savannah cruise ship study phase i report presentaion 06-24-13

44
1 Date: October 13, 2010 June 25, 2013 Savannah Cruise Feasibility Study CRUISE SHIP STAGING AREA STUDY Phase I Report Presentation

Upload: jhayman09

Post on 06-May-2015

94 views

Category:

Travel


2 download

TRANSCRIPT

Page 1: Savannah cruise ship study phase i report presentaion  06-24-13

1

Date: October 13, 2010

June 25, 2013

Savannah Cruise Feasibility Study

CRUISE SHIP STAGING AREA STUDY

Phase I Report Presentation

Page 2: Savannah cruise ship study phase i report presentaion  06-24-13

2

BEA’s Team:

Page 3: Savannah cruise ship study phase i report presentaion  06-24-13

3

REPORT PRESENTATION – June 25, 2013 Phase One, CRUISE SHIP STAGING AREA STUDY

Savannah Cruise Feasibility Study

I - Overview of Study:

The scope of the project methodology analyzed three sites for a

potential Cruise Terminal capable of handling in range of 2,700 passengers and docking/berthing station. . The scope of this study evaluated environmental impacts, navigational challenges, and compatibility with the Georgia Ports Authority (GPA) vessel operations on the Savannah River, technical investigations, utility/traffic coordination, site challenges, docking requirements and identification of potential challenges with each site. The Phase I report has taken into consideration and evaluated the waterside / marine conditions and general infrastructure existing at each of the three sites and provided a tabulation of ranking ranging from Most Desirable to Least Desirable.

Page 4: Savannah cruise ship study phase i report presentaion  06-24-13

4

REPORT PRESENTATION – June 25, 2013 Phase One, CRUISE SHIP STAGING AREA STUDY

Savannah Cruise Feasibility Study

I - Overview of Study (Continued)-

The report has been developed on the basis of information gathered and developed from meetings with and / or from information provided by: ; The U.S. Army Corps of Engineers,

Savannah Pilots Association,

United States Coast Guard,

U.S. Fish and Wildlife Service,

National Marine Fisheries Service,

Georgia Department of Natural Resources,

Colonial Oil,

Limited contact with Georgia Ports Authority,

Georgia Archaeological Site File

Georgia’s Natural, Archaeological and Historic Resources GIS.

Page 5: Savannah cruise ship study phase i report presentaion  06-24-13

5

Cruise Vessel Development Over Time V

es

se

l S

ize

s

900-1050 FEET

Up To 30

20-36

26-30

26-34

1960 ‘ s

1970 ‘ s

1980 ‘ s

+1990‘ s

400-500

600

1200-2000

2600-3800

18

20

80

90-150

800 FEET

500 FEET

400 FEET

Ship

Displacement

(In Thousands Grt.)

Passengers Drafts Air Drafts

140-175

160-180

-

-

960-1250 FEET

30-34 3500-5000 150-250 +/- 200

+2000‘ s

Page 6: Savannah cruise ship study phase i report presentaion  06-24-13

6

Page 7: Savannah cruise ship study phase i report presentaion  06-24-13

7

Carnival Vessel

Lineup

Royal Caribbean Vessel

Lineup

Page 8: Savannah cruise ship study phase i report presentaion  06-24-13

8

Critical Demographics and Psychographics within a One Day Drive of Savannah and

Comparables (2009)

Source: SRDS, PSI, Google Maps, MapInfo

SAV JAX CHS MOB

mil mil mil mil Demographics (Persons or Households)

2009 Population 56.4 46.2 44.3 42.0

2009 Population Age over 55 14.5 11.9 11.1 9.8

White Collar Workers 15.3 12.6 12.1 11.1

Households with Income $75,000 or more 5.9 4.9 4.6 4.1

Persons over 25 with Some College or More 18.8 15.5 14.6 13.0

Psychographics (Adults)

Interested in The Arts 15.4 12.6 11.9 10.8

Rely on Newspaper to Keep Me Informed 15.0 12.3 11.7 10.7

Prefer Specialty Stores because Have Best Brands 8.5 7.0 6.6 6.1

Do Some Sport/Exercise Once a Week 21.1 17.2 16.4 15.0

Typically Avoid Watching TV Commercials 18.9 15.4 14.8 13.5

2009 Departing Passengers (in 1000's) 188.2 37.4 134.6

Within a One Day Drive of:

