Salem Avenue Reconstruction Phase 1 From North Avenue to Manhattan Avenue
Construction in 2021
Salem Avenue Reconstruction Phase 2 From West Riverview Avenue to North Avenue
Construction in 2022
Salem Avenue Reconstruction Phase 3 From Manhattan Avenue to Cornell Drive
Construction in 2023
Salem Avenue Reconstruction Phase I
Project Limits: North Avenue to Manhattan Avenue Construction will start in spring of 2021 and completed by spring of 2022 Project will Include new :
• Pavement and Base • Curb • Driveway Approaches • Walk • Ornamental Street Lighting • Crosswalks
Proposed Section • Four lanes section that will match the existing section • Five lane section with left turn lanes at North Avenue and Harvard Blvd Property Acquisition • Minor permanent and temporary easement will
be required.
Salem Avenue Reconstruction Phase II
Project Limits: West Riverview Avenue to North Avenue Construction will start in spring of 2022 and completed by summer of 2023 Project will Include new :
• Pavement and Base • Curb • Driveway Approaches • Walk • Ornamental Street Lighting • Crosswalks
Proposed Section • Five lanes section with a center two way left turn lane or median • Two way separated cycle track will be constructed on the south curb lane. Property Acquisition • Minor permanent and temporary easement will be required.
Salem Avenue Reconstruction Phase III
Project Limits: Manhattan Avenue to Cornell Drive Construction will start in spring of 2023 and completed by spring of 2024 Project will Include new :
• Pavement and Base • Curb • Driveway Approaches • Walk • Ornamental Street Lighting • Crosswalks
Proposed Section • Under Design Property Acquisition • Minor permanent and temporary easement maybe
be required.