Scoping Meeting
Yuba Goldfields200-Year Flood Protection ProjectEnvironmental Impact Report
June 23, 2014
![Page 2: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/2.jpg)
Meeting Agenda
• Welcome and Introductions• Meeting Objective• Project Background • Proposed Project Alternatives• Scoping and CEQA Process• Environmental Issues • Public Comments and Input
2
![Page 3: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/3.jpg)
Introductions
Three Rivers Levee Improvement AuthorityPaul Brunner, Executive Director
Downey BrandAndrea Clark, Legal Counsel
MBK EngineersLarry Dacus, P.E., Project Engineer
AECOMAndrea Shephard, Ph.D., Environmental Project Manager
3
![Page 4: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/4.jpg)
Meeting Objective
Seek public and agency input on the scope and content of the EIR, including
alternatives
4
![Page 5: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/5.jpg)
Proposed Background
5
![Page 6: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/6.jpg)
Project Location
6
![Page 7: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/7.jpg)
Project Need
• Yuba River actively eroding south bank tailings mound.
• Landform changes in Goldfields have affected flow paths and made it easier for floodwaters to flow through the Goldfields.
• Areas that were thought to have 200-year flood protection are still at risk.
7
![Page 8: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/8.jpg)
Project Purpose
8
Reduce flood risk to properties in RD 784 and TRLIA assessment districts by providing sustainable200-year flood protection.
Source: Data compiled by AECOM in 2014
![Page 9: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/9.jpg)
Project Objectives
• Prevent 200-yr flood waters from flowing through Goldfields and flanking State Plan of Flood Control levee system.
• Implement long term sustainable solution by 2025.
• Minimize impacts on aggregate mining operations.
• Minimize impacts on gold dredging operations.
• Minimize impacts on environmental resources.
• Provide environmental benefits, if feasible.
9
![Page 10: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/10.jpg)
Proposed Project Alternatives
10
![Page 11: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/11.jpg)
Project Alternatives
• Four (4) Action Alternatives plus the No-Project Alternative to be evaluated at equal level of detail in EIR.
• Alternatives 1, 2, and 3 – Construct embankment within the Goldfields using existing dredge tailings.
• Alternative 4 – Construct engineered levee south of the Goldfields using material imported from nearby.
• All alternatives would meet USACE and DWR urban levee design criteria for 200-year flood protection.
11
![Page 12: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/12.jpg)
Project Alternatives
Alternative 1: 100-Year Project Enlargement9.0 mile embankment 331 acres in Goldfields
Alternative 2: West-Side Goldfields Boundary Alignment8.8 mile embankment 317 acres in Goldfields
Alternative 3: South Bank Yuba River Alignment 9.1 mile embankment 291 acres in Goldfields
Alternative 4: Levee South of the Goldfields3.5 mile embankment 199 acres in Goldfields
12
![Page 13: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/13.jpg)
13
Project Alternatives
![Page 14: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/14.jpg)
14
Alternatives 1, 2, and 3200-Year Embankment in Goldfields
Source: TRLIA 2013, adapted by AECOM in 2014
• Regular O&M: inspections, weed abatement, surface patrol road maintenance.
• During High Flow Periods: Surface road patrols every 4 hours to identify/address potential flooding issues
![Page 15: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/15.jpg)
Alternative 3Relocation of Waterway 13
15
Source: TRLIA 2013, adapted by AECOM in 2014
Source: TRLIA 2013, adapted by AECOM in 2014
Fish barrier at New Outlet Scour Protection
• Will require periodic repair and replacement. • Expected design life of 50 years.
![Page 16: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/16.jpg)
16
Alternative 4200-Year Levee South of Goldfields
Source: TRLIA 2013, adapted by AECOM in 2014
• Regular O&M: Same as other alternatives plus management of vegetative cover on levee side slopes, operation and annual maintenance of pipe and gates at YCWA canal crossing.
• During High Flow Periods: Surface road patrols every 4 hours to identify/address potential flooding issues
![Page 17: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/17.jpg)
No-Project Alternative
• 200-year flood protection solution not built.
• 100-year flood protection solution built.
• Decreased flood inundation benefits of TRLIA 200-Year Flood Protection Program.
• Portions of RD 784 and TRLIA assessment districts may be mapped into FEMA floodplains.
• Residents have to purchase flood insurance.
17
![Page 18: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/18.jpg)
CEQA Review Process
18
![Page 19: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/19.jpg)
Purpose of Scoping
• Inform public and agencies
• Receive public/agency input
• Help define project
• Help identify range of alternatives
• Help identify environmental effects to be evaluated
19
![Page 20: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/20.jpg)
Environmental Review Schedule
20
Notice of Preparation of an EIR June 13, 2014
Scoping Meeting June 23, 2014
Scoping Period Ends July 14, 2014
Notice of Availability/Draft EIR August 2014
Public Review 45 days
Response to Comments/Final EIR November 2014
Commenting Agency Review 10 days
EIR CertificationProject Decision
FindingsOverriding ConsiderationsMitigation Monitoring Plan
Notice of Determination
November/December 2014
Permitting 2015
![Page 21: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/21.jpg)
Opportunities for Input
Scoping Meeting Today
NOP 30-Day Comment Period June 13 – July 14
Draft EIR 45-Day Public Review Period August/September
21
![Page 22: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/22.jpg)
Issue Areas to be Addressed
• Aesthetics• Agricultural and Forestry
Resources• Air Quality• Biological Resources• Cultural Resources• Geology/Soils/Minerals/
Paleo Resources• Greenhouse Gas
Emissions
• Hazards and Hazardous Materials
• Hydrology/Water Quality• Land Use/Population and
Housing• Noise• Recreational Resources• Transportation/Traffic• Utilities and Public
Services
22
![Page 23: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/23.jpg)
23
Project Alternatives
![Page 24: Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014](https://reader036.vdocuments.mx/reader036/viewer/2022062511/551ab32855034656628b511b/html5/thumbnails/24.jpg)
How do you participate?
• Present your views today.
Please focus on the scope of the project (i.e. project elements and alternatives & environmental effects and mitigation).
• Provide written comments on the NOP today or to TRLIA by 5 pm, July 14, 2014.
Paul Brunner, TRLIA
1114 Yuba Street, Suite 218, Marysville, CA 95901
Fax: (530) 749-6990 Email: [email protected]
• Review and comment on the Draft EIR.
• Contact TRLIA throughout the process.
24
THANK YOU