Page 1: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOTTransportationTransportation

Management Plans:An Overview

R ll B H lt P E

May 3, 2011

Russell B. Holt, P.E.Senior Civil EngineerTraffic Engineering Unitg gRhode Island Department of Transportation

Page 2: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

Rhode Island FactsRhode Island Facts• Population: 1,018 per Sq. Mi.

S d b Th I t t t• Served by Three Interstate Routes– I-95 (190,000 ADT)– I-195 (170,000 ADT)– I-295 (90,000 ADT)

• RIDOT Owns/Maintains:– 1,102 Highway-Miles

• ~2,900 Lane-Miles– 644 Bridgesg

• ~20% Structurally Deficient– 790 Traffic Signals

• 80 Roadway Fatalities/Year

May 3, 2011 RIDOT TMPs: An Overview 2

80 Roadway Fatalities/Year

Page 3: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

Work Zones in Rhode Islanddo cause impacts!do cause impacts!

May 3, 2011 RIDOT TMPs: An Overview 3

Page 4: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT Policy on TMPsRIDOT Policy on TMPs

• Work Zone Safety & Mobility Policy/DPMWork Zone Safety & Mobility Policy/DPM– Adopted December 2008

Require:– Require:• Identification of Significant Projects• Assessment of Work Zone ImpactsAssessment of Work Zone Impacts• Selection of Appropriate Transportation

Management Strategies• TMP Development

May 3, 2011 RIDOT TMPs: An Overview 4

Page 5: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT Work Zone Impact LevelsRIDOT Work Zone Impact Levels

W k ADT on Most

H il Anticipated D f Work

Zone Impact Le el

Work Anticipated to Include

Lane Cl ?

Anticipated Duration of

W k

Heavily Traveled Roadway

within Project Li it

Anticipated Level of Public

I t t

Degree of Adverse Impact to Road Users

Without Miti ti

PossibleE lLevel Closures? Work Limits Interest Mitigation Examples

1 Yes Very Long > 50,000 Very High Very HighReconstruction Projects on major freeways

2 Yes Moderate to Very Long > 15,000 Moderate to

High HighMajor bridge Projects on principal arterials

3 Yes Short toVery Long Any Low to

Moderate ModerateResurfacing Projects on minor arterials

4 N Short to A L LShort-term

May 3, 2011 RIDOT TMPs: An Overview 5

4 No Short to Long Any Low Low maintenance

activities

Page 6: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT Work Zone Impact Levels

W k ADT on Most

H il Anticipated D f

RIDOT Work Zone Impact Levels

Work Zone

Impact Le el

Work Anticipated to Include

Lane Cl ?

Anticipated Duration of

W k

Heavily Traveled Roadway

within Project Li it

Anticipated Level of Public

I t t

Degree of Adverse Impact to Road Users

Without Miti ti

PossibleE lLevel Closures? Work Limits Interest Mitigation Examples

1 Yes Very Long > 50,000 Very High Very HighReconstruction Projects on major freeways

2 Yes Moderate to Very Long > 15,000 Moderate to

High HighMajor bridge Projects on principal arterials

3 Yes Short toVery Long Any Low to

Moderate ModerateResurfacing Projects on minor arterials

4 N Short to A L LShort-term

May 3, 2011 RIDOT TMPs: An Overview 6

4 No Short to Long Any Low Low maintenance

activities

Page 7: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT Transportation Management StrategiesManagement Strategies

1. Traffic Control, Coordination, Contracting (TCC&C) StrategiesA. Traffic Control StrategiesB. Traffic Control DevicesC. Project Coordination and Contracting Strategies

2. Public Information (PI) StrategiesA. Public Awareness StrategiesB. Road User Information Strategies

3. Transportation Operations (TO) StrategiesA. Demand Management StrategiesB. Corridor/Network Management StrategiesB. Corridor/Network Management StrategiesC. Work Zone Safety Management StrategiesD. Traffic/Incident Management and Enforcement Strategies

4 Performance Monitoring (PM) StrategiesMay 3, 2011 RIDOT TMPs: An Overview 7

4. Performance Monitoring (PM) Strategies

Page 8: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT Transportation Management Strategies

