risk( 风险 ) management presented by basker george

27
Risk( 风风 ) Management Presented by Basker George

Upload: blaze-bennett

Post on 03-Jan-2016

302 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Risk( 风险 ) Management Presented by Basker George

Risk( 风险 ) Management

Presented by Basker George

Page 2: Risk( 风险 ) Management Presented by Basker George

Risk Management Any project can fail Reasons for failure

Lack of proper engineering Lack of proper Management Occurrence ( 出现 ) of some unforeseen

( 无法预料的 ) events Any other problem

Page 3: Risk( 风险 ) Management Presented by Basker George

Risk Management The basic goal of all activities in a project is to ens

ure( 保证得到 ) that project succeeds. The engineering activities ensure that project doe

s not fail on engineering front( performance( 性能 ), functionality ( 功能性 , 泛函性 ) & Quality).

The Project Management activities focus on making sure that project does not fail due to poor management.

Risk Management tries to minimize the chance of failure caused by unforeseen events( 事件 ).

Page 4: Risk( 风险 ) Management Presented by Basker George

Risk Management

In project, a RISK is any condition or event ( 事件 ) whose occurrence ( 发生 ) is not certain( 确定的 ).

That is a event that can affect in a unfavorable ( 不宜的 ) manner.

The two element of risk are: Occurrence of risk is probabilistic( 或然说的 ) If it occurs, it can cause damage to project.

Page 5: Risk( 风险 ) Management Presented by Basker George

Risk Management The purpose of Risk Management is to

identify potential ( 可能的 ,) risk & then take actions such that their effect on project is. Minimized( 最小化 ).

Proper process for RISK MANAGEMENT are a requirement for Integrated Software Management KPA at CMM Level 3.

Page 6: Risk( 风险 ) Management Presented by Basker George

Risk Management In this cheaper we shall study

General concept of RISK & Risk Management

Risk Assessment( 估价 ) Risk Control

Page 7: Risk( 风险 ) Management Presented by Basker George

Background Risk is the possibility of loss, injury( 伤害 ) ,

disadvantage or destruction ( 破坏 ). Risk are events or condition that may or m

ay not occur, “wish they will never occur”.

When it occurs, It has negative impact ( 效果 ) on the project

Page 8: Risk( 风险 ) Management Presented by Basker George

Risk management Risk management is

to identify the possible risk Assess the consequence( 结果 ) Plan to overcome ( 战胜 ) risk

Page 9: Risk( 风险 ) Management Presented by Basker George

Risk management activities Risk assessment

Risk identification ( 辨认 ) Risk analysis( 分析 ) Risk prioritization( 优先 )

Risk control Risk management planning Risk resolution( 决心 ) Risk monitoring( 控制 )

Page 10: Risk( 风险 ) Management Presented by Basker George

Risk management & project execution

Risk Assessment

Monitoring

Managing

Risk

Project processinformation

control

Other

factors

Page 11: Risk( 风险 ) Management Presented by Basker George

Risk Management at Infosys Risk Assessment

At Infosys risk assessment consists of two components:

Risk Identification Risk Prioritization

Page 12: Risk( 风险 ) Management Presented by Basker George

Risk Identification This activity focuses on enumerating ( 列

举 ) possible risk to projects Checklist of possible risk Interview, Meeting, & brainstorming( 智力

爆发 ) Review of plan, process & work products Surveys Risk management of similar project in PDB

Page 13: Risk( 风险 ) Management Presented by Basker George

Risk Prioritization The identified risk give a

possible event Therefore the risk has to be

prioritize to focus & manage the highest risk

It has to be analyzed for the possible effect & loss to the project.

Page 14: Risk( 风险 ) Management Presented by Basker George

Risk Prioritization Since risk is a probabilistic in nature, i

t can be categorized as: Risk Category ( 种类 ) Impact Category.

Page 15: Risk( 风险 ) Management Presented by Basker George

Risk CategoryProbability Range

Low 0.0 to 0.3

Medium 0.3 to 0.7

High 0.7 to 1.0

Page 16: Risk( 风险 ) Management Presented by Basker George

Impact Category

Level of consequences

Range

Low 0 - 3

Medium 3 - 7

High 7-9

Very High 9-10

Page 17: Risk( 风险 ) Management Presented by Basker George

Cont… The steps in risk prioritization are: For each risk, rate the probability for the risk

as Low, Medium, or High (0 – 1). For each risk, assess its effect on the project

as Low, Medium, High, V High(1-10) Rate the risk based on the probability &

effect on the project. Select the top risk items for mitigation &

tracking

Page 18: Risk( 风险 ) Management Presented by Basker George

Risk Control Once the risk has been identified & prioritiz

ed plan & manage them so that their consequence is minimal.

That is… Planning of risk mitigation( 减轻 ) Execution of a plan Monitoring the risk

The process database can also be used to identify risk & mitigation steps.

Page 19: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

1 Shortage of technically trained manpower

Make estimates with little allowance for initial learning timeMaintain buffers of extra resourceDefine project specific training programConduct cross-training session

Page 20: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

2 Too many requirement changes

Obtain sign off for initial requirement specification from clientConvince the client that changes in requirement will affect the scheduleDefine a procedure to handle requirement changesNegotiate payment on actual effort

Page 21: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

3 Unclear requirement

Use experience & logic to make some assumptions & keep the client informed; obtain sign- offDevelop prototype /get the requirement reviewed by the client

Page 22: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

4 Manpower attrition

Ensure multiple resource are assigned on key project areasHave team buildingRotate jobs among team membersKeep extra resources in the project as backupMaintain proper documentation of individual workFollow the configuration management process & guidelines strictly

Page 23: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

5 Externally driven decisions forced on project

Outline disadvantages with supporting facts/data & negotiate with the personnel responsible for forcing the decisions.If inevitable, identify the actual risk & follow its mitigation plan

Page 24: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

6 Not meeting performance requirements

Define the performance criteria clearly & get them reviewed by the clientDefine standards to be followed to meet the performance criteriaPrepare the design to meet performance criteria & review itSimulate prototype performance of critical transactionTest with a representative volume of data where possibleConduct stress test where possible.

Page 25: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

7 Unrealistic Schedule

Negotiate for a better scheduleIdentify parallel taskHave resource earlyIdentify area that can be automatedIf the critical path is not within schedule, negotiate with the clientNegotiate payment on actual effort

Page 26: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

8 Working on new technology(Hardware & Software)

Consider a phased deliveryBegin with the delivery of critical modulesInclude time in the schedule for learning curveProvide training in the new technologyDevelop proof-of-concept application

Page 27: Risk( 风险 ) Management Presented by Basker George

Top Ten Risk & their risk mitigation steps

Sq. No

Risk Category

Risk Mitigation Steps

9 Insufficient business knowledge

Increase interaction with the client & ensure adequate knowledge transfer.

10 Link failure / slow performance

Set proper expectation with the clientPlan ahead for the link loadPlan the optimal link usage