Saffo Contractors. Clinton Overpasses Clinton, NC 2007. Project Overview. This project called for abrasive blasting and painting of the steel beams supporting the overpasses on 7 stretches of US Highway 421 outside of Clinton. . Services Performed. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Saffo  Contractors

Saffo Contractors

Clinton OverpassesClinton, NC

2007

Page 2: Saffo  Contractors
Page 3: Saffo  Contractors

Project Overview

This project called for abrasive blasting and painting of the steel beams supporting the overpasses on 7 stretches of US Highway 421 outside of Clinton.

Page 4: Saffo  Contractors

For this project, all steel beams on the overpasses in the area around Clinton, NC were abrasive blasted using a grit recycling system and painted. Saffo was responsible for adhering to all DOT specifications for traffic control and monitoring. During two phases of the project, traffic had to be diverted from the main intersection of the town for the duration of the weekend in order to complete all work.

Services Performed

Page 5: Saffo  Contractors

ARS Recycling machine, Saffo Box Truck, & IR Dust Collector positioned next to contained overpass

Equipment Placement

Page 6: Saffo  Contractors

Saffo was responsible for setting up lane closures, detours, and signal trucks to reroute traffic while work was being completed.

Traffic Control

Page 7: Saffo  Contractors

The main intersection of Clinton has two overpasses that required blasting and painting work. The work was done in two consecutive weekends, and in a manner

so that traffic was still permitted to pass through under a lane closure.

Phase One of Intersection Work

Page 8: Saffo  Contractors

Intersection Phase One containment from an alternate angle, with traffic uninhibited.

Containment

Page 9: Saffo  Contractors

Much of the blast work was done by night so as to maintain proper temperature conditions for painting.

Overpass Two Containment

Page 10: Saffo  Contractors

ARS Dust Collector in place on overpass three.Containment Three

Page 11: Saffo  Contractors

Saffo Contractors