Page 9: Savannah cruise ship study phase i report presentaion  06-24-13

9

REPORT PRESENTATION – June 25, 2013 Phase One , CRUISE SHIP STAGING AREA STUDY

Savannah Cruise Feasibility Study

1- General Locations of Sites A, B, and C

2- General Characteristics of Sites A, B, and C

3- Site Analysis and Comparisons: Each of the three sites; A, B, and C were studied and the report presents the

findings for the following parameters for each of the sites, • SITE & INFRASTRUCTURE DATA

• Location • Site Acreage • Distance to Major Highway • Water and Sewer System • Electrical Service Availability

• NAVIGATION & HYDROGRAPHIC INFORMATION • WATER SIDE STRUCTURES • PRELIMINARY DREDGE ANALYSIS • UPLANDS NATURAL RESOURCES • MARINE BIOLOGICAL HABITATS • UNDERWATER ARCHEOLOGY • OTHER ISSUES

Page 10: Savannah cruise ship study phase i report presentaion  06-24-13

10

Cruise Terminal Sites For Analysis

SITE A:

SILO TRACT

SITE B

POWELL DYFFRYN

TRACT

SITE C

SAVANNAH RIVER

LANDING

Page 11: Savannah cruise ship study phase i report presentaion  06-24-13

11

Site A: Silo / Atlantic Cement Tract

Page 12: Savannah cruise ship study phase i report presentaion  06-24-13

12

Site A: Silo / Atlantic Cement Tract

Page 13: Savannah cruise ship study phase i report presentaion  06-24-13

13

Site B: Powell Dufferyn Tract

Page 14: Savannah cruise ship study phase i report presentaion  06-24-13

14

Site B: Powell Dufferyn Tract

Page 15: Savannah cruise ship study phase i report presentaion  06-24-13

15

Site C: Savannah River Landing Tract

Page 16: Savannah cruise ship study phase i report presentaion  06-24-13

16

Site C: Savannah River Landing Tract

Page 17: Savannah cruise ship study phase i report presentaion  06-24-13

17

Phase I - Project Issues Access to Major Highways –

Level Of Service (LOS) rankings obtained from 2004 MPC traffic congestion study.

Page 18: Savannah cruise ship study phase i report presentaion  06-24-13

18

Site & Infrastructure - Location

SITE A:

SILO TRACT

SITE B

POWELL DYFFRYN

TRACT

SITE C

SAVANNAH RIVER

LANDING

Page 19: Savannah cruise ship study phase i report presentaion  06-24-13

19

Site & Infrastructure - Acreage

A

B

C

Site Area: +/- 21.5 Acres

Site Area: +/- 14.5 Acres

Site Area: +/- 55 Acres

Page 20: Savannah cruise ship study phase i report presentaion  06-24-13

20

Site & Infrastructure – Distance to Major Highway

Level Of Service (LOS) rankings obtained from 2004 MPC traffic congestion study.

Page 21: Savannah cruise ship study phase i report presentaion  06-24-13

21

Site & Infrastructure – Water & Sewer (costs associated with selected site for these improvements investigated in next phase of the study)

Site A- Water:

• Existing 16 “ main @Hutchinson Island Rd.

• Need 12” main extended 650 ft.

Sewer :

• Need 6-8” main extended 650 ft.

• Existing 10” main @Hutchinson Island Rd.

Site B- Water:

• Existing 16” water main stubbed out at Wayne Shackleford Pkwy

• Need 12” main extended 2,300 ft..

