San Bernardino Community College District Addendum No. 02Procurement #CC03.3640-1.10 PAGE 1
RFQ ADDENDUM DISTRIBUTIONSan Bernardino Community College District [X] Owner550 E. Hospitality Lane, Suite 200 [X] San Bernardino Community CollegeSan Bernardino, CA 92408 RFQ/P District Zero Net Energy (ZNE)
Implementation Plan
PROJECT: Request for Qualifications (“RFQ/P”) ADDENDUM NUMBER: Two (02) District-Wide Zero Net Energy (ZNE) Implementation Plan San Bernardino Community College District
Procurement#: CC03.3640-1.10
OWNER: San Bernardino Community College District DATE OF ISSUANCE: July 20, 2020
THIS ADDENDUM HAS BEEN PREPARED TO CLARIFY, MODIFY, DELETE, OR ADD TO THE RFQPDOCUMENTS FOR THE ABOVE REFERENCED PROJECT. THE ITEMS LISTED HEREIN SUPERSEDEDESCRIPTIONS PRIOR TO THE DATE LISTED ABOVE. ALL CONDITIONS NOT SPECIFICALLYREFERENCED HERE SHALL REMAIN THE SAME. IT IS THE OBLIGATION OF THE APPLICANTS TOMAKE SUBCONSULTANTS AWARE OF ANY ITEMS HEREIN THAT MAY AFFECT STATEMENTS OFQUALIFICATIONS AND/OR PROPOSALS.
GENERAL INFORMATION:
A. This Addendum Two (02) confirms the following:
1. 2.4 Tentative Procurement Schedule for this RFQP has been updated:
Date TimeRFQP Issuance 7/10/2020Non-Mandatory Pre-Proposal Conference 7/16/2020 11:00AM PDT Microsoft Teams MeetingRequests for Clarifications (“RFCs”) Due prior to: 7/22/2020 2:00PM PDTFinal Addendum Issued: 7/27/2020 2:00PM PDT
Proposals Due prior to: 7/30/2020 2:00PM PDT Electronic Submission viaPlanet Bids
Shortlist 8/4/2020 2:00PM PDT If requiredInterviews 8/10/2020 2:00-5:00PM PDT If requiredNotice of Intent to Award Issued to Selected Firm: 8/12/2020Board of Trustees Action 9/10/2020
Notice to Proceed 9/11/2020
San Bernardino Community College District
San Bernardino Community College District Addendum No. 02Procurement #CC03.3640-1.10 PAGE 2
The following Tentative Procurement Schedule is provided as a courtesy only. The District reservesthe right to change any and/or all dates in its sole discretion. Any changes made to the schedulewill be made via Addendum to this RFQP.
Attachments included:
Pre-Proposal Conference Meeting AttendeesPowerPoint Presentation from Pre-Proposal Conference Meeting
End of Addendum No.2
Pre-Proposal Meeting for RFQP District-Wide ZNE Implementation Plan July 16, 2020 at11:00am to 11:49am
ATTENDEES: 41
1. Scott Preston2. Sherri Lien Giffin3. Tareq Alsayegh4. Mari Biagorria5. Cris Walker6. Brenda Huelsbeck7. Linda Morrison8. Calina Ferraro9. Farrah Farzaneh10. Ben Dalton11. Ryan Smith12. Yash Patel13. Josh K14. Sahar Abbaszedeh15. Kanika Sharma16. Shea Dibble17. Jeffery McEntee18. Brian Liabeuf19. Martin Howell20. Tara Kelly21. Eric Corey Freed22. Brandon Dekker
23. Jesse Urquidi24. James Del Monaco25. Brian Stern26. Michael Zeuger27. Jaime Smith28. Aravind Batra29. Jason Barajas30. David Shpigler31. Mark Richie32. 323.219.012033. 415.286.167034. 831.239.078135. 760.815.936736. 415.999.341037. 713.203.926738. 831.239.078139. 909.256.386440. 408.487.125641. 562.244.7488
Join Microsoft Teams Meeting+1 213-204-2377 United States, Los Angeles (Toll)(877) 286-5733 United States (Toll-free)Conference ID: 623 992 544#Local numbers | Reset PIN | Learn more about Teams | Meeting optionsJoin with a video conferencing [email protected] VTC Conference ID: 1121232683Alternate VTC dialing instructions
San Bernardino Community College DistrictDistrict-Wide ZNE Implementation PlanPre-Proposal Meeting
Thursday, July 16 th
Agenda• Introductions
• Procurement
• Values and Goals
• 2017 Master Plan
• ZNE Brief
• Sustainability Plan
• Utility Infrastructure Plan
• Q&A
Procurement Schedule
RFQP Issuance July 10, 2020
Non- Mandatory Pre-Proposal Conference July 16, 2020at 11:00 AM to 12:00 PSTMicrosoft Teams meeting
Requests for Clarifications (“RFCs”) Due prior to: July 22, 2020at 2:00 PST
Final Addendum Issued: (revised date) July 27, 2020
Proposals Due prior to: July 30, 2020at 2:00 PM PST
Shortlist (if required) August 4, 2020
Interview (if required) August 10, 2020at 1:00 PM to 5:00 PM PST
Notice of Intent to Award Issued to Selected Firm: August 12, 2020
Board of Trustees Action September 10, 2020
NTP September 11, 2020
• READ and FOLLOW DIRECTIONS!• Pay attention to procurement
schedule and note important dates• Carefully review Professional
Services Agreement• Note all scope items and
deliverables in both RFQP and PSA• Max 10 projects for Applicant and all
Sub-consultants Combined• Execute ALL Certifications and
Acknowledgments
Procurement Items
Procurement ItemsPROPOSAL RESPONSIVENESS CHECK LIST
RFQ Section orAttachment #
NAME OF
FORM OR DOCUMENT
REQUIRED NUMBER OF FORMS TO BESUBMITTED
Is this in MyProposal?
