RT-100 CaskCertificate of CompliancePre-Application Meeting

14 November 2011 RT-100 Pre-Application Meeting

14 November 2011

Robatel Technologies, LLCRoanoke, VA

1

Page 2: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Agenda

IntroductionsDesign & Licensing ExperienceRT-100 Conceptual Design

OverviewDesign – ConceptualDesign – DimensionsDesign – Characteristics & Contents

14 November 2011 RT-100 Pre-Application Meeting

gMaterials

Licensing ApproachStructural AnalysisThermal AnalysisShielding AnalysisModeling

Schedule for Application Submittal

2

Page 3: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Introductions

Mr. Teo Grochowski Robatel Technologies, Chief Operating Officer

Mr. George JobsonRobatel Technologies, Vice-President

Mr. Jack Rollins

14 November 2011 RT-100 Pre-Application Meeting

Robatel Technologies, Licensing ManagerMr. Fabien Labergri

Robatel Industries, Technical ManagerMr. Jean-Francois Damon

Robatel Industries, Cask EngineerNRC Staff

3

Page 4: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Design & Licensing Experience

Cask ExperienceRobatel has 60 years cask design, licensing, and fabrication experienceDesigned and licensed over 70 designs and fabricated more than 800 casks [Type A, Type B (U/M)]In-house Drop Test Facility

Engineering Experience

14 November 2011 RT-100 Pre-Application Meeting

Engineering ExperienceExtensive use of ANSYS and LS-DYNA for analysisThermal, Structural and Shielding

USNRC Licensing ProcessAware of USNRC expectations in our meeting the 10CFR71 Licensing RequirementsPast Experience w/B&W on BR-100 MPC & Transport Cask

4

Page 5: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Overview

Applicant – ROBATEL Technologies, LLC

New Cask (RT-100)

Waste: treated spent resins & filters

(Cask designed for additional type contents)

14 November 2011 RT-100 Pre-Application Meeting

Capacity: 160 cf , (10) 55-gallon drums

~15,000 lbs payload

Certificate Type B (U)

5

Page 6: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Overview

Steel – Lead – Steel Cylinder Construction

Toroidal Impact Limiters

PayloadLLRW Resins & Filters

lb f l l d

14 November 2011 RT-100 Pre-Application Meeting

~15,000 lbs useful load

Type B quantity NTE 2000 times Type A quantity

Loaded Weight w/Impact Limiters: ~75,000 lbs

Overweight, Not Oversize

6

Page 7: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Design - Conceptual

14 November 2011 RT-100 Pre-Application Meeting 7

Page 8: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Designs - Dimensions

Nominal Dimensions Inches(approximately)

Overall Length w/Impact Limiters 130

Overall Length w/o Impact Limiters 90

Outside Diameter w/Impact Limiters 100

Outside Diameter w/o Impact Limiters 79

14 November 2011 RT-100 Pre-Application Meeting

Outside Diameter w/o Impact Limiters 79

Cavity Length 77

Cavity Diameter 68

Weight lbs(approximately)

Empty Weight w/Impact Limiters 60,000

Loaded Weight w/Impact Limiters 75,000

8

Page 9: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Design – Characteristics and Contents

Cask CharacteristicsLarge Cavity Size – 160 cfTwo Lifting TrunnionsRoad Transport – OverweightImpact Limiters: wood or foam

14 November 2011 RT-100 Pre-Application Meeting

ContentsResins in linersFilters in linersType B Quantity 2000 times Type AThermal: 100 watts

9

Page 10: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Materials

Structural: ASME/ASTM-A240 304 L Stainless Steel

all structural components

Shielding – 4.5” Pb equivalent on all sides

Stainless Steel

14 November 2011 RT-100 Pre-Application Meeting

Stainless Steel

Lead

Impact Limiters

Considering wood or foam

10

Page 11: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Licensing Approach

SAR Format: Regulatory Guide 7.9Structural Analysis

Use of ANSYS for General Conditions (71.43-45)LS-DYNA confirmed by Benchmark data for NCT (71.71) and HAC (71.73) analyses

Thermal Anal sis

14 November 2011 RT-100 Pre-Application Meeting

Thermal AnalysisUse of ANSYSAnalysis using maximum decay heat of resin payload

Shielding AnalysisUse of MicroShield, MCNPNo credit taken for Impact Limiters

11

Page 12: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Modeling

Computational Analysis Use of Benchmark data from testing of similar casks

over 10 yearse.g, R73 Type B(U) Cask and R74 Type B(U) Cask Approach qualified by previous Drop-Test data and cross-checked with LS-DYNA results

M d li

14 November 2011 RT-100 Pre-Application Meeting

Modeling Free Drops (LS-DYNA plus Benchmark)Puncture Drops (LS-DYNA plus Benchmark)Thermal (1,475⁰ for 30 minutes) (ANSYS)Immersion (50 ft) (ANSYS)Shielding (MicroShield, MCNP)

12

Page 13: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

Representative Robatel Designs

14 November 2011 RT-100 Pre-Application Meeting 13

Page 14: RT-100 Cask Certificate of Compliance Pre …Certificate of Compliance Pre-Application Meeting 14 November 2011 RT-100 Pre-Application Meeting 14 November 2011 Robatel Technologies,

SAR Submittal Schedule

Action Date

SAR Completion and Submittal Goal: March 2012

I f C ifi f C li G l A /S b 2012

14 November 2011 RT-100 Pre-Application Meeting

Issuance of Certificate of Compliance Goal: August/September 2012

14