SACFA Process
FUNCTIONRegulatory Affairs
TITLE OF THE PROCESSSACFA Clearance
SUB-PROCESSES
PROCESS CODEP/REG/SAC/8003
PROCESS OWNERMO Technical
PROCESS CHAMPIONCircle Technical
GLOBAL PROCESS OWNER Head - MO Regulatory
GLOBAL PROCESS CHAMPIONManager - MO Regulatory
TABLE OF CONTENTS Section ContentsPage Number
I.Process Overview3
II.Key CTQs5
III.Process Details6
IV.Work Instructions12
V.Annexure / Formats ( No.)13
VI.Measurement Dashboard23
VII.Terminology & Abbreviations25
VERSION HISTORY
Version No. & DateChange Initiated
Version 1.1, 9/10/2006Process Review & Standardisation - This process has been modified in accordance with guidelines issued by WPC wing of DoT time-to-time, in order to get the SACFA clearances timely. It also covers the process for applying to WPC for frequency assignment.
Version 1.2, 13/02/2007SACFA Application Circulation submission timeline has been revised
Version 1.3, 3/07/2007SACFA Application submission timeline with SACFA Secretariat has been revised
Version 1.4, 19/07/2007SACFA Application circulation methodology and formats have been reviewed and revised accordingly
Version 1.5, 01/01/2008Scope extended upto obtaining Operating Licence and some Terminology & responsibilities have been revised
Version 1.6, 15/01/2008SACFA Application Online filing timeline and condition for putting up Site on Air has been reviewed and revised
Version 1.7, 01/09/10SACFA Process for Additional Antennae category applications has been simplified by WPC and applications for AAI NoC to be submitted with applicable Regional Hub
I. Process Overview
PURPOSE OF PROCESSTo ensure that all the sites radiating in Airtel networks have Final SACFA Clearance or WPC Acceptance No or acknowledgment from MO-Regulatory of submission of hard copy application to WPC.
SCOPE OF PROCESSThe process starts when site is leased and ends with obtaining Final SACFA Clearance & applying for Operating Licence.
CUSTOMEROUTPUTKEY PROCESS STEPSINPUTSUPPLIER
Circle SACFA team. Sites finalised for applying for SACFA.Network Planning finalising the sites and giving site details (as per suggestive formats) to Site Acquisition team for leasing and to SACFA team for applying for clearance.Site survey report.Network Planning/ Circle Site Acquisition team
Circle SACFA teamDDs for SACFA Fee.SACFA team to apply & co-ordinate with circle Finance function for Demand drafts for further submission to SACFA as SACFA application fee.Site detailsCircle Finance
MO Regulatory / SACFA Secretariat.SACFA application hard copyPreparing and submitting SACFA application for all antennas (in Full Siting / Additional antenna category) on WPC website http://www.wpc.dot.gov.in/) and sending application hard copy along with Demand Draft, Map etc. to MO-Regulatory for further submission to SACFA Secretariat.Complete SACFA applicationCircle SACFA team
Circle SACFA TeamSubmission AcknowledgementMO-Regulatory to check and submit SACFA applications with SACFA Secretariat, take acknowledgement and Inform Circle SACFA Team ,Complete SACFA applicationMO Regulatory
Circle SACFA team.WPC Acceptance No.MO-Regulatory to co-ordinate with SACFA Secretariat for getting WPC Acceptance No. Circle SACFA team will than intimate this to Network Planning / Project TeamComplete SACFA applicationMO Regulatory / SACFA Secretariat.
