Development of Brackish Groundwater Desalination Project: SAWS Twin Oaks Brackish Groundwater Desalination Program

TRANSCRIPT

Page 1: SAWS - Development of Brackish Groundwater Desalination Project

TWCA 2014 Mid-Year Conference

W. John Seifert, Jr., P.E.LBG-Guyton Associates

Kevin Morrison, P.G.San Antonio Water System

Development of Brackish Groundwater Desalination Project: SAWS Twin Oaks Brackish Groundwater

Desalination Program

June 12, 2014

Page 2: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 2

Topics

• Groundwater Hydrology • Groundwater Supply Development• Program Update

Page 3: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 3

What is Brackish Groundwater?

• Practical Definition: Brackish groundwater contains from 1,000 to 10,000 mg/L TDS

Fresh Brackish Saline Fresh Slightly-saline Moderately-saline Very-saline

1,000 mg/L 3,000 mg/L 10,000 mg/L

Page 4: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 4

Why Consider Brackish Groundwater?

• By 2060– Population will increase by 82% to 46.3 million– Demand will increase by 22%– Municipal demand will increase 71%– Supply (existing sources) decrease 10%– Advances in treatment technology

– Data from TWDB 2012 State Water Plan

Page 5: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 5

Carrizo-Wilcox

Gulf Coast

Hueco-Mesilla Bolsons

Major Aquifers

Page 6: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 6

Carrizo-Wilcox Aquifer

Page 7: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 7

Gulf Coast Aquifer

(Wells >500 ft deep)

Page 8: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 8

Aquifers with Substantial Amounts of Brackish Groundwater

• Carrizo-WilcoxInterbedded sand, silt and clay

• Gulf CoastInterbedded sand, silt and clay

• Hueco-Messilla BolsonsSilt, sand and gravel

Page 9: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 9

Favorable Conditions for a Brackish Groundwater Project• Water quantity adequate• Water quality acceptable

– Total dissolved solids content slightly saline to moderately saline

• Resource located in reasonable proximity to demand• Regulatory environment reasonable• RO Concentrate Management can be cost contained• Project effects are acceptable

Page 10: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 10

Carrizo-Wilcox Aquifer

- Strive for locations with

greater areal extent of resource

Page 11: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 11

Geologic Description of an Area

• Electric Log Data Point

Page 12: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 12

Carrizo-Wilcox and Gulf Coast AquifersBrackish Groundwater Resource Below Fresh Groundwater

Land Surface

Increasing

Depth

Brackish Water Sand(Yellow)

Freshwater Sand(Blue)

Clay(Brown)

Page 13: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 13

Wilcox Brackish Sands in Gonzales CountyF. Passmore #1

Page 14: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 14

GroundwaterSupply

Development

Page 15: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 15

Sequence of Supply Development

• Evaluate desk top data• Outline area for test drilling if needed• Perform drilling and water quality testing• Design wells and wellfield with appropriate well

spacing• Construct and test wells and evaluate water quality

data• Equip wells and construct water conveyance

infrastructure

Page 16: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 16

Screen Installation And Gravel Packing

Page 17: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 17

Large Capacity Brackish Water Production Well

Page 18: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 18

Production Well TestingObtain data on aquifer

productivity,

can be used for

groundwater flow modeling

Obtain water quality data

Collect data regarding

well efficiency

Page 19: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 19

Program Update

Page 20: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 20

Program General Information

• Source Water– Lower Wilcox Formation– 12 Production Wells – Avg. depth 1,600 ft.

• Treatment Process– Reverse Osmosis – 90% Recovery

• Concentrate Disposal– Deep Well Injection – 5,000 ft. depth– Two injection wells required for Phase I

Page 21: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 21

Program Components

• Production Wells

• Conveyance System (Pipelines)

• Reverse Osmosis Treatment Plant

• Injection Wells

• Electrical / SCADA

Page 22: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 22

SAWS BGD Program• Phase I (2016)

– 12 MGD or 13,440 Acre-feet/yr.

• Phase II (2021)– 12 MGD or 13,440 Acre-feet/yr.

• Phase III (2026)– 6 MGD or 6,720 Acre-feet/yr.

• Total– 30 MGD or 33,600 Acre-feet/yr.

