Robert Saur
Sr. Remediation Project Manager Environmental Remediation 3401 Crow Canyon Road San Ramon, CA 94583 (925) 415-6371 [email protected]
October 29, 2015 Mr. Kevin Vo and Mr. Paul Hibser Air Quality specialists Bay Area Air Quality Management District 929 Ellis Street San Francisco, CA 94109 Subject: Bi-weekly Asbestos (TEM) Monitoring Report for October 12, 2015 to October 23, 2015. Former Hunters Point Power Plant Site, 151 Jennings Street San Francisco, CA 94124 ADMP RIN # NOA0055 Dear Mr. Vo and Mr. Hibser: Please find attached the bi-weekly report of asbestos monitoring of the former Hunters Point Power Plant site. PG&E is currently working in Area J, and air monitoring for asbestos is implemented in accordance with the BAAQMD approved Asbestos Dust Mitigation Plan (ADMP). ERM performs air monitoring in accordance with the applicable requirements and prepared the attached report. Attached also is an excel spreadsheet with all the TEM data collected from July 2009 to October 23, 2015. Please contact me at 925-415-6371 if you have any questions. Sincerely,
Robert Saur, PG Sr. Remediation Project Manager Enclosure Cc: John Cavanaugh, ERM
29 October 2015
Mr. Rob Saur PG&E 3401 Crow Canyon Road San Ramon, CA 94583 Subject: Biweekly Asbestos (TEM) Monitoring Report for October 12th through October 23th Former Hunter’s Point Power Plant Site 1000 Evans Ave., San Francisco, CA 94124 ADMP RIN # NOA-0055 (Amendment#2)
Dear Mr. Saur:
In accordance with the Bay Area Air Quality Management District (BAAQMD)-approved Asbestos Dust Mitigation Plan (ADMP) amendment dated 2012 May 11, attached is a tabulation of the air monitoring results for airborne asbestos analyzed by Transmission Electron Microscopy (TEM). All air testing was performed in accordance with the approved ADMP. The attached figure shows the location of the Air Monitoring Stations (AMS).
Soil disturbance work was conducted from 12 October to 23 October 2015. During the reporting period, there were no TEM test reports for airborne asbestos that exceed 0.016 structures per cubic centimeter (s/cc), the trigger level established for this project. Site work is ongoing and estimated to be completed in January 2016.
The table below lists the activity and response action at the time of the excedance.
Environmental Resources Management 1277 Treat Boulevard Suite 500 Walnut Creek, CA 94597 (925) 946-0455 (925) 946-9968 (fax) www.erm.com
Mr. Rob Saur 29 October 2015 Page 2
Environmental Resources Management
Date Station ID/Area
Result (s/cc)
Average Wind Speed & Direction
Activity Onsite Response Action
No exceedances for this reporting period.
Please feel free to call me if you have any questions.
Sincerely,
Veronica Shannon Site Compliance Officer
Cell: 818-280-7501 email: [email protected] enclosures Table 1: Area Monitoring – TEM Figure 1: Site Plan
Mr. Rob Saur 29 October 2015 Page 3
Environmental Resources Management
TABLE 1
Perimeter Zone Monitoring – Airborne Asbestos (s/cc) by TEM (CARB-modified AHERA) PG&E Former Hunters Point Power Plant - Site Management Activities
Collection Date: Station # Sample ID Start-End
Time Duration
(Min) Volume
(liter) Results (s/cc)
Wind Direction (Compass) &
Speed
10/12/15 Mon AMS-J-1 AMS-J-1-101215 15:15-15:35 1,460 4,374 < 0.0010
SSE, 2-4MPH 10/12/15 Mon AMS-J-2 AMS-J-2-101215 15:02-15:02 1,440 4,039 0.0019