Network Planning / Project TeamSite on AIRBefore Putting up Site On-Air Network Planning /Project Team gets the Regulatory sign-off from Circle Regulatory. Circle Regulatory to submit a monthly audit report to MO Regu by 5th of every monthSACFA ComplianceCircle Regulatory
SACFA members.Application circulation to all SACFA membersCircle SACFA team to make multiple sets of applications (for Full siting category sites which are not cleared online and shown Under Process on WPC Website) and submit one set with applicable AAI regional Hub directly and send others sets to MO-Regulatory for onward submission to Defence services HQ by hand and Circle should kept one set of complete application in record Complete SACFA application with WPC Acceptance no.Circle SACFA team/ MO-Regulatory
MO-Regulatory/ Circle SACFA team.NOCs from SACFA members.Circle SACFA team to monitor all online NOCs/objections at WPC website or any written rejection by any of the members and take corrective actions and intimate MO-Regulatory. MO-Regulatory to co-ordinate with circle / SACFA members for all critical issues as and when required.Receipt of submission of SACFA applications.SACFA members
Circle SACFA team / Circle TechnicalFinal SACFA ClearanceMO-Regulatory to get Final SACFA Clearance from SACFA Secretariat and send to Circle CTO/ Circle SACFA team for their information and records. Circle Technical to keep all the Final SACFA ClearancesFinal SACFA ClearanceSACFA secretariat / MO Regulatory
Circle SACFA / Technical TeamOperating LicenceCircle SACFA Team to prepare and send Deployment Plan / Operating Licence application to MO Regulatory once in quarter at least. MO Regulatory to check and submit application to WPC and obtain Operating License at the earliest
Deployment Plan / Operating Licence ApplicationWPC / MO Regulatory
II. Key CTQs:
Parameter
CTQ MeasureDefect DefinitionUnitMeasurement MetricTargetControl Plan
OUTPUT MEASUREDelay in WPC Acceptance No.Time taken in obtaining WPC Acceptance No. is more than 14 days from the date of application submission to SACFA Secretariat If time taken is more than 14 daysEach SACFA ApplicationNo. of delayed WPC Acceptance No. / Total Application Submitted>80%Circle Dashboard & MO-Dashboard
Application RejectedAny application rejected YES or NOAny application rejected - YESEach SACFA ApplicationNo. of YES/ Total Applications submitted>95%Circle Dashboard & MO-Dashboard
PROCESS MEASURETimely dispatch of SACFA application hard copy to MOWithin 8 days of leasing of the site SACFA application hard copy not sent to MO with in 8 days of leasing of the siteEach affected site.No of sites affected/ Total no of sites>80%Circle Dashboard
Timely circulation of SACFA applicationSending application set for Defence services to MO-Regulatory and submit applications directly to AAI regional Hub within 10 days of getting WPC Acceptance no.If time taken is more than 10 daysEach SACFA ApplicationNo. of applications where TAT was not met/Total no of applications>90%Circle Dashboard & MO-Dashboard
Initiating timely corrective action to address objected /rejected sites.Time taken by circle in initiating action to address objection/ rejection of SACFA membersIf corrective action not initiated within max 2 weeksEach affected site.No. of time TAT was met/ No. of Objections>90%Circle Dashboard
INPUT MEASURETimely Filing of SACFA application online Circle SACFA team to file online application and send application hard copy to MO-Regulatory team within 6 days of leasing the site Application not filed online within 6 days of leasing the site.Each SiteNo of sites for which online SACFA application not filed within 6 days of leasing of the site90% with in TATMO-Regulatory
5
MO-Regulatory to liaise & get issued On-line WPC Acceptance number.
MO-Regulatory to liaise with SACFA secretariat for issuing on-line WPC Acceptance number.O + Day 19
>80% with in TATMO-Regulatory
6Circle SACFA Team to check WPC website for WPC Acceptance Number issued by SACFA on daily basis.Circle SACFA Team to check WPC website for SACFA WPC Acceptance Number issued by SACFA on daily basis.P( P- Date WPC Acceptance Number issued by SACFA )Circle SACFA Team
7Network Planning / Project Team to get circle Regulatory sign-off before putting up site on-AirBefore Putting up Site On-Air Network Planning /Project Team gets the Regulatory sign-off from Circle Regulatory
Circle Regulatory to verify from MO-Regulatory Email acknowledgment of submission of application hard copy /WPC Acceptance No. / SACFA Final Clearance before giving sign-off for the site
P + 1Network Planning/ Project Team /
Circle Regulatory Team
8NOYESCirculation to SACFA Members is not requiredSite Cleared Online / or additional antenna application?If site status shown as CLEARED on WPC Web Site OR filed under additional antenna category, than Circulation of application to SACFA Members is not required
P+1Circle SACFA Team
9Circle SACFA team to make multiple sets of applications which required to be circulated and send to MO-Regulatory / AAI Circle SACFA Team to send application set for Defence Services to MO-Regulatory and submit one set with regional AAI office within 10 days of getting WPC Acceptance NoDay P+10> 90% within TATCircle SACFA TeamAnnexure 004 /05
10Circle SACFA Team to check WPC Website on daily basis for NOCs /Objections from SACFA members
Circle SACFA Team to check WPC Website on daily basis for NOCs /Objections from SACFA members, and intimate Circle Tech / Circle Regu for any missing in-between NOCs/objections or any rejection in writing immediately.
