risk assessment for the second day of filming
TRANSCRIPT
Production title:Short film
Production date(s):19/11/14
Producer name:Emma Irwin, Ellisha Clapham, Alice Mee, Amber Renshaw
Director name:Emma Irwin, Ellisha Clapham, Alice Mee, Amber Renshaw
Date of risk assessment:19/11/14
Risk assessment conducted by:Emma Irwin
Hazard Persons who may be harmed
Property that could be damaged
Risk controls that are already in place
Risk Assessment, LOW, MODERATE, HIGH, EXTREME
Further action required to control risk
Tripping on lamp wires
All team and cast Camera, tripod and lamp
No running, sensible shoes, acting sensibly
Moderate Make sure everyone is aware where the wires are, and act sensibly
Camera falling when doing high angle shots
All team and cast Camera and tripod Make sure that the equipment is stable, and at sensibly
Moderate Warn people to take extra care when handling the equipment and be co-operative
Falling in the dark
All team and cast Camera, tripod and lamp
No running and make sure there is always a source of light
Low Warm people to take extra care when around the equipment
FILM PRODUCTION RISK ASSESSMENT