Sewer :

• Existing stubbed out 8” force main at Wayne Shackleford Pkwy

Site C- Water:

• Existing 12” main serving site but needs 1,000 ft extension for terminal

Sewer :

• System never completed, needs completed and accepted by City

Page 22: Savannah cruise ship study phase i report presentaion  06-24-13

22

Site & Infrastructure – Electrical Service

Site A- • 3 Phase - @ 25 kV available at site

• 12-14 kV required for cruise terminal service

• Do not foresee major electrical changes needed to serve site

Site B- • 3 phase overhead available now at this site

• System modifications/maintenance needed for service

Site C- • Does not have electrical wiring on site, but private conduits

and manhole are existing at the site

• GA Power indicated complex process to get power to

terminal site

• Site would have largest projected cost of the 3 alternative

sites

• Need electrical power study to consider alternative methods

vs. cost

Page 23: Savannah cruise ship study phase i report presentaion  06-24-13

23

Navigation & Hydrographic Information

Issues Applicable To All Sites- Ships greater than 800 ft turning to occur upriver at King’s Landing

For maneuvering Pilots request additional 100 ft mooring area each end of ship

Seasonality effects passage, such as in the spring when fog is common, limit vessel operations in the river. Other ports like Tampa and New Orleans have similar fog from time to time.

Military Outload Division (MOD) use of the Ocean Terminal facilities and the Naval Vessel Protection Zone (NVPZ) in place and enforced by the US Coast Guard (CG) during the course of MOD operations (100 yard intercept zone / 500 yard escort zone).

US Coast Guard (CG) reports that the regulations concerning LNG vessels could cause cruise ship delay in transit due to one of these LNG vessels transiting the area. Such operational coordination requirements common at most major ports

Site A- Currently only approx. 656 ft river frontage, (need 1,000 ft) therefore, additional

waterfront access to be acquired

Shoaling reported by Pilots in vicinity of site

Should site be selected for further consideration, the NVPZ restrictions may also apply while the cruise ship is docked

Page 24: Savannah cruise ship study phase i report presentaion  06-24-13

24

Navigation & Hydrographic Information Site B-

Currently only approx. 602 ft river frontage, (need 1,000 ft) therefore, additional waterfront access to be acquired

Shoaling reported by Pilots in vicinity of site

Concern to the Pilots, due to the site’s location within a turn in the river, there is potential for a “suction” effect on vessels that are moored in this area caused by passing vessels making the turn

Site C- Some concern of steering large vessels in vicinity of site due to curve in river

Pilots preferred site location due to less surrounding berthing facilities which eases maneuvering

Page 25: Savannah cruise ship study phase i report presentaion  06-24-13

25

Water Side Structures Site A-

• Existing in-water structure consists of 4 mooring structures each spaced approximately 125 feet apart. These structures are located approximately 50 feet from the shore and are connected by supported access ways that appear to

be in good condition.

• New waterside mooring/berthing structures will have to be constructed

Site B-

• Existing structure consists of center berthing area with 4 mooring structures (2 on each side)

• Riparian boundary in relation to existing structures needs further investigation

• Engineering analysis needed to assess potential of integration into new

cruise ship berth (new vs. modification)

Site C-

• Approx 1,984 ft of bulk head and river walk

• Not designed to berth large vessels but may be integrated into cruise berth infrastructure

• Marine structures for berthing cruise ships needs engineering analysis (modifications)

Page 26: Savannah cruise ship study phase i report presentaion  06-24-13

26

Preliminary Dredge Analysis

Site A- Approx 130 ft from Fed Channel to existing mooring structures

Approx 34,800 cubic yards of dredging may be needed to achieve 34 ft draft

Prior land use assessment needed to evaluate source material/contributions regarding dredge spoils as contamination may be an issue

Existing dredge pipeline adjacent to berth area will need to be addressed

Sediment analysis required

USCE need to approve a dredge disposal management plan

(Permit) Conditional on salt marsh impact and adequate river frontage, site has high probability of obtaining a USCE Sect 10/404 permit

Site B- Approx 120 ft from Fed Channel to existing mooring structures Approx 24,300 cubic yards of dredging may be needed to achieve

34 ft draft Prior land use assessment needed to evaluate source

material/contributions regarding dredge spoils as contamination may be an issue

Sediment analysis required

USCE need to approve a dredge disposal management plan

Page 27: Savannah cruise ship study phase i report presentaion  06-24-13

27

Preliminary Dredge Analysis

Site B- (Con’t) (Permit) Conditional on good sediment analysis, high likelihood of

approval for initial and ongoing maintenance dredging

(Permit) Conditional on salt marsh impact and adequate river frontage, site has moderate probability of obtaining a USCE Sect 10/404 permit