Circle SACFA Team
11Site Cleared by SACFA?NOAny written rejection communication, to be sent to Circle SACFA team/CTO within 3 daysYESAny written objection/ rejection of the site by any SACFA Member to be informed to Circle SACFA Team for taking necessary action on dismantling or reapplying the site.With in 3 day of receiving information for > 90% cases.Timely reply to the objections raisedMO-Regulatory.
12Corrective actions for rejected/ objected sites Circle Tech /Circle Regu team to take corrective actions to address objection of the member (if any)Circle Technical/ Circle Regulatory Annexure 009
Addressing objection /rejection concerns of the SACFA member or relocation of site
13MO-Regulatory to obtain SACFA Final Clearance Certificate for Full Siting applications, from SACFA Sectt and send to circle CTO / Circle SACFA Team..Original SACFA Clearance Certificate to be sent to the respective circle CTOs / Circle SACFA Team with necessary update in MO SACFA records. Circle Technical to keep original SACFA clearances certificatesWith in 3 days of receiving the certificates for >90% cases.MO-Regulatory / Circle Technical TeamSACFA clearance
14Circle SACFA Team to apply for the Operating License at the earliestCircle SACFA Team to prepare and send Deployment Plan. Operating Licence applications to MO Regulatory at the earliestOnce in a quarter minimumCircle SACFA TeamForm 008Dep Plan / Operating Licence Application
15MO Regulatory to obtain Operating License at the earliestMO Regulatory to check and submit application to WPC and obtain Deployment Plan approvals / Operating License at the earliest
As requiredMO Regulatory TeamOperating Licence
END
IV. WORK INSTRUCTIONS
Code Description
WI / MO/REG/SAC/8003Process of SACFA Clearance
Sl. NoWork Instructions
1Collection of Site data from Site acquisition / Network Planning Team(As per Process)
2Preparing of SACFA Application & sending to MO-Regulatory
3 Circulate the SACFA application after obtaining WPC Acceptance No. within 10 days.
4Follow up with SACFA members for NoC and final SACFA clearance from SACFA Secretariat.
5Apply and obtain Operating Licence for all sites in the network
V. ANNEXURES & FORMATS*
Sl. NoCodeDescriptionDetails
1F/MO/Projects/SACFA CLearance/001FormRequest letter to Network Planning for Site Details
2F/MO/Projects/SACFA CLearance/002FormRequest Letter to A/C dept
3F/MO/Projects/SACFA CLearance/003FormApplication for SACFA Clearance
4A/MO/Projects/SACFA CLearance/004AnnexureApplication for SACFA Members NOCs
5A/MO/Projects/SACFA CLearance/005AnnexureList of SACFA members
6A/MO/Projects/SACFA CLearance/006AnnexureChecklist for sending the SACFA applications to MO regulatory
7A/MO/Projects/SACFA CLearance/07AnnexureChecklist for Circulation of SACFA applications
8F/MO/Projects/SACFA CLearance/08FormFormat for Preparing of Deployment Plan
9F/MO/Projects/SACFA CLearance/08AFormFormat for Preparing Operating Licence Application
10A/MO/Projects/SACFA CLearance/10AnnexureProcess Guidelines for addressing Objected /Rejected Sites
* S.No. 1 & 2 are suggestive formats,FORMAT: F/MO/Projects/SACFA CLearance/001 Suggestive Format
REQUEST LETTER TO NETWORK PLANNING FOR SITE DETAIL
SACFA Siting Clearance Requisition FORM
Please provide the information as per the following details:
1Site Address:
2AMSL:
3Lat Long:
4GBT/RTT (Total Height Required):
5Height of Bldg if Rooftop
GSMMW
6Frequency Band:
7Max. Height of Antenna AGL:
8Transmitted Power
9Antenna Size:
10Max Azimuth:
11Rx Location:
12HOP Length:
13Distance from International Border
Approved By ___________________________________
FORMAT : MO/Regu/SACFA CLearance/002 Suggestive Format
Request Letter to Finance / Accounts dept for DD of SACFA Fee
Inter Office memo
From:aaa
Thru:xyz
To:Finance / Accounts Deptt.
Date:dd/mm/yyyy
Subject : Fees for SACFA Clearance - .. Circle
You are requested to please arrange to release .. Nos demand draft(s) of Rs ________/- in favour of PAO(HQ), DOT, Payable at Service Branch Code No 7687 as fee for SACFA clearance.
