    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    1

    Establishment of Fuel Farms and

    Operation & Maintenance of

    Hydrant Refueling System on

    Public Private Partnership (PPP)Basis at New Benazir Bhutto

    International Airport, Islamabad

    Request for Qualification (RFQ)

    April

    2011

  • 8/16/2019 Rfq Fuel Farm Pakistan

    2/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    2

    Table of Contents

    DEFINITIONS ............................................................................................................................................ 4 

    1.  INTRODUCTION ............................................................................................................................... 6 

    1.2 SALIENT FEATURES OF THE PROJECT.............................................................................................................. 7 1.3 HYDRANT REFUELING SYSTEM  ..................................................................................................................... 7 1.4 FUEL FARM  .......................................................................................................................................... 11 

    2.  RFQ DOCUMENTATION PACKAGE .................................................................................................. 13 

    3.  EVALUATION CRITERIA .................................................................................................................. 14 

    3.1  RELEVANT EXPERIENCE AND PAST PERFORMANCE (55 POINTS) ...................................................................... 15 

    3.2  FINANCIAL STANDING (25 POINTS) ...................................................................................................... 16 3.3  APPROACH TOWARDS THE PROJECT (20 POINTS) ...................................................................................... 17 

    APPENDIX-1 ........................................................................................................................................... 18 

    APPENDIX-2 ........................................................................................................................................... 19 

    APPENDIX-3 ........................................................................................................................................... 21 

    APPENDIX-4 ........................................................................................................................................... 22 

  • 8/16/2019 Rfq Fuel Farm Pakistan

    3/23

  • 8/16/2019 Rfq Fuel Farm Pakistan

    4/23

  • 8/16/2019 Rfq Fuel Farm Pakistan

    5/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    5

    maintenance of ‘Fuel Farms and Operation and Maintenance of

    Hydrant Refueling System’ at BBIA

    Request for Proposal

    or RFP

    The tender documents to be issued to the Pre-Qualified

    Applicants.

  • 8/16/2019 Rfq Fuel Farm Pakistan

    6/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    6

    1.  Introduction 

    Islamabad is the capital of Pakistan and the tenth largest city in the country. The

    population of the city has increased from 100,000 in 1951 to 1.21 million in 2009. The

    Rawalpindi/Islamabad metropolitan area is the third largest in Pakistan with populationof over 4.5 million. The twin cities of Islamabad/Rawalpindi serve as commercial hub for

    the northern belt of Pakistan.

    Islamabad/ Rawalpindi region is currently being served by Benazir Bhutto International

    Airport, which is the third largest airport in country in terms of passenger traffic. Due to

    increase in number of passengers over the years, the existing Islamabad airport has not

    able to cope with this growth. Therefore, Government of Pakistan decided to construct

    a new airport outside Islamabad to address this issue. The New Benazir Bhutto

    International Airport is being developed by Pakistan Civil Aviation Authority (CAA. The

    new airport is located near Fateh Jang some 25 kilometers from Islamabad and 30

    kilometers from the existing airport. The airport will be connected through the network

    of motorway and Kashmir highway (the main express way of the city) is being extended

    to the airport. The airport is expected to handle 6.5 million passengers with

    approximately 100,000 metric tons of cargo annually which will gradually grow to 25

    million passengers and 300,000 metric ton cargo, respectively.

    Around 2000 acres of the site are to be utilized for aviation related facilities and 1,200

    acres shall be reserved for future commercial development. The new airport has been

    planned to include all kind of facilities associated with an international airport such as

    passenger and cargo terminal buildings, duty free shop, runway systems, taxiways,

    aprons, Airfield Lighting System, Air Traffic Control tower, etc. The Terminal Building

    shall have a modular design facilitating future expansions with ease.

    1.1 Pakistan Civil Aviation Authority

    Pakistan Civil Aviation Authority is a Public sector autonomous body working under the

    Federal Government of Pakistan through the Ministry of Defence. It was established on7th December, 1982 as an autonomous body. Prior to its creation, a Civil Aviation

    Department in the Ministry of Defence used to manage the civil aviation related

    activities. All kinds of Civil Aviation related activities are performed by CAA including the

    regulatory, air traffic services, airport management, infrastructure and commercial

    development at the airports, etc.

