SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

Upload: osborne-russell

Post on 18-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

S A N M A R C O S U N I F I E D S C H O O L D I S T R I C T

A U G U S T 1 9 , 2 0 1 4

FACILITIES UPDATEGOVERNING BOARD MEETING

Page 2: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

2

Facilities Update: In Planning/Design

• Proposition 39: Energy Jobs Act• “Kick-off” meeting• Conduct campus analyses• Create proposed project list• Submit proposals to CEC for approval• Construct projects

• Proposition K: Campus Modernization Projects• Preliminary master plans• Preliminary site surveys• Special Board Meeting “Workshop”

8/19/2014

Page 3: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

3

Facilities Update: In Construction

• Woodland Park MS Modernization Project

• Professional Learning Center (PLC) – NCREC – S

• Shade Shelters – MHHS, SEMS, DSC, SME

• Facilities Needs for 2014-2015 – AD, DSC, SEMS

• New Classroom Buildings – CAR, DSC, SME

• Technology Infrastructure Projects

• San Marcos K-8 School

8/19/2014

Page 4: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

4

Facilities Update: In Construction

• Woodland Park MS Modernization Project: Aug. 2014• Completed final accessible ramp, casework (cabinets), and A/V equipment

8/19/2014

New Front Entry

Page 5: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

5

Facilities Update: In Construction

• Professional Learning Center (PLC) at NCREC – S• Professional Development

8/19/2014

Page 6: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

6

Facilities Update: In Construction

• Professional Learning Center (PLC) at NCREC – S• Professional Development - TOSAs

8/19/2014

Page 7: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

7

Facilities Update: In Construction

• Professional Learning Center (PLC) at NCREC – S• Centralized Kitchen

8/19/2014

Page 8: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

8

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Discovery ES• New Shade Shelter and reconstruct Walkway Cover

8/19/2014

Page 9: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

9

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Discovery ES• New Shade Shelter and reconstruct Walkway Cover

8/19/2014

Page 10: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

10

Facilities Update: In Construction

• Discovery ES• 1 temporary Portable Building• Until SMK8 opens

8/19/2014

Page 11: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

11

Facilities Update: In Construction

• San Elijo MS: Support for temporary enrollment growth for 2014-15 school year

School• 3 lunches• Large P.E. classes

Facilities• Shade Shelter for PE/Lunch

• Additional Basketball Courts

• Upper Field Power/Communications

8/19/2014

Page 12: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

12

Facilities Update: In Construction

• Facilities Needs for 2014-2015• San Elijo MS• New shade shelter, new basketball courts, new track perimeter

8/19/2014

Page 13: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

13

Facilities Update: In Construction

• Facilities Needs for 2014-2015• San Elijo MS• New shade shelter, new basketball courts, new track perimeter

8/19/2014

Page 14: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

14

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Mission Hills HS• New shade shelter for art and outdoor classroom

8/19/2014

Page 15: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

15

Facilities Update: In Construction

• Facilities Needs for 2014-2015• San Marcos ES• New shade shelter for Kindergarten area

8/19/2014

Page 16: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

16

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Alvin Dunn ES• New perimeter fence

8/19/2014

Page 17: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

17

Facilities Update: In Construction

• New Classroom Buildings• Anticipated enrollment growth

at CAR and SME

8/19/2014

Page 18: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

18

Facilities Update: In Construction

• Carrillo ES: 5-Classroom Permanent Building

8/19/2014

Page 19: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

19

Facilities Update: In Construction

• Carrillo ES: 5-Classroom Permanent Building

8/19/2014

Page 20: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

20

Facilities Update: In Construction

• San Marcos ES: 4-Classroom Permanent Building

8/19/2014

Page 21: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

21

Facilities Update: In Construction

• San Marcos ES: 4-Classroom Permanent Building

8/19/2014

Page 22: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

22

Facilities Update: In Construction

• San Marcos ES: 4-Classroom Permanent Building

8/19/2014

Page 23: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

23

Facilities Update: In Construction

• Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Completed• Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – Jul. – Oct. 2014• Remaining campuses – Oct. 2014 – Spring 2015

8/19/2014

Page 24: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

24

Facilities Update: In Construction

• Prop K: Technology Infrastructure Projects

8/19/2014

Page 25: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

25

Facilities Update: In Construction

• Prop K: Technology Infrastructure Projects

8/19/2014

Page 26: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

26

Facilities In Construction: SMK-8

8/19/2014

Page 27: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

27

Facilities In Construction: SMK-8

8/19/2014

Fields

ParkingParking

Buildings

Buildings

Central

Courtyard

Page 28: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

G O V E R N I N G B O A R D M E E T I N G

A U G U S T 1 9 , 2 0 1 4

FACILITIES UPDATE:THANK YOU!