The list of sites is enclosed for your reference, please.
Regards
FORMAT: F/MO/Projects/SACFA Clearance/003
ANNEXURE : MO/Regu/SACFA Clearance/004
ANNEXURE : MO/Regu/SACFA Clearance/005
AAI Regional Hubs: For submission of applications by circle
S.NOAAI Regional HubsLocation
1The Regional Executive DirectorAirport Authority of India,Chennai Airport, MeenambakkamChennai 600027
Chennai
2The Regional Executive Director, Airport Authority of India, New ATS Complex, IGI Airport, New Delhi 110 037
Delhi
3The Regional Executive Director, Airport Authority of India, Lok Priya Gopinath Bardoloi International Airport, Guwahati - 781015
Guwahati
4The Regional Executive Director, Airport Authority of IndiaNSCBI Airport, Kolkata - 700052
Kolkata
5The Regional Executive Director, Airport Authority of IndiaDomestic Terminal 1-B,Chatrapati Shivaji AirportMumbai - 400099
Mumbai
6The Regional Executive Director, Airport Authority of IndiaHyderabad Airport,Hyderabad - 500016
Hyderabad
7The Regional Executive Director, Airport Authority of IndiaDevanahalli Airport,Outer Ring Road, HebbalBangalore - 560024
Bangalore
8The Regional Executive Director, Airport Authority of IndiaNagpur Airport, Nagpur - 440005
Nagpur
9The Regional Executive Director, Airport Authority of IndiaS P International Airport, Ahmedabad - 380003
Ahmedabad
Defence HQ: Application to be circulated by MO Regulatory by hand
S.NOName & Address of SACFA MembersNo. of Copies to be sentAny Specified Document Required
Bharti Airtel Limited SACFA CLEARANCE PROCESS
1Page of 166Prepared by: Sunil SareenReviewed by: Ashwani RanaApproved by: Ashwani RanaVersion:
Effective Date :
Supercedes:
Page :
Mobile No. +91 98100-94055Mobile No.: +9198100-28807Mobile No.: +91 98100-288071.701/09/20101.6Page 4 of 25
1Diretor Operations (Signal)Air Headquater, Room No. 514Vayu Bhawan, New Delhi 110 001
1Applications to be segregated command wise
2Navel Headquater Room No. 33,Sena Bhavan, C WingNew Delhi 100 001
1No
3Army HeadquaterRoom No. 634, A-Wing Sena Bhavan, New Delhi- 110 001
1No
4JCESCabinet Secretariat,Military Secretariat, Military WingRoom No. 34, Plot No. 108,Church Road, New Delhi - 11001No
ANNEXURE : MO/Regu/SACFA CLearance/006
CHECKLIST FOR SENDING THE SACFA APPLICATIONS to MO REGULATORY
ANNEXURE: MO/Regu/SACFA Clearance/007
CHECKLIST FOR CIRCULATING SACFA Applications
AEnsure that all the SACFA Circulation letters are duly signed and stamped
BSupporting Maps attached with applications are also stamped & signed by Concerned Circle SACFA Coordinator
CPrepare the set with all the required necessary Documents (As mentioned in checklist of filing of SACFA Applications)
DPrepare application copies as required by SACFA Members (Annexure 006):
iOne Set of application to be submitted directly with Regional AAI office (With ASP in original for sites falling within 6 KMs of the Aiprorts). List attached at Annexure 006
iiiFor Defence Services HQ, applications to be sent to MO-Regulatory for submission by hand along with circulation acknowledgement as per Annexure 005
iiiOne set to be kept at circle for records
FORMAT : F/MO/Projects/SACFA Clearance/008
Preparing Deployment Plan Application
FORMAT : F/MO/Projects/SACFA Clearance/008A
Preparing Operating Licence Application
ANNEXURE : MO/Regu/SACFA Clearance/009
Process Guidelines for addressing Objected /Rejected Sites
VI. PROCESS MEASUREMENT DASHBOARD
Data Collection sheet no.
