SAP Migration to Novell LinuxValue Proposition and Process
Global Fujitsu SAP Competence Center Walldorf, June 2009
Executive Summary – SAP Migration
Project Details: definitions, requirements, check services
Standard SAP OS/DB Migration: project phases and steps
Fujitsu Migration Services
Agenda
© Copyright 2009 Fujitsu Technology Solutions1
© Copyright 2009 Fujitsu Technology Solutions
Global and local pool of experienced
and certified migration consultants.
Global Fujitsu SAP Competence Center
supporting the design of the best fit solution.
Standardized & proven toolset for the migration.
SAP OS Migration checks as part of their
safeguarding program (free service).
Fujitsu ensured for 200+ FlexFrame for SAP
customers a smooth transition from “Unix” to “Linux”.
The SAP tools have been used in thousands
of customer projects for more than 10 years.
SAP providing
Fujitsu and partners leveraging
Our project experience
A team to ensure smooth transition
3
More than 200 migration projects
Customers who have successfully migrated to FlexFrame and Novell Linux
© Copyright 2009 Fujitsu Technology Solutions
"We migrated from HP-UX to Novell Linux within a
FlexFrame for SAP environment back in 2004. To
be perfectly honest it was simpler than expected,
even with lower efforts on our side than for a usual
SAP upgrade project. The standardized toolset
and services from SAP plus the expertise from
Fujitsu and our System Integrator ensured a very
smooth transition - on time and within budget.“J.G.M. Kroon, ICT Architect, ICT AS Solutions CC, TNT
Post
““Fujitsu even took care of problems they were not even responsible for. Our experience was really very positive.”Joachim Friedemann, Team Manager Hosting and Database Technology, Rechenzentrum Leipzig e.V.
“Without exception, Fujitsu delivered exactly what was promised in terms of technology and cost.”Christian Baier, IT Manager SAP Base, REHAU AG + Co
Aerospace & Defense
Automotive
Banking & Insurance
Chemical
Consumer
Engineering,
Construction &
Operations
4
SAP migration: overview
History. 15 years ago SAP identified the need for a standardized migration processdue to:
New platform decisions (x86) in a customer data centers
Mergers & acquisitions
Objective. Ensure a smooth transition via:
Standardized toolset
Support services
Result. SAP OS/DB Migration Check as part of SAP’s Safeguarding program. This service is part of standard SAP maintenance contract.
Availability. Toolset available for all major SAP components:
R/3 3.0D, 3.X, 4.X, ECC5, ECC6…
BW, CRM, SCM, SRM,…
Experience:
Thousands of migrations between various platforms (incl. TB databases)
All major SAP consultants offer required Migration Services
© Copyright 2009 Fujitsu Technology Solutions5
SAP OS/DB Migration Check
Description:
The OS/DB Migration Check is mandatory when migrating a productive system. The service delivery then includes all systems in the system landscape conenrned.
If full support for the migration is required (be it a production system or not), the services of a technical consultant with special certification for OS/DB migration must be ensured.
Value proposition:
SAP OS/DB Migration Check minimizes technical risk involved in an operating system and/or database migration and avoids unforeseen costs that can occur during the migration.
Benefits of SAP OS/DB Migration Check :
Efficient, technically robust operation of the new operating system and/or database is achieved with minimum cost
The migration project is accelerated to get a faster return on your investment
Expensive system downtimes during the migration are minimized
System resource usage is optimized to make the most of your IT investment
© Copyright 2009 Fujitsu Technology Solutions6
Migration steps: high-level
1. Select your preferred partner for the migration project -> SAP certified migration consultant
2. Initiate SAP OS/DB Migration Service with SAP
3. Run Remote Project Audit Session
4. Define joint migration plan
5. Execute test migration
6. Run analysis session (4-6 weeks before final migration)
7. Migrate non-production environments
8. Execute final migration
9. Run verification session (2-4 weeks after migration)
Project timeline: from 6 weeks to 3 months depending on the number of SAP systems to be migrated and availability to test and access the systems.
© Copyright 2009 Fujitsu Technology Solutions7
Project detailsDefinitions, requirements, check services
© Copyright 2009 Fujitsu Technology Solutions8
Definitions
Homogeneous System Copy
The copy of SAP system to another hardware with the same OS and database is called a homogeneous system copy. -> No change of DB and OS
Heterogeneous System Copy = SAP OS/DB-Migration
If the target SAP system will run on a different operating system (OS) and/or a different database system (DB) as the source SAP system, then this is called a heterogeneous system copy. -> Change of DB and/or OS
UNICODE Conversion
An SAP System is converted to UNICODE during a system copy. This can be a homogeneous or heterogeneous system copy.
