize!

Feature

A

B

C

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 12: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Let’s prioritize!

Feature MoSCoW

A Must have

B Must have

C Must have

Which  one  should  we  do  first?  Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 13: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Let’s prioritize!

Feature MoSCoW ROI

A Must have 10%

B Must have 15%

C Must have 8%

How  about  now?  Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 14: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Let’s prioritize!

Feature MoSCoW ROI Relative CoD

A Must have 10% 10

B Must have 15% 4

C Must have 8% 7

And  now?  Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 15: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Let’s prioritize!

Feature MoSCoW ROI Relative CoD

Revenue /week

A Must have 10% 10 $100k

B Must have 15% 4 $15k

C Must have 8% 7 $800k

Are  you  sure?  Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 16: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

h"p://collegian.tccd.edu/wp-­‐content/uploads/2013/10/poli.cal-­‐incivility-­‐color.jpg  Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 17: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 18: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

h"p://vehicletrackingscotland.co.uk/wp-­‐content/uploads/2015/01/laptop_PNG5893.png  

#2 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 19: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

h"p://a.fastcompany.net/mul.site_files/fastcompany/imagecache/1280/poster/2014/10/3036369-­‐poster-­‐p-­‐1-­‐the-­‐keys-­‐to-­‐successful-­‐pair-­‐programming-­‐pa.ence-­‐and-­‐humility-­‐say-­‐experts.jpg  

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 20: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Productivity

-15pp Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 21: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

What other key parameters do you need to know?

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 22: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Help us speed up the purchasing

process!

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 23: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

~$2,330,000

Irrecoverable, lost VALUE:

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 24: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Time

$ /week

work work work

Total Delay Cost

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 25: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

~$40k/week Benefit

Time

work work work

Total Delay Cost

$ /week

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 26: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

~$40k/week Benefit

Time

work work work

Total Delay Cost

$ /week

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 27: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Productivity

-15pp Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 28: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Weekly cost of a developer

$800 + $120 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 29: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Weekly net value delivered per developer

$32,533 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 30: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay per developer

$32,653 /week 5 teams, 6 developers each:

$979,600 /week Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 31: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

~$2,330,000

Irrecoverable, lost VALUE:

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 32: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

15,985 monitors

By now we could have bought

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 33: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

<<< 1 day

Time to break even

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 34: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Put a price-tag on time

$ Business value of the

feature

Cost of Delay

Information Discovery Value How that value

varies over time

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 35: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

A framework for thinking about value

Increase Revenue

Increasing sales to new or existing customers. Delighting or Disrupting to increase market share and size

Protect Revenue

Improvements and incremental innovation to sustain current market share and revenue figures

Reduce Costs

Costs that we are currently incurring, that can be reduced. More efficient, improved margin or contribution

Avoid Costs

Improvements to sustain current cost base. Costs we are not currently incurring but may do in the future

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 36: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Example: Cost of not having Monitors for Pair Programming

Start generating revenue without

delay

Avoid paying 15% more to achieve the

same outcome

Estimate the value of the effects of the change 1

A couple of tactics for getting to $

Avoid Costs

Reduce Costs

Protect Revenue

Increase Revenue

$120 $32,533 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 37: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Make the value equal to cost of alternatives

Example: Automating a process

Avoid Costs

Reduce Costs

Protect Revenue

Increase Revenue

Cost of human error

Current manual

cost

A couple of tactics for getting to $

2

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 38: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

h"p://.p.gatech.edu/sites/default/files/Resolución%20en%20cajas%20(Medium).JPG  

#3 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 39: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Automating a Process Automating a process to satisfy new regulation: •  Reduce the additional manual processing resource which

is estimated to cost about 20 FTEs at $20k (p.a.) per FTE •  Due to the current manual process, there is a 10%

probability of an error •  Once a month there’s an inspection. If an error is found,

the company has to pay a $5,000,000 fine

What is the cost of delaying this automation? Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 40: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Reduce Cost: 20 FTEs at $20k each per year = $400,000 /year ~ $8,000 /week

Avoid Cost:

$5,000,000 in fines per month * 10% Probability of finding an error = Expected Value = $500,000 /month ~ $125,000 /week

Cost of Delay: ~ $133,000 /week

Automating a Process

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 41: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Put a price-tag on time

$ Business value of the

feature

Cost of Delay

Information Discovery Value How that value

varies over time

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 42: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Willingness to pay for the info?

Quantifying the value of information

Cost to obtain info first-hand?

Information Discovery

Value

What is it worth to avoid taking

the wrong path?

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 43: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Put a price-tag on time

$ Business value of the

feature

Cost of Delay

Information Discovery Value How that value

varies over time

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 44: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Urgency Profiles Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 45: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

For ideas with a very long-life, with peak unaffected by delay

Time

Cost of Delay

$ Be

nefit

s /

wee

k Long-life, unaffected peak 1

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 46: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

For ideas with a very long-life, with peak unaffected by delay

Time Late Entry

Cost of Delay

$ Be

nefit

s /

wee

k Long-life, unaffected peak 1

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 47: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

For ideas with a very long-life, with peak unaffected by delay

Time Late Entry

Cost of Delay

$ Be

nefit

s /

wee

k

Delay Cost

Long-life, unaffected peak 1

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 48: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

For ideas with a very long-life, with peak unaffected by delay

Time Late Entry

Cost of Delay

$ Be

nefit

s /

wee

k

Delay Cost

Long-life, unaffected peak 1

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 49: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Short benefits horizon, and reduced peak due to late delivery