ParameterCTQ TargetData Source / FrequencyCustomerResponsibility
OUTPUT MEASURENo application should be Rejected by the SACFA Secretariat90%Circle DashboardMO-RegulatoryCircle SACFA Team
Timely circulation of SACFA application - Sending application set to SACFA members within 10 days of getting WPC Acceptance No.>80%Circle DashboardMO-RegulatoryCircle SACFA Team
Liaising with SACFA secretariat for issuing WPC Acceptance number with in 14 days.>80%MO DashboardCircleMO-Regulatory
Timely reply (within 15 days) to the queries / information received from SACFA members.>90%MO DashboardSACFA membersCircle SACFA Team / MO-Regulatory
INPUT MEASURETimely filing of online application>95%Circle DashboardMO RegulatoryCircle Technical team / Circle SACFA Team
VII.Terminology, Definition & Abbreviations
S.No.Short FormsFULL FORM
1AAIAirport Authority of India
2ASPAuthenticated Site Plan
3AIPAgreement In Principle Approved Frequency Plan
4SACFAStanding Advisory Committee on Frequency Allocation
5WPCWireless Planning & Coordination Wing of DoT
6TATTurn Around Time
7AMSLAverage Mean Sea Level
8CTOChief Technical Officer
9GBTGround Based Tower
10RTTRoof Top Tower
11Airport GRID MAPIt is a internal map of all airports, with sites plotted and dully certified by Airport Director/ Incharge. Airport will directly dispatch this grid map to AAI, New Delhi under intimation to Bharti
12.Full Siting CategoryAny sites can be applied in this category / or If site is new or no prior SACFA final clearance has been obtained.
13.Additional Antenna CategoryIf putting up additional antenna on our existing site / shared site, where AAI NOC, Final SACFA clearance have already been obtained
14.DayWorking Day
15NoCNo Objection Certificate
Prepared by: Sunil SareenReviewed by: Ashwani RanaApproved by: Ashwani RanaVersion:
Effective Date :
Supercedes:
Page :
Mobile No. +91 98100-94055Mobile No.: +9198100-28807Mobile No.: +91 98100-288071.701/09/20101.6Page 25 of 25
Application - Circle NameSoft copy (thru mail) to be mailed in advance before sending Hard copies of the applications to MO for onward submission to SACFAName of the Circle :S.No.Site AddressLatLongFrequencyRemarks (If any)SACFA Acknowledgement NoSACFA Acknowledgement Date(dd/mmm/yy)Sent to MO on (Courier Date)(dd/mmm/yy)
&R&"Arial,Italic"&8&F / &A /&D
Date :
To,
SACFA Members
Subject : Forwarding of Siting Applications of Bharti Airtel Limited Circle Name
Sir,
Please find enclosed herewith copies of Full Siting applications as detailed below :
S.No.Site AddressLatitudeLongitudeNearest Airport NameAirport Distance (KMs)WPC Acceptance No.Date
1
2
3
4
5
6
7
8
9
10
Encl :
1. Application in prescribed proforma of WPC
2. Copy of siting Map / Authenticated site plan
We request you to please issue NOCs for the above WPC Acceptance Nos. at the earliest
Thanking You,
Yours Sincerely
For Bharti Airtel LimitedName
Designation
Please respond to :
Regulatory Affairs - Mobile Services
Bharti Airtel Limited
Airtel Centre
Sixth Floor, 'A' Wing
Plot No.16, Udyog Vihar,Ph-IV
Gurgaon - 122001, Haryana
Fax : 0124-4109585
Paste/write Mailing address of SACFA Member
Mention circle name
Circulation AcknowledgemntThe receipt of Siting Application(s) with following details is/are acknowledged
Name of the Application Bharti Airtel Limited Cellular Mobile Services in . Telecom Circle
S.NoFrom WPC Acceptance No (ID)To WPC Acceptance No (ID)DateNo. of Applications
1P/FVC/JLD/103689/2006
P/FVC/JLD/103691/200617/08/20062
2P/FVC/JLD/103693/2006
P/FVC/JLD/103695/200617/08/20062
3P/FVC/JLD/103698/2006P/FVC/JLD/103701/200617/08/20064
4P/FVC/JLD/103703/2006
P/FVC/JLD/103705/200617/08/20062
5P/FVC/JLD/103734/2006 P/FVC/JLD/103736/200617/08/20062
6P/FVC/JLD/103856/2006 P/FVC/JLD/103858/200617/08/20062
7P/FVC/JLD/103860/2006
P/FVC/JLD/103862/200617/08/20062
8P/FVC/JLD/103864/2006P/FVC/JLD/103865/200617/08/20062
Total18
S.No. Name of the SACFA Members
Name & Designation of Receiving Officer with Stamp.
