riverside community college district

10
FY 2011-2012 Final Budget Riverside Community College District

Upload: gezana

Post on 06-Feb-2016

38 views

Category:

Documents


0 download

DESCRIPTION

Riverside Community College District. FY 2011-2012 Final Budget. Riverside Community College District FY 2011-2012 Final Budget. The District prepared a 2011-2012 budget projection following release of the Governor’s initial budget proposal in January 2011. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Riverside Community College District

FY 2011-2012 Final Budget

Riverside Community College District

Page 2: Riverside Community College District

The District prepared a 2011-2012 budget projection following release of the Governor’s initial budget proposal in January 2011.

That projection reflected a budget problem, composed of both reduced revenues and increased costs, in the amount of $18.4 million.

A plan for addressing this problem was then developed and discussed in a variety of forums, including a presentation to the Board of Trustees in February 2011.

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 3: Riverside Community College District

FY 2011-2012 Budget Problem $ (18.41)

Proposed Budget Adjustments/Strategies

1. Contingency Drawdown to 5% Reserve Level (July 1, 2011) $ 3.22

2. FY 2009-2010 P1 Apportionment Adjustment 0.40

3. DSPS Revenue Adjustment/Categorical Backfill Reduction 0.72

4. PERS Rate Increase Adjustment from 14.0% to 13.3% 0.24

5. No Additional BCTC Sheriff Academy 0.34

6. Payoff Major Gifts Campaign Receivable andEliminate Performance Riverside Accumulated Deficit1.63

7. Outsource Safety & Police Dispatch Operation 0.25

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 4: Riverside Community College District

Proposed Budget Adjustments/Strategies (continued)

8. Eliminate March Dental & March Education Center Rent 0.16

9. Reduce New Facility Operating Cost Estimates 0.84

10. Reduce Printing of Class Schedule & Catalog 0.05

11.Positive Budget Variance 2.94

12.Enrollment/Schedule Reductions 2.93

13.Compensation Adjustment 0.28

14.Short-Term Temporary & Student Employees - 20% Reduction 0.37

15.Reduce 5% Contingency Reserve to 3.0% 2.92

16. Interfund Borrowing from Resource 4130 (La Sierra Capital) 1.12

FY 2011-2012 Remaining Budget Problem $ -

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 5: Riverside Community College District

Although there are some differences in the detail, our early analysis of the 2011-2012 State budget situation was on target. Thus, the proposed 2011-2012 RCCD budget is based on the plan we developed several months ago.

The plan for addressing the FY 2011-2012 budget shortfall included a loan of $1.12 million from Resource 4130 (La Sierra Capital). Since the contingency/reserve balance is projected to be above the 3% level, the additional loan was not included in this budget proposal.

FY 2011-2012 Reserve Requirement 3% $ 4.47Contingency/Reserve Balance 5.84

Amount Above 3% $ 1.37

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 6: Riverside Community College District

Risks

The District faces the very real possibility of mid-year general apportionment reductions if State revenue projections are not realized. The reductions will be “triggered” in two phases referred to as Tier 1 and Tier 2. In addition, it is likely that the State has overestimated the amount of student enrollment fees by a approximately $25 million.

Mid-Year Reduction ScenarioDistrict

Tier 1 ($30 Million Systemwide) $ 0.73

Tier 2 ($72 Million Systemwide) 1.75

Enrollment Fee Shortfall ($25 million Systemwide) 0.61

Total $ 3.09

Possible Solutions to Mid-Year Reductions in FY 2011-2012

December 31, 2011 Retirees Estimated Golden Handshake Savings $ 1.00

Contingency/Reserve Amount Above 3% 1.37

Total $ 2.37

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 7: Riverside Community College District

Enrollment

For fiscal ’12, the District will face a 6.21% workload reduction directed by the State, which equates to 1,666 credit FTES. Significant enrollment risk exists within the State adopted budget. If certain revenue projections fail to materialize, the two mid-year revenue reductions mentioned previously could be triggered, resulting in additional workload reductions. Tier 1 could result in a workload reduction of 160 credit FTES. Tier 2 could result in an additional workload reduction of 383 credit FTES.

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 8: Riverside Community College District

Mid-Year Reductions

Budget Possible PossibleProposal Tier 1 Tier 2

Credit FTES

Beginning Funded Base Credit FTES 26,811 26,811 26,811

Less, Workload Reduction (1,666) (1,826) (2,209)

Ending Funded Credit FTES 25,145 24,985 24,602

Colleges Target Credit FTES 26,357 26,357 26,357

Unfunded Credit FTES (1,212) (1,372) (1,755)

Unfunded Percentage -4.82% -5.49% -7.13%

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 9: Riverside Community College District

Looking Ahead – FY 2012-2013

The prospects for the FY 2012-2013 budget picture are not good. It is likely the State’s budget situation will deteriorate. Our budgetary problems are three fold:

Decreasing budgets from the State. Built-in cost escalation in our expenditure budgets. A budgetary imbalance whereby ongoing budget issues are being addressed by one-time

budget solutions. A “Solutions Sustainability Analysis” was prepared several months ago to assist the District in assessing this situation (see the following page).

$8.30 million of our $18.41 million budget problem for FY 2011-2012 was solved via the use of one-time funding.

Interfund borrowing was used to solve one-time budget problems for fiscal ’12 and fiscal ‘11.

The combination of one-time solutions, interfund loan repayments, annual State budget cutting and cost escalation factors (e.g. new space to maintain, contractual agreements, etcetera), have created an overall budget problem for RCCD that requires that we focus our attention beyond the annual budget.

Riverside Community College DistrictFY 2011-2012 Final Budget

Page 10: Riverside Community College District

Solutions Sustainability Analysis*

FY 2012-13 Projection Best Middle Worst Case Case Case

Revised Projection $ (1.88)1 $ (5.77)2 $ (7.43)3

Prior-Year One-Time Solutions (8.30) (8.30) (8.30)

Projected Budget Problem,Fiscal Year 2012-13 $(10.18) $(14.07) $(15.73)

1 Assumes $5.94m in New State Funding2 Assumes $1.67m in New State Funding3 Assumes No New State Funding

*Presented to the Board of Trustees and to college and District groups in Spring 2011

Riverside Community College DistrictFY 2011-2012 Final Budget