© Copyright 2009 Fujitsu Technology Solutions9
Successful Migration - Requirements(1)
The Migration has to be done by a certified SAP Technology Consultant for OS/DB migrations:
Certified Technical consultant (at least 4.x)
Special certification for migration (TABC92)
Consultants are on SAP’s migrations consultant list
Experience in heterogeneous system copies (migrations)
SAP data dictionary knowledge
Advanced knowledge of the source database
Advanced knowledge of the target database and operating system
© Copyright 2009 Fujitsu Technology Solutions10
Successful Migration – Requirements(2)
Establish SAP Migration Project Team
Migration Consultant
Project Manager internal/external (depending on project)
Customers technical Consultants (system administrators)
Customers application Consultants (developers)
Customers Power Users for tests and functionality checks
Customers IT management
The migration partner and customer are responsible for the migration. SAP provides back-office support only
© Copyright 2009 Fujitsu Technology Solutions11
Successful Migration – Requirements(3)
Detailed project plan for migration has to be sent to SAP
Order the new system hardware based on a proper sizing
Order R/3 license to reflect the new platform data
Order an OS/DB Migration Kit (Mat.-No. 52002792); this is platform independent(release <= 4.6, from 6.x the tools are on the Installation Master)
Order an Installation Kit for the new platform
Order SAP Migration Check Services for a productive system
Test/migrate the functionality of external interfaces and other applications
Printing system, archive, job scheduling, etc.
External connections (ALE, RFC, NFS, …)
Integrate the migrated system to customer’s High Availability, Backup and System Management solution
The source system has to be available 4 weeks after the live migration
© Copyright 2009 Fujitsu Technology Solutions12
Successful Migration – Requirements(4)
SAP’s prerequisites for the SAP OS/DB Migration Check
SAP systems must be SAP R/3 3.0D or newer
The platform combination chosen is supported by SAP http://service.sap.com/platforms
Remote connection to SAP and an installed SAProuter
SAP EarlyWatch Alert should be running
SAP strongly recommends an implemented SAP Solution Manager
© Copyright 2009 Fujitsu Technology Solutions13
SAP Migration Check Services (I)
Remote Project Audit
Customer completes a questionnaire before the Remote Project Audit is scheduled
Information from the questionnaire is used to determine:
The necessary precautions for a smooth migration
If your requirements are realistic and can be met
Content
Collection of general company data
Checks if the new OS/DB combination is supported by SAP
Checks planning dates for non-productive and productive systems
Checks if the technical consultant is registered as a certified technical consultant with additional certification for OS/DB Migration and fulfills therequirements for executing OS/DB migration projects
© Copyright 2009 Fujitsu Technology Solutions14
SAP Migration Check Services (II)
Analysis Session
Checks whether current hardware is sufficient for the target system
Takes place four to six weeks before migrating
Performed on the source system
A report indicates whether hardware is sufficient and if parameter configuration is necessary
Analyze the performance of your system with respect to the average response times and total workload. The following is analyzed in detail:
Transaction profile check
Top time transactions by response time
R/3 table buffering
© Copyright 2009 Fujitsu Technology Solutions15
SAP Migration Check Services (III)
Verification Session
Checks the new operating system and/or database to verify the assumptions from the Analysis Session
Occurs two to four weeks after migration of the production system
Performed on the target system
Final report confirms configuration and makes recommendations for improvement
SAP prefers to schedule the service sessions well in advance. Thus service contracts should be signed as early as possible.
© Copyright 2009 Fujitsu Technology Solutions16
Standard SAP OS/DB MigrationProject Phases and Steps
© Copyright 2009 Fujitsu Technology Solutions17
Standard SAP OS/DB Migration
Project Phases and Steps:
PreparationThe preparation phase begins with the decision to move to a different OS or DB platform. At the end of this phase the equipment is installed, all key players are involved and a project plan is ready.
MigrationThe migration phase covers the actual system migrations, first a series of test migrations (repeated until the process is fully under control), followed by the “live” migration of the development, QA and production system.
Follow-upThe follow-up phase begins when the entire SAP landscape is operational on the new platform, and covers post-migration, validation and support activities.
© Copyright 2009 Fujitsu Technology Solutions18
Project Steps - Preparation (I)
Item Tasks Responsibility Remarks
1. Decision to migrate Customer Customer must carefully assess the impact that this change will have on his company’s IT.
2.Contact hardware and/or
DBMS vendorCustomer Proper sizing is a crucial task in the migration process.
3.Contact SAP contract
adminCustomer SAP must be informed to adapt the license.
4.Order OS/DB Migration Kit
(<= 4.6)Customer
Up to 4.6 migration tools are in the migration kit. From 6.x the tools are on the Installation
Master.
5.Order OS/DB Migration
Check ServiceCustomer
SAP will deliver three service sessions, two before and one after the productive migration.
This is only required for production systems.
6. Select migration partner Customer A Certified Migration Consultant is mandatory.
7. Inform key playersCustomer/
Migration ConsultantManagement, development, key users, technical personnel, etc. should be informed.
8. Create project planCustomer/
Migration Consultant
The project plan should contain information on: HW installation and configuration, timing for
test- and productive system migrations, user acceptance tests, printer configuration, external
communications and interfaces, backup and recovery, clustering and high availability.
