CONSTRUCTION OF CEMENT CONCRETE ROAD
3
SUBMITTED TO - SUBMITTED BY-
H.O.D CIVIL ENGINEERING Dr .V.K.GUPTA
HINDUSTAN COLLEGE OF SCIENCE & TECHNOLOGY
ANIL GUPTAVII SEM
1206400013
4
PUBLIC WORKS DEPARTMENT- AN OVERVIEW
Public Works Department (PWD), under the Ministry of Public Works department, is the pioneer in construction arena of Uttar Pradesh.
It plays a pivotal role in the implementation of government construction projects
To accelerate the construction of bridges in the state, Uttar Pradesh State Bridge Corporation was founded in 1973.
In year 2004-05, Uttar Pradesh state highways authority was established to overcome with problem of pavements in state.
5
INTRODUCTION
Development of a country depends on the connectivity of various places with adequate road network.
Roads constitute the most important mode of communication in areas where railways have not developed much.
India has one of the largest road networks in the world (over 3 million km at present).For the purpose of management and administration, roads in India are divided into the following five categories:
• National Highways (NH)• State Highways (SH)• Major District Roads (MDR)• Other District Roads (ODR)• Village Roads (VR)
•
6
WHAT IS ROAD AND PAVEMENT ?
Road is an open, generally public way for the passage of vehicles, people, and animals.
Pavement is finished with a hard smooth surface. It helped make them durable and able to withstand traffic and the environment. They have a life span of between 20 – 30 years.
• FUNCTIONS• One of the primary functions of pavement is load distribution. It can be
characterized by the tire loads, tire configurations, repetition of loads, and distribution of traffic across the pavement, and vehicle speed
7
TYPES OF PAVEMENTSThere are various types of pavements depending upon the materials used; a briefs description of all types is given here-
FLEXIBLE PAVEMENT
Bitumen has been widely used in the construction of flexible pavements for a long time. This is the most convenient and simple type of construction. The cost of construction of single lane bituminous pavement varies from 20 to 30 lakhs per km in plain area.Flexible pavement have-
Have low flexural strength
Load is transferred by grain to grain contact
Have low completion cost but repairing cost is high
Have low life span (High Maintenance Cost)
8
RIGID PAVEMENT
• Rigid pavements, though costly in initial investment, are cheap in long run because of low maintenance costs, The cost of construction of single lane rigid pavement varies from 35 to 50 lakhs per km in plain area,
• Rigid pavement have-
Deformation in the sub grade is not transferred to subsequent layers
Design is based on flexural strength or slab action
Have high flexural strength
No such phenomenon of grain to grain load transfer exists
Have low repairing cost but completion cost is high
Life span is more as compare to flexible (Low Maintenance Cost)
9
Longitudinal joint
Transverse joint
Subgrade Base
Surface Texture
Surface smoothness Thickness Design
Dowel bars
Concrete materials
Tiebars
Basic Components of a Concrete Pavement
10
Using mix Concrete , there some Point to construct the road-
1. Preparation of base2. Form working3. Preparation of subgrade4. Watering of base5. Joints6. Material mix & placing7. Compaction
11
Using mix Concrete , there some Point to construct the road-
8. Finishing of surface8A. Floating8B. Belting8C. Brooming9. Curing10. Joint filling11. Edging12. Open to traffic
12
1. Preparation of subgrade
1. Rolling on sub grade by roller2. Filling the granular soil in the weak part and pot
holes3. Correct the soil coat , Camber , longitudinal slop When concrete direct laid on subgrade, For preventing the water-seepaging into the soil , used water proof paper on entire length.
13
PREPERATION OF SUB GRADE
14
ROLLING OF SUBGRADE
15
2. Preparation of base
Choose any one type of base1. W.B.M. base As base material of W.B.M. Road; stone ballast, concrete 10-15cm layer are used. For bonding between concrete slab & W.B.M. used 1:2 cement wash on W.B.M.2. Concrete base On the road used 10cm Cement concrete(1:2:4) or lime concrete(16:32:64)
16
3. Granular medium material layer 10-15cm composite layer of sand , moorum , bajri are used for better drainage facilities4. Stabilization soil
17
3. Form work Material for form work- Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope, minerals.
1. before using form work, it should free from all type material like as dust ,cement. 2. To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden sheeting.
18
3. The depth of wooden block must be same as level of slab thick. 4. After 24hrs form work displaced next length of road.
19
4. Watering of base
If base is dryThan using the sprinkling process on it properly after that placing the concrete.
20
5. JOINTS
Where is necessary to provide transverse, Longitudinal joints; there wedge of woods, metals fix on level of concrete. After setting of concrete it should be pull out. If provided the dowel bar in joints, bars should be fit at right position.
21
6. Material mix & placing
Mixer is equipment that mix the concrete using distinct amount of cement , concrete, sand and water. Concrete slab should have more than 5-10cm thick cause of drying.Used two type mixer-1. Batch mixer- at site, used for small road construction2. Continuous mixer- Continuous mixer used for large construction . if distance is more from site , mix concrete transported at site within setting time.
22
23
Laying of polyethylene sheet over DLC
24
25
Two methods generally used in placing of concrete-1. Alternate bay method- Placed the concrete on both side of road alternatively like as1,3,5… part at one side and 2,4,6… part other side . 1st side 2nd sideThis method have slow process due to road traffic problems.
26
2. Continuous bay method- construct one side of road regularly, if completed some part of first side than construct other side. this method have fast process without no obstruction of traffic
27
7. Compaction
Purpose of compaction is that to pull out air from void and make concrete harden. Compaction done by- 1.mechanically surface vibrator 2. manually hand tempers
28
8. Finishing of surface
1.Floating- For levelling the surface use floating, scree-ding , power trowel. So that there is no acceptable more than 3mm variation in concrete level surface.2.Belting- For making surface clean used belting process. Belt is nothing but a 15-30cm thick sheets of canvass which have more length than road.
29
30
3. Brooming- Brooming is the process in which we made rough surface parallel to road by brush. It useful in avoiding slip & comfortable travelling on road . the depth of line on road no more than 1.5mm.
31
Texturing of finished surface by texturing machine
32
9. Curing
Curing is the name of increasing the hydration process of cement. after setting the concrete , curing process done till 14-28days.
33
Some method of curing are-1.Shading concrete works2. Covering with hessian & gunny bags3. Sprinkling of water4.By ponding5. Membrane curing6. Steam curing
34
CURING
35
10. Filling joint
After drying road, clean the joints and fill the shelling compound or hot bitumen . also bitumen fill road bank.
36
11. Edging
To protect damaging the sides of concrete pavements used over burnt brick work. in place of brick, provided kerb of pre mix concrete.
37
12. OPEN TO TRAFFIC
Generally after a month, road should be open to traffic. If used rapid hardening cement it take 7 days to open traffic.
38
Advantages of Concrete Road
• Durability and maintenance free life• Vehicles consume less fuel• Resistant to automobile fuel spillage and
extreme weather• Greener process• Saving of natural resources• Eco friendly process