sc links integration point 7
DESCRIPTION
SC Links Integration Point 7. S. Weisz , J. P. Corso and A. Ballarino. Overview of Point 7. DFBA actual position. DFBA actual position. IP7. SC links. DFH HL-LHC positions. Assumptions retained for the SC link at Point 7. - PowerPoint PPT PresentationTRANSCRIPT
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.
SC Links IntegrationPoint 7
S. Weisz, J. P. Corso and A. Ballarino
2
IP7
Overview of Point 7DFBA actual position DFBA actual position
DFH HL-LHC positions
SC links
3
Assumptions retained for the SC link at Point 7
• Find a routing for a 200mm semi-flexible pipe ~500m long from service modules in RR73/77 to the DFH connections to the power converters relocated in the TZ76 gallery
•Minimum bending radius of 1,5m (to be experienced with multiple bends)
• Leave free the transport areas in the LHC tunnel and in the TZ76 gallery
43rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing in TZ76
53rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing in TZ76
63rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing in TZ76• Only one practical solution: under existing cable trays
Rack
s
Rack
s
Rack
s
SC links
Links during installation ?
73rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing in TZ76• Section along TZ76 and detailed view of the exit UJ76
83rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing UJ76 junction – Two options• Tunnel to UJ76 service area: existing ducts are full!• 2 “small” ducts 400mm must be drilled• Between 2m & 3m long, depends on the angle…
• UJ76 to TZ76 gallery: 2 main options• without long ducts, along UJ76 bottleneck…• with 2 new long ducts ( 19m each) ̴�
93rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing UJ76 – Option 1• 2 shorts ducts from LHC tunnel to service area
• NO new long ducts
SC Links
UJ76LHC Tunnel
103rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing UJ76 – Option 1• Along UJ76 bottleneck
11
Routing UJ76 – Option 2• 2 shorts ducts from LHC tunnel to service area• With 2 new long ducts from UJ76 to the TZ76 gallery
12
Routing Options – UJ76• Overview of the two options: 1st option (no long ducts)
requires more bends and smaller bending radius
133rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Routing R771 towards RR77• 3 Sections with various positions of the link & pipe
14
Routing inside RR77
Connection to cryostat to be studied
153rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Access to Point 7 for SC links
Point 7
Point 6
Point 8~3,3 km
~3,3 km
16
Transport of SC links to Point 7Access Pit PM 85
173rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Access to Point 7 for SC links
Access Pit PM 65 Access Pit PM 85
18
Transport of SC links to Point 7500m link ready for handling
Space inside PM 85
Surface BuildingSD8 1,
8
5,5
19
Hard Points• RR73/77 to Long Straight Section (R74 and R771) : • Many constraints due to shielding, metallic
structures and supports• need design of the service module
• Very few practical solutions in the LHC tunnel and in the TZ76 gallery!
• UJ76 crossing: many bends in multiple directions
20
Conclusions• Experience is needed for the transport and
installation of two 500m long semi-flexible links ̴�through curved passages. Thanks to the proposed design, transport and installation of the new DFBs should be a challenge
• Integration tests will be done at CERN by mid 2015 using a 60 m long cryostat
• Choice between Option 1 and Option 2 can be made by mid 2015 – and civil engineering during TS in 2016
213rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013
Acknowledgements
Thanks to J.P. Corso for the detailed integration studies
(EDMS 1419773)