Site C- Approx 150 ft from Fed Channel to existing mooring structures

Approx 38,500 cubic yards of dredging may be needed to achieve 34 ft draft

Prior USCE Sect 10/404 permit (2007) for Savannah Riverwalk Extension appears to have been issued and project extended

Prior land use assessment needed to evaluate source material/contributions regarding dredge spoils as contamination may be an issue

USCE need to approve a dredge disposal management plan

Site has high probability of obtaining a USCE Sect 10/404 permit

Existing development at site likely to make terminal permitting much easier

Page 28: Savannah cruise ship study phase i report presentaion  06-24-13

28

Uplands Natural Resources Site A-

Site B-

Site C-

• For all three (3) sites, a review of the USFWS Chatham County list

indicated that three (3) plant species as potentially occurring in

Chatham County. Potential impacts will have to be assessed during

Phase II of the study; once a survey with tree information is available,

should any of these sites be selected.

Page 29: Savannah cruise ship study phase i report presentaion  06-24-13

29

Marine Biological Habitats Site A-

Site B-

Site C-

• For all three (3) sites, a review of the USFWS Chatham County list

indicated that seventeen (17) animal species as potentially occurring

in Chatham County. Potential impacts will be further assessed during

Phase II of the study should any of these sites be selected. Although

no listed species were observed during this study, due to the presence

of potentially suitable habitat for the federally protected species, it

cannot be guaranteed that listed species would not or could not use

this site currently or in the future.

Page 30: Savannah cruise ship study phase i report presentaion  06-24-13

30

Underwater Archeology Site A-

•One submerged resource (poorly preserved Twentieth Century wooden barge)

located at this site

• USACE, Savannah District confirmed this site is not of underwater archeological

concern

Site B- • Underwater survey identified no underwater archeological resources at this site

• USACE, Savannah District confirmed this site is not of underwater archeological

concern

Site C- • USACE issued permit in 2007 for this site. Work undertaken at that time included

an archaeological survey of the in-water and land side of the property and historic

resources (boat wreckage, portion of old wharf, bricks) were encountered at this site

• A Programmatic Agreement between the City of Savannah, USACE, Savannah

District and Georgia SHPO, was signed in January 2007 detailing the required

cultural resource studies for the Riverwalk project at this site

•Further work on additional components of the archaeological survey may be required

in order to accommodate a Cruise Terminal development at this site (use

modification may trigger revisions)

Page 31: Savannah cruise ship study phase i report presentaion  06-24-13

31

Other Issues: Site A-

• This site offers approximately 6 to 10 acres for potential ancillary mix-use

development to serve cruise passengers and the general public; subject to local

parking requirements for the development of a cruise terminal facility.

• Refueling at this site will likely result in the bunker barge potentially

extending into the federal channel.

• This site is directly across Ocean Terminal site. Should this site be used for a

cruise terminal, cruise ships calling at this facility; while the Military Outload

Division (MOD) is in operation at Ocean Terminal, are subject to berthing

restrictions associated with the NVPZ 100 yard “intercept zone” restriction.

Page 32: Savannah cruise ship study phase i report presentaion  06-24-13

32

Other Issues: Site B-

• This site offers approximately 4 acres for potential ancillary mix-use

development to serve cruise passengers and the general public; subject to local

parking requirements for the development of a cruise terminal facility.

• Refueling at this site will likely result in the bunker barge potentially

extending into the federal channel.

•Should this site be used for a cruise terminal, cruise ships will use the King’s

Landing turning basin. While the MOD is in operation at Ocean Terminal,

cruise ships sailing upstream to access the King’s Landing turning basin may

be subject to transiting through the NVPZ 100 yard intercept zone and 500

yard escort zone restrictions.

Page 33: Savannah cruise ship study phase i report presentaion  06-24-13

33

Other Issues:

Site C- • This site offers approximately 40 to 45 acres for potential ancillary mix-

use development to serve cruise passengers and the general public; subject

to local parking requirements for the development of a cruise terminal

facility.

• Direct access for all bus and truck traffic may be achieved by routing such

traffic to a roadway running north to south along the east boundary of the

property to access President Street as well as Truman Parkway.

•Cruise vessels refueling at this site may accommodate the bunker barge

without extending into the federal channel. This site currently has more

linear distance from the existing wharf to the federal channel; final facility

design will ultimately dictate these distances.

