    System Process DocumentRolling Up Cumulative Lead Times

    Department

    Responsibility/Role

    File Name 27762168.docRevision

    Document Generation Date 18/01/2010 09:40:00

    Date Modified 1/18/2010 09:40:00 AM

    Last Changed by

    Status

    Rolling Up Cumulative Lead Times

    Trigger:

    Concept

    Bills of Material computes cumulative manufacturing lead time and cumulative lead time by

    stepping through indented bill structures. Item information is updated as part of both the

    cumulative calculations.

    Changes to the indented bill of material and component lead times can impact a parent item's

    cumulative lead times. After each change made to a bill (adding components, assigning to a

    different operation, and so on) or the item lead times, you can roll up the cumulative lead times.

    If you choose to roll up cumulative lead times for a range of items, then you can enter a category

    set to roll up the cumulative lead times of the items associated with this category set. The defaultis the category set you defined for your functional area.

    You can also calculate lead times from the Routings page, when creating or updating a routing.

    In this topic, you will roll up cumulative lead times.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/18/2010 09:40:00 AM Page 1

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    2/26

    System Process DocumentRolling Up Cumulative Lead Times

    Procedure

    Step Action

    1. Begin by navigating to the Calculate Lead Times page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    3/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/18/2010 09:40:00 AM Page 3

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    4/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    5/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    6/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    6. Click the M1 Seattle Manufacturing list item.

    Step Action

    7. Click the OKbutton.

    orPress [Alt+O].

    Page 6 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    7/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    8/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    9. Click the OKbutton.

    Step Action

    10. Use the Calculate Lead Times page to enter the name of the request.

    Page 8 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    9/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    11. Click in the Name field.

    Last changed on: 1/18/2010 09:40:00 AM Page 9

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    10/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    11/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    14. Use the Parameters page to enter the parameters for the request.

    Last changed on: 1/18/2010 09:40:00 AM Page 11

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    12/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    15. Click in the Item field.

    Step Action

    16. Use the System Items page to enter the item.

    Page 12 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    13/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    17. Click in the Item field.

    Last changed on: 1/18/2010 09:40:00 AM Page 13

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    14/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    18. Enter the desired information into the Item field. Enter "RT1000".

    Step Action

    19. Click the OKbutton.

    orPress [Alt+O].

    Page 14 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    15/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    20. Click in the Date REQUIRED field.

    Last changed on: 1/18/2010 09:40:00 AM Page 15

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    16/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    17/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    23. Click the Submit button.

    orPress [Alt+m].

    Last changed on: 1/18/2010 09:40:00 AM Page 17

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    18/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    19/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    20/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    21/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    22/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    23/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    24/26

  • 8/14/2019 Rolling Up Cumulative Lead Times_SPD

    25/26

    System Process DocumentRolling Up Cumulative Lead Times

    Step Action

    35. Click the View Details... button.

    orPress [Alt+s].

    Last changed on: 1/18/2010 09:40:00 AM Page 25