RUNWAY 28 EXTENSION Stakeholders Meeting. April 17, 2013. Updates Since Last Meeting: Runway 28 Extension Decreased duration of reduced runway length – NOW = 10 days Relocation of existing PAPI prior to threshold relocation Installation of temporary REIL for threshold relocation - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/1.jpg)
RUNWAY 28 EXTENSIONStakeholders Meeting
April 17, 2013
![Page 2: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/2.jpg)
Updates Since Last Meeting:
Runway 28 Extension1. Decreased duration of reduced runway length – NOW = 10 days2. Relocation of existing PAPI prior to threshold relocation3. Installation of temporary REIL for threshold relocation4. ASOS relocation time: ONE DAY. (to be schedule after glide slope relocation)5. Runway opens to 6,900’ length after 10 day threshold relocation is over
Runway Overlay and Marking6. Night work Runway 10/287. Maintenance of standard markings8. Day work Runway 18/36
![Page 3: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/3.jpg)
![Page 4: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/4.jpg)
![Page 5: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/5.jpg)
1010
9/13/13Reopen Runway 6,900, (Localizer only) 9/13/13
12/13/13 1 7 FAA Publishes flight procedures (Full ILS) 12/13/13 12/13/13
1
![Page 6: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/6.jpg)
![Page 7: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/7.jpg)
![Page 8: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/8.jpg)
NOTE: Aircraft must use Taxiway Gto access the end of Runway 28
Construction Access
Phase I
![Page 9: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/9.jpg)
Construction Access
Phase II NOTE: Aircraft must use Taxiway Dto access the end of Runway 28
![Page 10: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/10.jpg)
Construction Access
Phase IIINOTES
• Aircraft departing Runway 28 must back-taxi from Taxiway H and turn around on the runway for maximum available takeoff length.
• Aircraft landing Runway 10 and traveling beyond Taxiway H must turn around on the runway and back-taxi in order to exit the Runway via Taxiway H
End Runway 285,900 ft.
End Runway 105,500 ft.
![Page 11: RUNWAY 28 EXTENSION Stakeholders Meeting](https://reader036.vdocuments.mx/reader036/viewer/2022081514/56812e03550346895d936604/html5/thumbnails/11.jpg)
Final
PAPI
Glide Slope