© Copyright 2009 Fujitsu Technology Solutions19
Project Steps - Preparation (II)
Item Tasks Responsibility Remarks
9. Return SAP questionnaireCustomer/
Migration ConsultantWith the information of the project plan return the questionnaire to SAP.
10.Order equipment (HW
migration)Customer Review the configuration with the migration consultant.
11.Install equipment (HW
migration)HW partner The HW must be installed and the OS configured in compliance with the requirements of SAP.
12. First SAP check session SAPIn the Remote Project Audit session SAP uses the information provided in the questionnaire to
determine that your configuration fulfills all the requirements.
13. Adapt project plan based
on SAP feedback
Customer/
Migration Consultant
When SAP returns the report of the Remote Project Audit, the necessary technical and / or
planning changes have to be made.
© Copyright 2009 Fujitsu Technology Solutions20
Project Steps - Execute Migration
© Copyright 2009 Fujitsu Technology Solutions
The success of the productive migration depends highly on the quality
of the previous test work.Migration Consultant
Migrate productive
system9.
Migrating the QA system is optional. QA can also be rebuild on the
target system through a homogenous system copy of the productive
system.
Migration ConsultantMigrate / Copy QA
system10.
Custom ABAP code may contain features that are platform-
dependant, e.g. Native SQL.
Customer/
Migration ConsultantABAP developer tests4.
Migration Consultant
SAP
Customer/
Migration Consultant
Customer/
Migration Consultant
Customer/
Migration Consultant
Migration Consultant
Responsible
The development system is usually the first system of the live
landscape to be migrated.
Migrate development
system7.
The SAP Analysis Session will check whether the HW is sufficient for
the target system.
Second SAP check
session6.
The key application users must define a set of business reports, which
will validate the consistency of the data.User acceptance tests5.
It is important, that during the test migrations, where downtime is not
yet an issue the system is rigorously tested and tuned.
Technical
configuration and
tuning
3.
A start-to-finish guide on how to carry out the migration. It should also
contain a procedure handbook which describes the problems not
mentioned in the standard documentation.
Design / improve
documentation2.
Proper testing is absolutely crucial for the success of the project.
As a rule of thumb, two test migrations for a productive system should
be enough. Two weeks between test and live migration is a minimum.
Perform test migration1.
RemarksTasksItem
21
Project Steps - Follow-up
Item Tasks Responsible Remarks
1. Monitoring, tuning, supportCustomer/
Migration Consultant
The system will still need more than the usual attention after the go-live. Performance
monitoring is important in this phase.
2.Final SAP Check Session
(GoingLive Check)SAP
The third SAP Check Session is the Verification Session takes place between two and six
weeks after the migration of the production system. The assumptions of the Analysis session
are verified and the session also identifies and provides corrective advice for any bottlenecks
and problems observed in the system.
3.Keep old system as
reference
Customer/
Migration ConsultantThe old target system should remain available for several weeks after the migration.
© Copyright 2009 Fujitsu Technology Solutions22
© Copyright 2009 Fujitsu Technology Solutions
Project Management
Solution Concept
Inspection ServicesTool based Assessment
Solution Preview
Service Level Management
Consult Design Build MaintainOperate
Technical IT Infrastructure Services
AssessmentIT Infrastructure
Solution Specification
Migration Specification Migration Service
Upgrade Services
Audit Service
Go Live Services
Solution Support
Financial TCO and ROI Services
TCO = Total cost of ownership
ROI = Return on investment
ROI Estimate ROI Predict ROI Deliver
Operational
Specifications
Business Critical Computing (BCC) Services
Customer Briefing
Solution Implementation
Customer specific Trainings
Strategy Workshop
Inspection ServicesTool based Modeling
Inspection ServicesTool based Verification
Hardware Installation
Operational
Implementation
Configuration & Sizing
Proof of Concept Rollout Services
Operational Services
Service Packs
Service Contracts
Software Services
Service Portfolio for SAP IT Infrastructure
Fujitsu Migration Services
TCO / ROI Evaluation
24
Fujitsu Migration Services (I)
Migration Specification
Our "Migration Specification" Professional Service provides you with a detailed concept for migrating your SAP systems to your future SAP IT infrastructure.
The "Migration Specification" Service covers three phases:
Phase I: Workshop for coordinating the "Migration Specification"
Phase II: Creation of the document "Migration Specification SAP IT Infrastructure"
Phase III: Acceptance of the "Migration Specification" by the customer
© Copyright 2009 Fujitsu Technology Solutions25
FSC Migration Services (II)
Migration Service
Migration of the application from the source system to the target system
Migration services includes:
Basic Preparation
Implementation in accordance with the documentation "Migration Specification for SAP IT Infrastructure"
Follow-up activities in accordance with SAP guidelines and the "Migration Specification for SAP IT Infrastructure"