1General Manager (Operations)
AAI, Room No. 128, Rajiv Gandhi Bhawan
Safdarjung Airport, New Delhi 110 003
To be submitted with regional AAI office
3Diretor Operations (Signal)
Air Headquater, Room No. 514
Vayu Bhawan, New Delhi 110 001
1 set to MO (Segregated command wise)
4Navel Headquater
Room No. 33,
Sena Bhavan, C Wing
New Delhi 100 001
1 set to MO
5Army Headquater
Room No. 634, A-Wing
Sena Bhavan, New Delhi- 110 001
1 set to MO
6JCES
Cabinet Secretariat,
Military Secretariat, Military Wing
Room No. 34, Plot No. 108,
Church Road, New Delhi - 11001 set to MO
Circulation copies to MOSoft copy (thru mail) to be mailed in advance before sending Circulation hard copies to MO for onward circulation to 4 important SACFA MembersName of the Circle : S.No.Site AddressLatLongFrequencySACFA ID NoSACFA ID DateWPC Acceptance No.WPC Acceptance Date(dd/mmm/yy)Circulation sent to MO - Courier date(dd/mmm/yy)12345678910
&R&F / &A /&D
SACFA Check List 7ASACFA Check List (SACFA application hard copy should be checked as per below given Check-List before sending to MO-RegulatoryS.No.DescriptionYESNO1Fee draft @ Rs. 1,000/- per application in favor of "PAO (HQ) DoT" payable at SBI, Branch Code 7687, New Delhi.2Name of company, circle and first SACFA ID is mentioned on back of Demand Draft3Photo copy of the covering letter and DD is attached on top ?4Application for SACFA Clearance (As per Annexure), with undertaking of correctness of AMSL & Coordinates5Supporting map with site duly marked is required to be attached with each application.6In SACFA application allocated frequency band /spots are exactly as per WPC Frequecny Allocation letter7For Additional Antenna Category application, Copy of the earlier SACFA clearance attached8Copy of Frequency agreement letter & Site Deployment Plan attached9Copy of the License Agreement (Top 2 - main sheets only)10Application is signed properly11WPC Sites clearance sheet (attached on top of each folder) - Sample Attached
SITE CLEARANCE UNDER FULL SITE CATEGORYApplicant: Circle:
Diary Date: No of Applications:
Amount of Drafts: DD. No: DD.Dated:
RAC:
1Whether Applicant has LOA of frequency agreement / deployment plan.Yes /No
2Whether a copy of online submission enclosed.Yes /No
3Whether antenna height includes building height, if yes building height indicated.Yes /No
4Whether attached map authenticated by authorized signatory.Yes /No
5Whether site and its coordinates marked on the map is under correct scale (1:50).Yes/No
6Whether site is located with in the 5 Kms from airport if yes ASP enclosed.Yes /No
7Whether Draft enclosed bears the name of Company ID No. on its back.Yes /No
8Whether Applications is signed by Applicant.
Yes /No
In View of above applications is in order; we may issue WPC Acceptance Number Please.
JE/JWO
For Approval Please.
Engineer (P-4)
AWA (P-1)Sample : SACFA Application Covering LetterDate:
The Secretary SACFA
WPC Wing
Department of Telecommunications
Sanchar Bhavan, 20, Ashoka Road,
New Delhi-100 001
Subject : Application for Full Siting /Additional Antenna clearance Bharti Airtel Limited , Circle Name.
Reference : License Agreement No Dated . Dear Sir,
We are enclosing herewith our applications in respect of the following sites Full Siting /Additional Antenna CLEARANCE to set up our Cellular Mobile Telephone Service.S.No.SITE NAME & ADDRESSLATTITUDELONGITUDENearest Airport NameAirport DISTANCE(KMs)ACKNOWLEDGEMENT (SACFA ID) NO.DATED
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
It is certified that the Geo-coordinates and AMSL, used in the enclosed SACFA applications have been taken by using reputed .. make (specify make) GPS/altimeters and have been duly checked & verified.
DD no. ______________ Dated ____________ Amount Rs. __________ is enclosed.We would request you to please issue the WPC Acceptance No. for the above-mentioned sites to proceed further for SACFA CLEARANCE.
Thanking you,
Yours sincerely,
For Bharti Airtel Limited
Name
DesignationMention circle name
This para is required only if you are not attaching SOI certificate, and AMSL obtained by any other means
Mention Circle License No. & Date
Use any one