science centre south update - ucd.ie south presentation1.pdf · science centre south update...

14
Science Centre South Update 3/02/2010

Upload: others

Post on 10-Sep-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

Science Centre South Update

3/02/2010

Page 2: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

Overview� Introduction

� South Project Status

� Phasing and Interface Element� Phasing and Interface Element

� Construction Look ahead

� Science Masterplan

� Queries/ Questions

Page 3: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

South Project Status

Page 4: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

Project Status

Page 5: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

Project Status� Decanting of A2

• A1 and CSCB Operation

• A3 Operation� Enabling Works:

• Complete September 2009� Main Contract:

• Appointment of John Paul Construction

• Phase 1: Start on site January 2010

A2 element)� Substantial Completion:

• Phase 1: December 2010� Appointment of John Paul Construction

• Site Setup January

• Substructure and Superstructure February–September

• External Façade March-August

• Fit-Out April-November

• Phase 1 complete December

• Lobby Area complete by February 2011� Impact on current activities

• Daily operation of School

• Sensitive equipment

• Teaching Laboratory activities

• Works to front of CSCB

• Noise and Dust

• Fire Alarm

Page 6: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

Phasing & Interfacing Elements � Lobby Area

� Existing Office Areas & Signature wall

� Lifts

� Storage � Storage

� Access to Building

� Lifts

� Bridge connection to Hub

� Works to Hub building

� Temporary Stairs

Page 7: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

G

R

O

U

N

D

3/02/2010 Science Centre South

F

L

O

O

R

Page 8: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

F

I

R

S

T

F

L

O

O

R

Page 9: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

S

E

C

O

N

D

F

L

O

O

R

Page 10: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

T

H

I

R

D

F

L

O

O

R

Page 11: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

Construction Look AheadFebruary/March 2010

� Creation of temporary access to A3

� Removal of Link Bridge

� Works to front of CSCB to facilitate drainage

� Demolition works in A2

February/May 2010

� Works to lobby area and lifts

� Superstructure of new build.

� Weather sealing of building

Page 12: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

UCD Science Centre Masterplan

Page 13: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

UCD Science Centre Masterplan

Page 14: Science Centre South Update - ucd.ie south presentation1.pdf · Science Centre South Update 3/02/2010. Overview Introduction South Project Status Phasing and Interface Element Construction

South ElevationSouth Elevation

North Elevation