Montara Development – Drilling Program
• Drill, Complete & Clean-up 2 new Subsea Development wells (Water Depth 82m)
• Re-enter 2 existing subsea wells, run a tree, complete and clean-up each well (Water Depth 77 to 82m)
• Drill and complete 3 platform wells (Water Depth 80m)
• Jack-up MODU with 400’ legs required
![Page 3: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/3.jpg)
Chris Wilson – September 2008
Subsea Trees
Tree• Vetco 13 5/8” 5000psi• Separate flow base• 4.3m(l) x 3.9m(w) x 2.6m(h)Flowbase• 3.9m(l) x 3.8m(w) x 5.1m (h)
– with guideposts installed
![Page 4: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/4.jpg)
Chris Wilson – September 2008
Two New Subsea Wells
• Wells needed to be close enough not to move the rig
• Not too close to inhibit ROV Access
• Performed 3D modelling with TMT to determine spacing
• 5m Centre to Centre• 1m Difference in
Elevation
![Page 5: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/5.jpg)
Chris Wilson – September 2008
Existing Subsea Wells
• Needed to have positioning tolerance capabilities
• Positioning on a “postage stamp” is time consuming & difficult with a jack- up
![Page 6: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/6.jpg)
Chris Wilson – September 2008
Montara Development Drilling Project Requirements
• 400’ Leg Jack-up New Generation Jack-up• Ability to drill two subsea wells at 5m centres Modified
conductor deck• Run subsea trees (preferably not picking-up off the
back of a boat) Make room under the cantilever• Be able to support the weight of the high pressure
riser and BOP’s outside of the existing conductor tensioner location Modified conductor deck
• Have positioning tolerance capability Modified conductor deck
![Page 7: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/7.jpg)
Chris Wilson – September 2008
MODU – Seadrill’s West Atlas•
K-Fels Mod V Class B
•
Leg Length –
157m (517’) capable of drilling in 114m of water
•
Derrick Capacity –
1500 kips
•
BOP Pressure Rating – 15kpsi
•
Proven Rig design (Ensco 104, 106, 107, 108, Wilcraft & Atwood Beacon)
![Page 8: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/8.jpg)
Chris Wilson – September 2008
Rig Modifications to Handle Subsea Trees
•
Relocation of the Cement Unit to allow Subsea Trees & Flow Bases to be skidded aft
![Page 9: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/9.jpg)
Chris Wilson – September 2008
Tree Skidding System
•
Train Track Style•
Easy to Install
•
No welding required•
Tree Trolleys to have capability to test trees
![Page 10: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/10.jpg)
Chris Wilson – September 2008
Conductor Deck Modification Requirements
• Space to drill 2 subsea wells at 5m centre• Ability to hold weight of the high pressure riser,
BOP’s plus a safety factor (~200MT)• Provide positioning tolerance• Handle environmental loads• Able to run trees through (if required)
![Page 11: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/11.jpg)
Chris Wilson – September 2008
Concepts
![Page 12: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/12.jpg)
Chris Wilson – September 2008
Final Design
![Page 13: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/13.jpg)
Chris Wilson – September 2008
Installation of Conductor Deck Extension
![Page 14: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/14.jpg)
Chris Wilson – September 2008
Final Product – Conductor Deck Extension
![Page 15: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/15.jpg)
Chris Wilson – September 2008
Final Product - Spreader Beam Assembly
![Page 16: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/16.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor
![Page 17: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/17.jpg)
Chris Wilson – September 2008
![Page 18: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/18.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft
![Page 19: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/19.jpg)
Chris Wilson – September 2008
![Page 20: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/20.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
![Page 21: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/21.jpg)
Chris Wilson – September 2008
![Page 22: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/22.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree
![Page 23: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/23.jpg)
Chris Wilson – September 2008
![Page 24: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/24.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft
![Page 25: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/25.jpg)
Chris Wilson – September 2008
![Page 26: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/26.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft• Run tree through the conductor deck extension
![Page 27: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/27.jpg)
Chris Wilson – September 2008
![Page 28: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/28.jpg)
Chris Wilson – September 2008
Tree / Flowbase Running Sequence• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft• Run tree through the conductor deck extension• Lower the box beam assembly into the conductor deck
extension• Land tree and nipple-up Surface wellhead & BOP’s
![Page 29: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/29.jpg)
Chris Wilson – September 2008
![Page 30: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/30.jpg)
Chris Wilson – September 2008
![Page 31: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/31.jpg)
Chris Wilson – September 2008
Conductor Deck Extension – Lessons
• Deck was time consuming to recover and store between wells
• Support slings time consuming to move when skidding cantilever
• Box beam assembly was cumbersome• Despite the lessons – the extension deck
satisfied a wide variety of expectations
![Page 32: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/32.jpg)
Chris Wilson – September 2008
Tree Skidding System - Lessons
•
End of the track interfered with cantilever beam
•
Tree Was not on centreline (handling Issues)
•
Tolerance was tight
![Page 33: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside](https://reader030.vdocuments.mx/reader030/viewer/2022021511/5b14d42a7f8b9a7d068c22e4/html5/thumbnails/33.jpg)
Chris Wilson – September 2008
Subsea Trees on Jack-ups - Conclusions
• Early access to rig during construction allowed for subsea tree running to be part of the rig design
• Conductor Deck Extension ~ 8 Months from concept to delivery & cost ~$750,000
• Drilling Contractors should recognize the ability of these new build jack-ups to run subsea trees especially with the increased water depth capability