Time Late Entry

Reduced Peak

Delay Cost

$ Be

nefit

s /

wee

k Short-life, affected peak 2

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 50: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

For ideas with a very long-life, with reduced peak due to later delivery

Time Late Entry

Reduced Peak

Delay Cost

$ Be

nefit

s /

wee

k Long-life, affected peak 3

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 51: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Time Late Entry

Delay Cost

$ Be

nefit

s /

wee

k Seasonal/date-driven 4

Last Responsible

Moment Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 52: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Automating a Process Automating a process to satisfy new regulation: •  Reduce the additional manual processing resource which is

estimated to cost about 20 FTEs at $20k (p.a.) per FTE •  Due to the current manual process, there is a 10% probability of an

error •  Once a month there’s an inspection. If an error is found then the

company has to pay a $5,000,000 fine •  The new regulation will be effective starting 1st May 2016 •  The duration of the implementation is estimated to be 13 weeks

What is the total delay cost by December 17th? Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 53: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Automating a Process Automating a process to satisfy new regulation: •  Reduce the additional manual processing resource which is

estimated to cost about 20 FTEs at $20k (p.a.) per FTE •  Due to the current manual process, there is a 10% probability of an

error •  Once a month there’s an inspection. If an error is found then the

company has to pay a $5,000,000 fine •  The new regulation will be effective starting 1st May 2016 •  The duration of the implementation is estimated to be 13 weeks

What is the total delay cost by December 17th? *Hint: ~19 weeks away Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 54: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Urgency Profiles

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 55: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

https://dereklieu.files.wordpress.com/2011/01/tetris-marathon-tetris.jpg

#4 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 56: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Feature Cost of Delay X $133,000/week Y $80,000/week Z $1,000,000/week

Which one would you do first?

If these take the same amount of time to deliver:

Scheduling decisions

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 57: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay Simulation

Feature Duration (weeks)

Cost of Delay (m)

A 5 $1

B 1 $4

C 2 $5

(BlackSwanFarming.com)

Which one should we do first? Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 58: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay Simulation

Time

Valu

e Po

tent

ial

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 59: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay Simulation

A

Time

Valu

e Po

tent

ial

5 4 3 1 2

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 60: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay Simulation

$ A

Time

Valu

e Po

tent

ial

5 4 3 1 2 6

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 61: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

B

Cost of Delay Simulation

$ A

Time

Valu

e Po

tent

ial

5 4 3 1 2 6

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 62: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

B

Cost of Delay Simulation

$

$ $ $ $

A

Time

Valu

e Po

tent

ial

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

5 4 3 1 2 6

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 63: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

B

Cost of Delay Simulation

$

$ $ $ $

A

C

Time

Valu

e Po

tent

ial

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

5 4 3 1 2 6

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 64: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

B

Cost of Delay Simulation

$

$ $ $ $

$ $ $ $ $

A

C

Time

Valu

e Po

tent

ial

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $ $

$ $ $ $ $

$ $ $ $ $

5 4 3 1 2 6

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 65: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 66: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

B

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 67: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

$ $

$

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $

C

B

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 68: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

$ $

$

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $ $

$ $ $ $ $

$ $ $ $

C

B

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Total Delay Cost = $50

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $

$50

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 69: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

$ $

$

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $

$50 C

B

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Time

Cost

of D

elay

B

A

C

Cost of Delay (CD3) Scheduling

Total Delay Cost = $50

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 70: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

$ $

$ $ $ $ $

$ $ $

$

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $

C

B

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Time

Cost

of D

elay

B

A

C

Cost of Delay (CD3) Scheduling

Total Delay Cost = $8 Total Delay Cost = $50

$50

$8 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 71: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

$ $

$

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $ $

$ $ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $ $

$ $ $

$ $

$ $ $ $ $

$

C

B

A

Time

Cost

of D

elay

First-In-First-Out

Scheduling

Time

Cost

of D

elay

B

A

C

Cost of Delay (CD3) Scheduling

84% reduction in delay cost vs FIFO

In this simple example:

Total Delay Cost = $8 Total Delay Cost = $50

$50

$8

(BlackSwanFarming.com)

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 72: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

When time to deliver varies, use Cost of Delay Divided by Duration

Cost of Delay

Duration CD3

$ Business value of the feature

Information Discovery Value

How that value varies over time

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 73: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay Simulation

Feature Duration (weeks)

Cost of Delay (m)

CD3

A 5 $1 0.2

B 1 $4 4

C 2 $5 2.5

(BlackSwanFarming.com)

So again, which one should we do first? Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 74: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

CD3 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 75: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

In CD3, why divide by

Duration…

and not

Cost? Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 76: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Money? You can beg, borrow or steal…

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 77: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Time? Can’t be replaced. Can’t be reversed!

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 78: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Knowing how long the pipeline is

blocked is more valuable information

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 79: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Takeaways

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 80: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

Cost of Delay

Improves prioritisation

Enables better trade-off decisions

Changes the focus of the conversation

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 81: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

#1 #2

#3 #4 Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 82: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

People make decisions Not the data, or an algorithm

Organisational strategy

Technology strategy

Start with CD3 ‘initial triage’

Adjust CoD to reflect strategy

State reasons for adjustment

Additional levers? In the real world…

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015

Page 83: ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay

1.  Contact: [email protected]

2.  Thanks [email protected] & emergn.com

3.  Experience report and more detail: BlackSwanFarming.com by Joshua Arnold and Özlem Yüce

Prepared by Carlos Letelier & César Idrovo ScrumDay Chile 2015