10/12/15 Mon AMS-J-3 AMS-J-3-101215 15:25-15:30 1,445 3,651 0.002
10/13/15 Tue AMS-J-1 AMS-J-1-101315 15:05-15:42 1,475 3,587 0.0037
SE, 2MPH 10/13/15 Tue AMS-J-2 AMS-J-2-101315 8:42-16:30 468 1,198 0.0049
10/13/15 Tue AMS-J-3 AMS-J-3-101315 15:30-16:05 1,475 3,688 0.001
10/14/15 Wed AMS-J-1 AMS-J-1-101415 15:45-15:27 1,422 3,434 <0.0010
NW, 8MPH 10/14/15 Wed AMS-J-2 AMS-J-2-101415 16:30-15:15 1,365 3,092 <0.0010
10/14/15 Wed AMS-J-3 AMS-J-3-101415 16:05-15:47 1,422 3,271 <0.0010
10/15/15 Thu AMS-J-1 AMS-J-1-101515 15:30-15:00 1,410 4,047 <0.0010
SE, 2-8MPH 10/15/15 Thu AMS-J-2 AMS-J-2-101515 15:15-14:45 1,410 3,328 <0.0009
10/15/15 Thu AMS-J-3 AMS-J-3-101515 15:50-15:20 1,410 4,060 <0.0011
10/16/15 Fri AMS-J-1 AMS-J-1-101615 15:00-13:22 1,342 3,301 <0.0010
NW, 4MPH 10/16/15 Fri AMS-J-2 AMS-J-2-101615 14:45-13:10 1,345 4,667 <0.0009
10/16/15 Fri AMS-J-3 AMS-J-3-101615 15:20-13:35 1,335 4,539 <0.0010
10/19/15 Mon AMS-J-1 AMS-J-1-101915 15:35-15:10 1,395 4,437 0.0019
W, 15MPH
10/19/15 Mon AMS-J-2 AMS-J-2-101915 8:45-15:47 422 3,136 0.002
Mr. Rob Saur 29 October 2015 Page 4
Environmental Resources Management
TABLE 1
Perimeter Zone Monitoring – Airborne Asbestos (s/cc) by TEM (CARB-modified AHERA) PG&E Former Hunters Point Power Plant - Site Management Activities
Collection Date: Station # Sample ID Start-End
Time Duration
(Min) Volume
(liter) Results (s/cc)
Wind Direction (Compass) &
Speed
10/19/15 Mon AMS-J-3 AMS-J-3-101915 15:52-15:30 1,418 4,282 <0.0009
10/20/15 Tue AMS-J-1 AMS-J-1-102015 15:10-15:17 1,447 4,209 0.0009
S, 2MPH 10/20/15 Tue AMS-J-2 AMS-J-2-102015 15:50-15:05 1,395 3,976 0.001
10/20/15 Tue AMS-J-3 AMS-J-3-102015 15:30-15:36 1,446 4,692 <0.0009
10/21/15 Wed AMS-J-1 AMS-J-1-102115 15:17-15:20 1,443 5,224 <0.0009
NW, 3-5MPH 10/21/15 Wed AMS-J-2 AMS-J-2-102115 15:05-15:05 1,440 3,816 0.0019
10/21/15 Wed AMS-J-3 AMS-J-3-102115 15:36-15:38 1,442 4,066 0.001
10/22/15 Thu AMS-J-1 AMS-J-1-102215 7:53-15:00 427 1,789 <0.0010
SE, 0-1MPH 10/22/15 Thu AMS-J-2 AMS-J-2-102215 15:05-15:40 1,475 4,307 <0.0009
10/22/15 Thu AMS-J-3 AMS-J-3-102215 15:38-15:18 1,460 3,957 0.001
10/23/15 Fri AMS-J-1 AMS-J-1-102315 15:00-15:31 1,471 3,655 <0.0010
NE, 0-10MPH 10/23/15 Fri AMS-J-2 AMS-J-2-102315 15:41-15:08 1,407 4,559 <0.0009
10/23/15 Fri AMS-J-3 AMS-J-3-102315 15:18-15:38 1,460 3,679 0.001 NOTES: (1) Sampling flow rates are below 10 liters per minute, per sampling method. (2) Lab analysis performed by Asbestos TEM Laboratory, Berkeley, CA. (NVLAP Accreditation #: 101891-0) (3) Samples collected on 25-mm, 0.45-micrometer Mixed Cellulose Ester Filters in conductive cassettes. (4) “<” result = below detection limit for the sample. (5) s/cc = structures/cubic centimeter; Min = minutes; AMS = Air Monitoring Station (6) BAAQMD has been notified of results exceeding 0.0162 s/cc, and additional dust mitigation measures have been
implemented. (7) NA = not available
WAREHOUSE
WHITE CAPPROPERTY
AREAAREA B
CENTRAL
AREA J
AREA C/DOPERATING SUBSTATION
AREA H
AMS-J-1
AREA I AREA BSOUTH
AREA A
AREA BNORTH
UNIT 4BASEMENT AREA
APPROXIMATEPREVAILING WIND
DIRECTION
AMS-J-2
AMS-J-3
0 100' 200' 400'
SCALE IN FEET
LEGEND
Remediation And Restoration In AreaComplete Or Inactive Area
Operating Substation Boundary
Active Remediation Area
Potential Mobile Air Monitoring Station
Indicates Example Range Of Mobile AirMonitoring Station Locations
© ERM
Figure 1