screen wall at pbp site
TRANSCRIPT
-
8/3/2019 Screen Wall at Pbp Site
1/33
SCREEN WALLTower - 2
-
8/3/2019 Screen Wall at Pbp Site
2/33
Contents
Introduction
Stages
Roles & Responsibilities
Flow Chart
Total Scope & Details
Dimensions
Problems Faced Solution Adopted
Screen Wall Pics
Conclusion
-
8/3/2019 Screen Wall at Pbp Site
3/33
Introduction
Erecting structural steel work for
commercial building construction takes
place in a dynamic changing environmentwhere there are many risks and hazards
associated with it.Proper and timely
planning and coordination are the most
effective ways to manage these hazardsand risks.
-
8/3/2019 Screen Wall at Pbp Site
4/33
Stages
Project involving structural steel
construction have main 4 stages.
The stages are as follows :Design
Fabrication
TransportErection
-
8/3/2019 Screen Wall at Pbp Site
5/33
Roles & Responsibilities
The person who is responsible for the engineeringdesign of the Structure
Structural designEngineer
The party who is responsible for managing theconstruction and who has control over itClient
The person who is responsible for the engineeringdesign and stability aspects of the erection of the steelstructure
Erection Engineer
The person responsible for making the steel work
Fabricator
The Employer responsible for engaging the erectioncrew and erecting the structureErector
The person who will be looking after the safety aspects
during erection.Safety Inspector
-
8/3/2019 Screen Wall at Pbp Site
6/33
Flow Chart
-
8/3/2019 Screen Wall at Pbp Site
7/33
Total Scope & Details
Scope of Work 285 MT
Length ofSW 120 metre
Width ofS
W 22 metre Height ofSW 16.5 metre
Total Columns 18 Nos
Total Tie Beams 60 Nos
Total Tube 132 Nos
Plates - 432 Nos
-
8/3/2019 Screen Wall at Pbp Site
8/33
Dimensions
Column 450mm x 750mm x 16mm
Tie Beam 350mm x 750mm x 10mm
Tube size- 150mm x 150mm x 4mm C-Channel 100mm x 50mm
-
8/3/2019 Screen Wall at Pbp Site
9/33
System Process We Adopted Prior
ToS
tructural Erection
-
8/3/2019 Screen Wall at Pbp Site
10/33
What We Do ?
Define : Understand and specifying the problem
Measure : Identifying the risks involved
Analyze : Brainstorming with the Consultants
and come up with innovative ideas Improve : Bring Change while implementing new
technologies
Control : Keep Control while actual erection to
avoid unprecedented accidents
-
8/3/2019 Screen Wall at Pbp Site
11/33
To Avoid Risk
-
8/3/2019 Screen Wall at Pbp Site
12/33
Prepare be ready
Respond In a timely manner
Recover when the need arises Mitigate Eradicate the errors/Reduce the
errors
Contd..
-
8/3/2019 Screen Wall at Pbp Site
13/33
Sequence of Activities during
Erection Receiving Material from the shop and
temporarily stacking them, if necessary.
Lifting and placing the member andtemporarily holding in place.
Temporarily bracing the system to ensure
stability during erection.
Aligning and permanently connecting the
members either by bolting or welding.
-
8/3/2019 Screen Wall at Pbp Site
14/33
SCREEN WALL Tower 2
Problems faced : Prior starting theScreen wall fabrication a square hollow
section of dimension (750x450x16)mm isrequired for Screen wall Vertical Columns
which isnt easily available in market and if
we need to manufacture such section it
would cost at skyrocketing price.
-
8/3/2019 Screen Wall at Pbp Site
15/33
Contd..
Solution we adopted : We created ashop drawing for the square hollowsection of the required dimension (Cutthe plate and bend it into J section and
joining the two J shaped plates into 1square hollow section with the help of
Splice Plates) which we got it approvedfrom the Consultant and Client.
-
8/3/2019 Screen Wall at Pbp Site
16/33
Contd..
Achievement :
Saved time
Provided value engineering ideasReduced time cycle
-
8/3/2019 Screen Wall at Pbp Site
17/33
Problem 2
Problems Faced : At terrace level (117mheight) about a total of 250 MT of box
columns needed to be lifted and fixed butthe problem we faced is the unavailability
of crane and due to the height factor hydra
cannot be used which is virtually impossible
to use.
-
8/3/2019 Screen Wall at Pbp Site
18/33
Solution
Solution We adopted : Usage ofVertical Gadams and chain pulleys
having a capacity to lift 4MT waserected at Terrace and used to lift the
2.5m of Column pieces to complete the
total 16m height of each column.
-
8/3/2019 Screen Wall at Pbp Site
19/33
After Fabrication of two J shaped
Section
-
8/3/2019 Screen Wall at Pbp Site
20/33
Erection of 1st Screen Wall Section
-
8/3/2019 Screen Wall at Pbp Site
21/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
22/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
23/33
Screen Wall in Progress
-
8/3/2019 Screen Wall at Pbp Site
24/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
25/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
26/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
27/33
Screen Wall in Progress
-
8/3/2019 Screen Wall at Pbp Site
28/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
29/33
Contd..
-
8/3/2019 Screen Wall at Pbp Site
30/33
GOAL IS ATTAINED ONLY IF
EVERYTHING FALLS
AT THE RIGHT PLACE
AT THE RIGHT TIME &
HAVE THE RIGHT RESOURCES
MACHINE
Teamwork Resources
MANPOWER
SAFETY
GOAL
-
8/3/2019 Screen Wall at Pbp Site
31/33
-
8/3/2019 Screen Wall at Pbp Site
32/33
Conclusion
The Structural Heavy work requires pre-
planning before performing the actual
erection on site. It involves all the aspects
of organizing resources , proper job
allocation and systematic co-ordination ,
risk assessment to achieve great results
on site.
-