Ringling Riverfront Redevelopment Update

July 2, 2009

Page 2: Ringling Riverfront Redevelopment Update July 2, 2009

Presentation Overview

• Riverfront Redevelopment Area Plan Review

• Implementation Recommendations

• Additional Implementation

• Next Steps

Page 3: Ringling Riverfront Redevelopment Update July 2, 2009

Presentation Overview

• Riverfront Redevelopment Area Plan Review

• Implementation Recommendations

• Additional Implementation

• Next Steps

Page 4: Ringling Riverfront Redevelopment Update July 2, 2009

Planning Purpose

• Baraboo Comprehensive Plan – Public identified riverfront redevelopment as a high priority project.

• Wisconsin Department of Commerce Grant

Page 5: Ringling Riverfront Redevelopment Update July 2, 2009
Page 6: Ringling Riverfront Redevelopment Update July 2, 2009
Page 7: Ringling Riverfront Redevelopment Update July 2, 2009
Page 8: Ringling Riverfront Redevelopment Update July 2, 2009

Market Opportunities Related to Market Niche

• Riverfront Residential

• Riverwalk Entertainment/Retail• Employment – Knowledge Worker (Secondary Impact)

• Riverwalk

• Range View Housing

Page 9: Ringling Riverfront Redevelopment Update July 2, 2009

Riverfront Residential– Central location for residents adjacent to water– Accommodate all markets within the River Corridor

• Young professionals• Madison transplants• Aging Baby-boomers

Page 10: Ringling Riverfront Redevelopment Update July 2, 2009

Riverwalk Retail & Entertainment– Capitalize on river as asset– Activities that compliment Downtown and Circus World

Museum– Orient restaurants to the river– Create open access to the river and riverwalk– Host four-season activities (e.g. ice rink)

Page 11: Ringling Riverfront Redevelopment Update July 2, 2009

Employment– Generate office space in second stories– Create a market to drive new start-up businesses– Offer employment downtown or along the river– Establish another level of economic development

Page 12: Ringling Riverfront Redevelopment Update July 2, 2009

Riverwalk– Edge restoration with native vegetation– Ensure public access to the river– Create trails– Orient land uses and activities to the river

Page 13: Ringling Riverfront Redevelopment Update July 2, 2009

Riverwalk

Page 14: Ringling Riverfront Redevelopment Update July 2, 2009

Range View Housing– Serve as a window to the southern range– Capture views of the area’s natural attractions

Page 15: Ringling Riverfront Redevelopment Update July 2, 2009
Page 16: Ringling Riverfront Redevelopment Update July 2, 2009
Page 17: Ringling Riverfront Redevelopment Update July 2, 2009
Page 18: Ringling Riverfront Redevelopment Update July 2, 2009
Page 19: Ringling Riverfront Redevelopment Update July 2, 2009
Page 20: Ringling Riverfront Redevelopment Update July 2, 2009

Presentation Overview

• Riverfront Redevelopment Area Plan Review

• Implementation Recommendations

• Additional Implementation

• Next Steps

Page 21: Ringling Riverfront Redevelopment Update July 2, 2009

– Review private development proposals– Determine proposal compatibility with the Redevelopment Area Plan,

Comprehensive Plan, and City zoning

Plan Commission

Suggested Implementation Roles

– Policy and decision makers regarding funding and public expenditures– Approval authority for proposed redevelopment projects– Direct the CDA

City Council

Page 22: Ringling Riverfront Redevelopment Update July 2, 2009

– Review initial redevelopment proposals and provide recommendations to Plan Commission

– Serve as a conduit between the public and Riverfront Corridor implementation activities

– Lead redevelopment efforts (powers need City Council approval)– Own, lease, sell acquire, and operate property/housing projects– Bond, borrow, invest, and raise funds– Acquire, assemble, relocate, demolish, and prepare sites– Recruit developers– Administer redevelopment projects

CDA

Suggested Implementation Roles

BEDC

Page 23: Ringling Riverfront Redevelopment Update July 2, 2009

Suggested Implementation Roles

– Administers day-to-day redevelopment activities– Develop marketing materials, direct developer recruitment, RFPs– Provide legal advise in developer negotiations and environmental negotiations– Manage design and construction of public improvements– TIF management– Report to City Council– Revise Riverfront Redevelopment Area Plan, as needed

