sarma emilia-romagna & parma activity report end of june, 2010 budapest, june, 28th

9
SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

Upload: orly

Post on 06-Jan-2016

30 views

Category:

Documents


2 download

DESCRIPTION

SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th. WP1 - Partner Project Management (of project relevance). ANPAR withdrawal – ER acquisition of activities and budget. ANPAR activities revision WP2: international meeting at ECOMONDO, Rimini, Nov. 2010 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

SARMaEmilia-Romagna & Parma

Activity report

End of June, 2010

Budapest, June, 28th

Page 2: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

WP1 - Partner Project Management (of project relevance)

ANPAR withdrawal – ER acquisition of activities and budget

• ANPAR activities revision WP2: international meeting at ECOMONDO, Rimini, Nov. 2010 WP3: 2 new pilot sites in ER territory, best definition of LCA manual

output WP4: Best integration of Recycling in WP4.2 (ER task leader) in

term of Sustainable Supply, Planning, GIS

• Proposal under valuation by JTS• New partnership agreement under signing

• ANPAR budget revision

Page 3: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

WP COMPLETED IN PROGRESS NEXT STEPSOPEN PROBLEMS

WP 2.2Parma (Nov 2009) SARMa presentationLocal

Bologna (Dec 2010) WP3 – Pilot sites, GISRegional\national

Parma (May 2011) WP4 – Model sites, GIS, SSMRegional\national

-

WP 2.3Bologna (Jun 2009) Project Kick-off

Rimini (Nov 2010) Ecomondo WP3.3, 3.4 RecyclingInternational

- -

WP2 – Meetings directly managed by ER+Parma

Page 4: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

WP COMPLETED IN PROGRESS NEXT STEPS OPEN PROBLEMS

WP3.1 pilot site quarry restoration

SDB, BSR, PSR - - -

WP3.2 pilot site Illegal quarrying

SDB, BSR, PSR

PSR updatefinal results of LIDAr remote-sensing experimentation

- -

WP3.3 coord.(See Blengini report for details)

-

Coordination BSR-R, SDB-RLCA document, C&DW document

Ecomondo Nov 2010C&DW manual will be presented a draft of the LCA guidelines will be provided

Several documents by other partners are still missing: see Blengini report

WP3.3 pilot sites recycling

-SDB-R, BSR-R for the new pilot sites “Madregolo” and “Castellarano”

-

Some problems in collecting required information at “Castellarano”

WP3.4 synthesis SQ SQ-R -

In Italy data are difficult to gather at national/regional scale (provincial scale may be the best)

WP3 – 3.3 Task coordination (dark colors); 3.1, 3.2, 3.4 contributions

Page 5: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th
Page 6: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th
Page 7: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

WP ACTIVITIES COMPLETED IN PROGRESS NEXT STEPS OPEN PROBLEMS

WP4.1 SQSQ4.1 (some details are under revision of translation)

-

How about the SSM opinion pool by Tamas ? (for which stakeholders? In national language?)

WP4.2 coordination

•Preparation of SQ4.2; •GIS activities workplan•Definition and preparation of BSR for 3 Model Site (MS) 4.2

Collecting SQ4.2; Sinthesis Report 4.2 (+statistical synthesis from web questionnary )

Synthesis Report 4.2:3 boxes Model Sites: Pella (???), Trebbia (natural area), Styria (economy) 1 box GIS-ER

GIS activities require contributions of Deborah and Fotini (Nikos); no contribution from Pella for Model Site

WP4.2 •SQ•Model site (MS) quarrying in natural area

•SQ4.2 draft; •Model Site Report (MSR) draft

•SQ4.2 •MSR

-

WP4/5 - -

Contr. to Recommendations for GIS; Contributions to WP4+5 final reports about “Planning for sustainability”

-

WP5.3 -

Contribution for WP4+5 manual: Best Practices for post-quarrying restoration

-

WP4/5 – 4.2 Task coordination (dark colors); 4.1, 5.3 contributions

Page 8: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th
Page 9: SARMa Emilia-Romagna & Parma Activity report End of June, 2010 Budapest, June, 28th

WP ACTIVITIES COMPLETED IN PROGRESS NEXT STEPS OPEN PROBLEMS

WP 2.2Meeting Parma SARMa presentation (11/09)

Meeting Bologna WP3 (12/10) Meeting Parma WP4 (05/11) -

WP 2.3 KOM Bologna (6/09) Ecomondo WP3.3, 3.4 (11/10) - -

WP 3.1 (Lanca dei Francesi)

SDB, BSR, PSR - - -

WP 3.2 (Taro River)Required: SDB, BSR, PSR*Indirect: LIDAr survey of the Taro river alluvial fan

Integration to PSR (addendum including the final results of LIDAr remote-sensing sperimentation,).

- -

WP 3.3 -SDB-R, BSR-R for pilot sites “Madregolo” and “Castellarano”.

-Some problems in collecting required information at “Castellarano” site.

WP 3.3 coordination -Coordination BSR-R, SDB-RLCA document, C&DW document

Meeting Rimini (Ecomondo): 3-6 Nov 2010C&DW manual will be presented a draft of the LCA guidelines will be provided

Several documents are still missing: see note below

WP 3.4 SQ SQ-R -Some data are difficult to gather at national/regional scale, whereas at provincial scale may be easier.

WP 4.1 SQ4.1* -SSM opinion pool Tamas ??? (for stakeholders? national language?)

WP 4.2 - SQ4.2 (final draft); PSR Trebbia (final draft) Box GIS-ER in Sinthesis Report 4.2 -

WP 4.2 coordination

Preparation of SQ4.2; GIS activities workplanPreparation of BSR for pilote site 4.2

Collecting SQ4.2; Sinthesis Report 4.2 (+statistical synthesis from web questionnary )

3 Boxes pilot-sites 4.2: Pella (???), Trebbia (natural area), Styria (economy) in Sinthesis Report 4.2

GIS activities require contributions of Deborah and Fotini (Nikos); no contribution from Pella for Pilot Site.

WP 4/5 - -Contr. to Recommendations for GIS; Contributions to WP4+5 final reports about “Planning for sustainability”

-

WP 5.3 - -Contribution for WP4+5 manual: Best Practices for post-quarrying restoration

-

ER+Parma Technical report (June, 2010) - summary tableDark colors for activities at Project coordination level – ER task leader