SAW
İSTANBUL
2
1301 hectares of land expropriated
in 1988 by SSM.
ITEP Project has 4 main topics.
Airport
Technopark
Aircraft Maintenance Repair
and Overhaul Hangars (MRO)
Trade and Commercial Zone
SCOPE OF THE PROJECT
ITEP PROJECT
In order to operate Sabiha Gökçen Airport which is the
locomotive of ITEP Project HEAŞ “Airport Management and
Aeronautical Ind. Inc.” was founded in 27th of January 2000.
Sabiha Gökçen Airport opened domestic and international traffic
in January 2001.
HEAŞ and SABİHA GÖKÇEN AIRPORT (SAW)
After BOT Tender of The Terminal and Ancillary Facilities in
July 2007, HEAŞ delivered the operations of the below
items which had been done since January 2001;
Ground Handling
Fuel
Terminal
Warehouse
to Limak-GMR-Malaysia Airports consortium company ISG
(İstanbul Sabiha Gökçen Havalimanı Yatırım Yapım ve
İşletim A.Ş.) in May 2008.
AIRPORT AUTHORITY
As an Airport Authority of HEAŞ;
Air Navigation Systems,
Management of Runway, Taxiway and Aprons,
Technical Support and Control,
Safety Management System,
Aeronautical Information Management (AIM),
Rescue and Fire Fighting,
First Aid,
Obstacle Control,
are the main duties and functions.
AIRPORT AUTHORITY
Terminal I
(2000)
Terminal II
(2009)
THY HABOM
(2014)
My Technic (2008)
TEC
(2010)
SABİHA GÖKÇEN AIRPORT (SAW)
Aircraft Maintenance, Repair and Overhaul Hangars are located at the
south of the existing runway.
THY Teknik
Hangar (20 ha)
My Teknik
Hangar (5 ha)
TEC
Engine Center
(10 ha)
MRO FACILITIES
FLIGHT AND PASSENGER INCREASE
PASSENGER STATISTICS
FLIGHT STATISTICS
Passenger (Million)
2010 2011 2012 2013 2014 2015 2016 2017 2018
Türkiye 102,80 117,62 130,35 149,23 165,72 181,07 173,74 193,05 209,99
Atatürk 32,14 37,39 45,09 51,29 56,70 61,30 60,41 64,11 67,98
Sabiha Gökçen 11,19 13,12 14,69 18,52 23,49 28,11 29,67 31,86 34,13
Antalya 0,16 25,02 25,09 27,01 28,30 27,77 18,77 25,72 31,56
Flights (Thousand)
2010 2011 2012 2013 2014 2015 2016 2017 2018
Türkiye 919 1.042 1.093 1.223 1.345 1.456 1.452 1.500 1.542
Atatürk 288 325 364 406 439 464 466 460 464
Sabiha Gökçen 106 121 126 150 186 219 232 220 232
Antalya 148 164 160 171 177 174 127 159 190
TURKEY FLIGHT AND PASSENGER DATA
ACI – EUROPE AIR TRAFFIC REPORT
OAG – PUNCTUALITY REPORT
RUNWAY REPAIRS (JOINTS, CRACKS, PATCH ETC.)
RUNWAY REPAIRS (SMALL SLAB CHANGES)
RUNWAY RENOVATION
A BÖLGESİ B BÖLGESİ
Slabs Changed in
2018
Slabs Changing in
2019
Slabs Expected to be
changed after 2019
A BÖLGESİ
B BÖLGESİ
C BÖLGESİ
C BÖLGESİ
D BÖLGESİ
RUNWAY RENOVATION
D BÖLGESİ
Slabs Changed in
2018
Slabs Changing in
2019
Slabs Expected to be
changed after 2019
UNEXPECTED RUNWAY CLOSURES
Number of Runway Closure for an Urgent Repair Need
ONGOING PROJECTS
- 2 nd RUNWAY
- SUBWAY CONNECTION
2 nd RUNWAY PROJECT
Güney Bölge
Yeni Hangarlar
Alanı
Yeni Kargo
Apronu
II.PİST Orta Apronlar
Kule ve RFFS
I.PİST(mevcut) Terminal Yapısı
HEIGHT OF THE TOWER
WILL BE 91 M.
NEW ATC TOWER
SUBWAY PROJECT
PENDİK-SABİHA GÖKÇEN LINE
KAYNARCA-TUZLA LINE
KADIKÖY-KARTAL-KAYNARCA LINE
MARMARAY
TERMINAL
CONNECTION
SUBWAY (METRO) CONNECTION
24
SATALLITE
PIERS
NEW CARGO
TERMINAL
MULTI STOREY
CAR PARK
TERMINAL III
MAX. CAPACITY SAW
ANY QUESTIONS??
Barcelon
a Gatwick Stockhol
m
Frankfurt Munich Heathrow