3.1.1 Cover Page One (1) – Applicant needs to create3.1.2 Table of Contents One (1) - Applicant needs to create3.1.3 Cover Letter One (1) - Applicant needs to create
Attachment 1; PartA
Qualification Questionnaire Applicant completes and includes in its Proposalsubmission
Attachment 1; PartB
Qualification Questionnaire Each Consultant-Sub-Consultant must completeand include in Applicant’s Proposal submission.
Attachment 2 Individual Resume Form One (1) Resume Form for each Individualrequested in the Qualification Questionnaire
Attachment 3 Applicant History and Project Experience Form One (1) Complete form provided with up to ten(10) Projects
Attachment 4 Sub-Consultant History and Project ExperienceForm
One (1) Completed document from each Sub-Consultant proposed
Attachment 5 Acknowledgment of Addenda; One (1) Completed document signed byApplicant
Attachment 6 Applicant’s Representations and Certifications; One (1) Completed document signed byApplicant and from each Sub-Consultant TeamMember
Attachment 7 Conflict of Interest Certification; One (1) Completed document signed byApplicant
Attachment 8 Authorization to Release Information; One (1) Completed document signed byApplicant
Attachment 9 Non-Collusion Declaration One (1) Completed document signed byApplicant
Attachment 10 Non-Discrimination Declaration; One (1) Completed document signed byApplicant
Attachment 11 Confidentiality Agreement; One (1) Completed document signed byApplicant; and
One (1) Completed document signed by eachSub-Consultant being proposed
Attachment 12 Technical and Fee Guidelines One (1) Completed document signature ofacknowledgment
Attachment 13 Hourly and Personnel Classifications One (1) Completed document signed byApplicant
Procurement Items/Scoring
Overall Scoring Item Points
Attachment 1, Part “A”, Section 4.0 Qualifications 500
Attachment 12 Part 2 Technical and Fee Proposal 700
Subtotal 1,200
Part 3 Interview (if required) 300
Total 1,500
Procurement Items/Scoring
Proposal Evaluation Criteria(Attachment 12 Part 2)
Weight(% of First
Phase)
Max.Points
1. Proposed Technical Approach 35% 2452. Proposed Fee Proposal 20% 1403. Proposed Delivery Schedule 35% 2454. Overall 10% 70
Total 700
Section # Qualifications Category(Attachment 1 Part A)
PointsAvailable
TotalPoints
Available
4.1 Applicant Project Staff Experience 240
4.2 Applicant Project Experience 150
4.3 Proposed Overall Team Matrix 110Total 500
• Good Stewards of Public Funds• Client of Choice• Sustainability• Collaboration• Speed to Market• Outreach and Local Participation – Board
Policy 6610• Continuous Improvement
Select Measure CC Values and Goals
2017 Master Planning
ZNE Implementation Plan Tasks/Schedule
September October November December January
Task Wee
k 1
Wee
k 2
Wee
k 3
Wee
k 4
Wee
k 5
Wee
k 6
Wee
k 7
Wee
k 8
Wee
k 9
Wee
k 10
Wee
k 11
Wee
k 12
Wee
k 13
Wee
k 14
Wee
k 15
Wee
k 16
Wee
k 17
Wee
k 18
Wee
k 19
Wee
k 20
1Background Research, Data Collection andConservation Measures
2Identify Future Needs for Electrification &EV Charging
3Renewable Energy Feasibility Analysis -Phase 1: Early Start Project
3Renewable Energy Feasibility Analysis -Phase 2: Both Campuses
4 Roadmap for ZNE Implementation Plan
5Recommend Next Steps Toward a ZNCDistrict
FinalPlan
- Stakeholder engagement/ Implementation Workshop
Early StartProject(s) to BOT
Sustainability Plan (DRAFT)
Utility Infrastructure Master Plan (DRAFT)
Utility Infrastructure Master Plan (DRAFT)
Q&A