•Should this site be used for a cruise terminal, cruise ships will use the

King’s Landing turning basin. While the MOD is in operation at Ocean

Terminal, cruise ships sailing upstream to access the King’s Landing turning

basin may be subject to transiting through the NVPZ 100 yard intercept and

500 yard escort zone restrictions.

Page 34: Savannah cruise ship study phase i report presentaion  06-24-13

34

SITE RANKING SCORE CARD

Page 35: Savannah cruise ship study phase i report presentaion  06-24-13

35

Conclusions and Recommendations

• Study identifies that each of three sites have issues and concerns

that need to be addressed should it be chosen as

the preferred site by the City of Savannah to move forward to the

next pre-development/permitting stage.

• None of the three sites identified a highly significant negative

factor that the team considered as a “fatal flaw” which would

would eliminate it from further consideration.

• Analysis was limited to the critical factors identified and studied for

the alternative sites.

• Site rankings were presented in a score card format for presentation

purposes. Using the method for comparing the three sites, the ranking

of the sites are:

First Place: THE SAVANNAH RIVER LANDING (SRL) TRACT

Second Place Tie: Powell Dufferyn Tract and Silo / Atlantic Cement

Tract

Page 36: Savannah cruise ship study phase i report presentaion  06-24-13

36

Questions & Discussion

Thank you.

Page 37: Savannah cruise ship study phase i report presentaion  06-24-13

37

Overview of Next Phase Two: Cruise terminal Site & Landside Facilities Planning

I- Land Side Due Diligence

II- Site Analysis (including qualitative testing)

III- Conceptual Cruise Terminal/Site Plan Design

IV- Traffic Analysis

Final Report – Project deliverables

Page 38: Savannah cruise ship study phase i report presentaion  06-24-13

38

I - Land Side Due Diligence

Assemble available information

Historical Engineering data

Available City and GIS data

Zoning and development constraints

Page 39: Savannah cruise ship study phase i report presentaion  06-24-13

39

II - Site Analysis

Existing infrastructure

Soils

Environmental

Natural Resources

Wetlands

Site Contamination

Cultural Resources

Zoning & development permitting analysis

Page 40: Savannah cruise ship study phase i report presentaion  06-24-13

40

II - Site Analysis (Con’t) Site Qualitative Analysis & Testing USACE Wetland Delineation / Re‐verification plan Georgia Department of Natural Resources Marshlands

Delineation / Re‐verification plan Coordination meeting with USACE pertaining to the Sediment

Testing Scope of Work definition and Sampling Analysis Plan

Dredge Spoils Testing per USACE Sediment Testing Scope of Work; includes preparation of a sampling and analysis plan, dredge sediment and water sampling, and evaluation of dredge spoil disposal options.

Page 41: Savannah cruise ship study phase i report presentaion  06-24-13

41

III - Conceptual Cruise Terminal/Site Plan Design

Define programmatic elements for terminal

Develop Terminal Design Concept for each site Ingress & egress

Parking

Utility infrastructure

Location of buildings, docks, and ancillary facilities

Ingress and egress for passenger cars, busses/public transit and service vehicles

Cruise vessel docking footprint and proximity to Savannah River channel

Open space and buffers

Adjacent existing and proposed development

Preliminary probable estimate of construction cost and schedule

Page 42: Savannah cruise ship study phase i report presentaion  06-24-13

42

IV - Traffic Analysis

Project trips generated by terminal

Identify routes to primary highways

Access to public transit

Impacts to existing roadways Preliminary Traffic Impact Report based on

information gathered and available from local and state jurisdictions.

Provide Traffic Impact Analysis that includes counts at up to 4 intersections, exclusive of signal warrants or timing analysis

Page 43: Savannah cruise ship study phase i report presentaion  06-24-13

43

Project Deliverables

Phase 1 & 2 – Provide support documentation

needed for USACE Permit applications.

The project proponent (not mentioned in RFP); will need to also apply for and receive a Coastal Marshlands Protection Act Permit from the State of Georgia Department of Natural Resources – Coastal Resource Division

Page 44: Savannah cruise ship study phase i report presentaion  06-24-13

44

Questions & Discussion

Thank you.