Page 23: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 23

Lessons Learned from Past Projects

• Program Manager not having control over designers

• Low bid contractor may not be best qualified

• No contractor’s input in the design document preparation

• Claims, litigation and delays

• Change orders

• Lack of cooperation

Page 24: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 24

• Designer Engineers are under the contract of the Program Manager

• Sub-contractors are selected based on qualifications and experience under the Construction Manager At Risk (CMAR) procurement

• CMAR contractor were involved in the design phase

• Performance Incentive proposed

Procurement Plan

Page 25: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 25

Program Structure

- 4 Design Teams

- 20 Design Sub-Consultants

- 17 SMWB Firms

- 21 Local Firms

SAWS

Construction Manager at Risk (CMAR) Zachry Parsons Water

Resources JV

Program Manager Black & Veatch Corp.

Sub-ContractorsDesign Sub-Consultants

- 12 Construction Packages

- Multiple Subcontractors

Page 26: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 26

20132012

Conceptual Design

Pre-Construction

Design

2015 20162014

Program Completion October

2016

Construction Management Services

Construction

Commi-ssion

Commi-ssion Warranty

Warranty

2017 2018Program Manager

(PM)

Construction Manager at Risk

(CMAR)

GMP Board AwardMarch 2014

CMAR Process• Process allows:

– Contractor’s input in the design– Engineer’s involvement in construction planning– Qualification based selection– Guaranteed maximum price (GMP)– Pursue SAWS SMWB goals

Page 27: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 27

Guaranteed Maximum Price

• CMAR will publicly bid each construction package and recommend most qualified best value sub-contractor

• The payment to CMAR will be based on actual cost of construction not to exceed the GMP

• Should the actual cost be lower than the GMP, the difference will be a credit to SAWS

Page 28: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 28

Shared Performance Incentives• Maximum of $250,000 to Program Manager

• Maximum of $750,000 to CMAR

• Objective Parameters:• Budget• Completion Schedule• Change Control

• Subjective Parameters:• Partnering, Quality of service, Conflict Resolution,

Timely Responses

Page 29: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 29

RO Treatment

Acid

CF

AS

Calcite Contactor,Degasification,Sodium hydroxide

Product

WellConcentrate Disposal

Raw Water Blending

RO

Concentrate

Pre-treatment

Primary treatment

Post treatment

AS: Anti-scalent CF: Cartridge Filter

13

.11

MG

D2

MG

D

10 MGD

1.1

1 M

GD

11

.11

MG

D

12 MGD

Page 30: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 30

Production vs. Disposal

Land Surface

GeorgetownEdwards &

Upper Glen RoseLimestone

TD = 5,040 ft.

Midway Shale

AnacachoLimestone

Navarro Clay

Not to Scale

TD = 1,600 ft.

Production Well Injection Well

Confining Zone

~2,360 ft. Thick

Wilcox Sand(Brackish Water)

Upper Wilcox Clay

Eagle Ford Shale, Buda

Limestone, & Del Rio Clay

Austin Chalk

Carrizo Sand(Fresh Water)

Injection Zone

~ 860 ft. Thick

Production Zone

~ 600 ft. Thick

Page 31: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 31

Remaining Work for Phase I

• Additional four production wells

• Additional injection well

• Reverse Osmosis treatment plant

• Pipelines

• SCADA and Electrical system

Page 32: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 32

Construction Package Procurement

Work Package

DescriptionSAWS Approval of

CMAR Recommendation

1 Enabling (Silt Fencing / Site Fencing) May-142 Site Work May-143 Foundation May-144 Electrical / SCADA May-145 Water Treatment Plant Jun-146 Pipelines Jun-147 Access Roads Jun-148 Well Fit Out Jul-149 Production Wells Jul-14

10 Injection Wells Jul-1411 Landscaping Dec-1412 Security

Page 33: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 33

Cost

• Phase I total estimated construction cost is $192.66 million

• $/AF: $1,177 / AF

Phase I

Page 34: SAWS - Development of Brackish Groundwater Desalination Project

June 12, 2014

SAWS Brackish Groundwater Desalination ProgramPage 34

Questions?

Page 35: SAWS - Development of Brackish Groundwater Desalination Project

TWCA 2014 Mid-Year Conference

W. John Seifert, Jr., P.E.LBG-Guyton Associates

Kevin Morrison, P.G.San Antonio Water System

Development of Brackish Groundwater Desalination Project: SAWS Twin Oaks Brackish Groundwater

Desalination Program

June 12, 2014