PERFORMANCE MONITORING STRATEGIES

Management StrategiesPERFORMANCE MONITORING STRATEGIES

Team meetingsWindshield surveys

Public surveysSurveillance: Traffic counts

Surveillance: Traffic queues/delaysSurveillance: Traffic queues/delaysSurveillance: Travel timesSurveillance: Crash data

Assessment: MobilityAssessment: Safety

Road safety audits (construction)

May 3, 2011 RIDOT TMPs: An Overview 8

Road safety audits (construction)

Page 9: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

TMP Developmenton RIDOT Projectson RIDOT Projects

Preliminary Design

FinalFinal Design

May 3, 2011 RIDOT TMPs: An Overview 9

Page 10: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

TMP Developmenton RIDOT Projectson RIDOT Projects

• Designer obtains appropriate TMP Template from • Designer obtains appropriate TMP Template from RIDOT– One Template (Microsoft Excel format) for each Work Zone Impact LevelO e e p a e ( o a ) o eac p– Guidance notes provided in comment form on TMP Templates

• TMP updated iteratively throughout Design as TMP updated iteratively throughout Design as strategies are selected, TTC plans are developed, and Project changes occurj g– PI, TO, and PM strategies are explicitly identified in TMP– TCC&C strategies are not explicitly identified in TMP

May 3, 2011 RIDOT TMPs: An Overview 10

Page 11: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

TMP Developmenton RIDOT Projects

• Final Design Documentation

on RIDOT Projects• Final Design Documentation

– TMP submitted as part of each major Final Design b i i ( 30% 90% PS&E ADV & A d)submission (e.g., 30%, 90%, PS&E, ADV, & Award)

• One copy of TMP typically submitted to the following: Project Manager Construction Management Section – Project Manager - Construction Management Section

– Traffic Engineer - Transportation Management Center– FHWA Rhode Island Division Office (if Project oversight)

– Work zone safety and/or mobility-related analyses/reports should be provided as TMP attachments unless already i l d d i th Fi l D i t

May 3, 2011 RIDOT TMPs: An Overview 11

included in other Final Design reports

Page 12: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

TMP Developmenton RIDOT Projects

• RIDOT arranges for identification

on RIDOT Projects• RIDOT arranges for identification

of TMP Implementation Managersand TMP Approvalsand TMP Approvals

RIDOT Contractor

– For Significant Projects, the RIDOT and Designer indicate appropriate TMP Development Managers for the Project

RIDOT Consultant

May 3, 2011 RIDOT TMPs: An Overview 12

RIDOT Consultant

Page 13: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT TMP TemplatesRIDOT TMP Templates

Level 1 & 2 Level 3 Level 4Level 1 & 2 Level 3 Level 4(16 pages) (3 pages) (2 pages)(16 pages) (3 pages) (2 pages)

May 3, 2011 RIDOT TMPs: An Overview 13

(16 pages) (3 pages) (2 pages)(16 pages) (3 pages) (2 pages)

Page 14: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

(Browse Thru TMP Templates)(Browse Thru TMP Templates)

May 3, 2011 RIDOT TMPs: An Overview 14

Page 15: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

(Browse Thru Example TMP)(Browse Thru Example TMP)

May 3, 2011 RIDOT TMPs: An Overview 15

Page 16: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

RIDOT TMP Training/Resources

• Late 2008: Introductory session at local

g

Late 2008: Introductory session at local ITE Meeting

• Early 2009: RIDOT Training Sessions– Internal (Designers Managers Field Staff)Internal (Designers, Managers, Field Staff)– External (Consultants)

• Established E-Mail Account:[email protected]

May 3, 2011 RIDOT TMPs: An Overview 16

[email protected]

Page 17: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

Challenges / Next Steps

• Designers don’t always consider full

g p

Designers don t always consider full realm of potential strategies

I ffi i i i h i i TMP i• Inefficiencies with revising TMPs in construction

• Ideally TMPs will be incorporated into RIDOT’sincorporated into RIDOT s web-based Project Management Portal (PMP)

May 3, 2011 RIDOT TMPs: An Overview 17

Management Portal (PMP)

Page 18: RIDOT Transportation Management Plans: An Overview · B. Road User Information Strategies 3. Transportation Operations (TO) Strategies A. Demand Management Strategies B. Corridor/Network

Questions Welcome...

[email protected]

[email protected] 3, 2011 RIDOT TMPs: An Overview 18