PMT

Page 24: Ringling Riverfront Redevelopment Update July 2, 2009

Implementation Recommendations

1. Establish a PMT

COMPLE

TED

• 11 areas of responsibility

• Monthly teleconferences

• 16-item agenda with multiple tasks

Page 25: Ringling Riverfront Redevelopment Update July 2, 2009

Implementation Recommendations

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

INCOMP

LETE

• Guides TIF implementation

• Assigned to the CDA

• Placed on-hold by City Council

Page 26: Ringling Riverfront Redevelopment Update July 2, 2009

Implementation Recommendations

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

3. Create Design Guidelines and Zoning Overlay District

• Makes guidelines mandatory

• Using CU and PUD processes

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

3. Create Design Guidelines and Zoning Overlay District

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

3. Create Design Guidelines and Zoning Overlay DistrictINC

OMPLET

E

COMPLE

TED

Page 27: Ringling Riverfront Redevelopment Update July 2, 2009

Implementation Recommendations

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

3. Create Design Guidelines and Zoning Overlay District

4. Undertake District-wide Marketing Initiative

On-Goi

ng

• Branded as “Ringling Riverfront”

• Continue marketing as needed in the future

• Market as part of the downtown??

Page 28: Ringling Riverfront Redevelopment Update July 2, 2009

Implementation Recommendations

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

3. Create Design Guidelines and Zoning Overlay District

4. Undertake District-wide Marketing Initiative

5. Seek Additional Grants for Implementation

On-Goi

ng

• Awarded $1.2 million in USEPA grants since 2006

• $600,000 is site assessment

• $600,000 for Alliant site clean-up

Page 29: Ringling Riverfront Redevelopment Update July 2, 2009

1. Establish a PMT

2. Prepare a Statutory Redevelopment Plan

3. Create Design Guidelines and Zoning Overlay District

4. Undertake District-wide Marketing Initiative

5. Seek Additional Grants for Implementation

6. Zoning Decisions Consistent with the Plan

• NAPA

• Gilbert/Boo Canoe

• Diner

• Walnut Street Apartments

On-Goi

ng

Implementation Recommendations

Page 30: Ringling Riverfront Redevelopment Update July 2, 2009
Page 31: Ringling Riverfront Redevelopment Update July 2, 2009

Presentation Overview

• Riverfront Redevelopment Area Plan Review

• Implementation Recommendations

• Additional Implementation

• Next Steps

Page 32: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisition

• Closed (Summer 2008)

• Alliant planned to vacate site by mid July 2009

• Purchased with DOC grant funds

Page 33: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisition

Page 34: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisition

• Two public input meetings

• Developed Revitalization Action Model (31 measures)

• Baraboo is now a national ASTDR model

• Video production

Page 35: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisition

• On-going line re-routing negotiations

• Determine appropriate relocation site (no sites have been targeted to date)

Page 36: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisition

• Ice Age Trail

• NAPA land exchange

• Riverwalk and gazebo construction

Page 37: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisition

• RFP Drafted and Issued (summer 2008)

• Sara Investments selected (fall 2008)

• Completed Phase I environmental (late 2008)

• Ongoing tenant recruitment (Sara)

• Ongoing negotiations with Veolia (City and Sara)

Page 38: Ringling Riverfront Redevelopment Update July 2, 2009

Additional Implementation

7. Alliant Site Purchase

8. Environmental Assessment

9. Health Monitoring

10. Substation Relocation Planning

11. Riverfront Improvements

12. Veolia Site Developer Selection and Negotiation

13. Lynn Street Property Acquisitions

• Independently negotiated by Gilbert

• Proposed for public parking lot

• Closed (late spring 2009)

• DOC Grant funds

Page 39: Ringling Riverfront Redevelopment Update July 2, 2009

Publicly Owned Lands

Page 40: Ringling Riverfront Redevelopment Update July 2, 2009

Presentation Overview

• Riverfront Redevelopment Area Plan Review

• Implementation Recommendations

• Additional Implementation

• Next Steps

Page 41: Ringling Riverfront Redevelopment Update July 2, 2009

Next Steps1. Determine appropriate roles of the CDA and BEDC

2. Revisit the need for a Statutory Redevelopment Plan

3. Finalize Veolia relocation and redevelopment

4. Remediate Alliant and seek a developer

5. Identify next priority redevelopment sites

6. Begin environmental assessment of additional sites

Page 42: Ringling Riverfront Redevelopment Update July 2, 2009

Next Steps7. Initiate Co-op site development

8. Continue relocation discussion with Mueller Dairy

9. Initiate relocation discussion with Servo

10. Finalize substation relocation and routing

11. Continue riverwalk construction in conjunction with new development

12. Continue to seek additional grants

13. Continue to work with property owners and developers