  • 8/16/2019 Rfq Fuel Farm Pakistan

    7/23

  • 8/16/2019 Rfq Fuel Farm Pakistan

    8/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    8

    The HRS shall operate on the following Design Parameters:-

    1.  Type of fuel JetA-1 (Kerosene)

    ASTMD 1655 (latest edition)

    2.  Bulk Modulus 200,000 psi

    3.  Kinematics viscosity 2.5 cs @ 00C

    4.  Specific gravity 0.79

    5.  Vapour pressure 0.5 ft. of JetA-1

    6.  Temperature range -50C to 500C

    7.  Flash point 38-400C

    Fuel System Description

    1.  Type of system valves to allow for

    maintenance

    Dual loop system with isolation

    2.  Fuel Farm Capacity 21,770MT (~27,910M

    3) (based on 10

    days storage)

    3.  Avg. daily consumption 2,177 tonnes (2,791 M

    3) per day

    4. 

    Fuel facility coverage To cover aircraft fuel demand uptoyear 2030 (in phases)

    5.  Aircraft stands to be served (Including

    future expansion)

    As per category C,D,E and F

    C (26 nos.), D (24 nos.) E (23 nos)

    and F (4 nos.) according to ICAO

    6.  Total aircraft to be served by HRS 33 nos. (in this Phase)

    44 nos. (future)

    77 nos. total

    7.  Peak flow ~3,460 USGPM (785 m

    3/hr) with

    2.5 m/s velocity

    ~3,813 USGPM (866 m3

    /hr) with

    2.75 m/s velocity8.

      Flow per hydrant pit ~600 USGPM (~2,250 litre/min)

    9.  Velocity in main pipe (for main line pipe) 2.5 to 2.75 m/s

    10.  Velocity in branch pipe 1.5 to 2 m/s

    11.  Simultaneous refueling 2 nos. Code D to F (i.e 4 no of

  • 8/16/2019 Rfq Fuel Farm Pakistan

    9/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    9

    aircraft hydrants) to be refueled at a

    velocity of 2.5 m/s at a time.

    12.  Total Aircraft movement per day 195 Aircraft movement

    13.  Maximum departures per day 109

    14.  System operating pressure 12 bar

    15.  Pressure range at hydrant outlet 6 to 8 bar

    16.  Head required at aircraft wing ~ 50 psi

    17.  Operational pumps & Characteristics

    (not in contact)

    To be designed & developed by

    Aviation Fuel Agency to provide

    required simultaneous flow & head

    at aircraft wing

    18.  Fuel farm facility (Not in Contract) To be designed & developed by the

    Aviation Fuel Agency

    19.  Diameter of main pipe ~ 350mm

    20.  Diameter of branch & riser pipe ~ 150mm

    21.  Cathodic protection To be provided by impressed

    current system using cathodic

    protection rectifiers

    Above quantity includes following aircraft:-

    All material and equipment supplied and installed shall be designed, manufactured and

    tested to meet the following ambient conditions unless specially stated otherwise for

    any material / equipment.

    Aircraft Standard

    Category Code

    Aircraft Types No.of Hydrant Pits per

    Stand

    C B-737,A-300,A-320,MD90-30ER,

    B-777-300, A330

    One (star board side)

    D B-747, A-340 Two

    E B-747-400ER Two

    F A-380 Two

  • 8/16/2019 Rfq Fuel Farm Pakistan

    10/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    10

    Maximum ambient temperature 500C

    Minimum ambient temperature -50C

    Maximum humidity 90%

    1. 

    Velocity in branch pipe 1.5 to 2 m/s2.  Simultaneous refueling 2 nos. Code D to F (i.e 4 no

    of aircraft hydrants) to be

    refueled at a velocity of 2.5 m/s

    at a time.

    3 nos. Code D to F (from 6

    hydrants) @ velocity 2.75 m/s

    3.  Total Aircraft movement per day: 195 Aircraft movement

    4.  Maximum departures per day: 109

    5. 

    System operating pressure: 12 bar6.  Pressure range at hydrant outlet: 6 to 8 bar

    7.  Head required at aircraft wing ~ 50 psi

    8.  Operational pumps & To be designed & developed

    Characteristics (not in contact) by Aviation Fuel Agency to

    provide required simultaneous

    flow & head at aircraft wing

    9.  Fuel farm facility To be designed & developed

    (Not in Contract) by the Aviation Fuel Agency

    10. 

    Dia of main pipe ~ 350mm11. Dia of branch & riser pipe ~ 150mm

    12. Cathodic protection To be provided by impressed

    current system using

    cathodic protection rectifiers

    All material and equipment supplied and installed shall be designed, manufactured and

    tested to meet the following ambient conditions unless specially stated otherwise for

    any material / equipment.

    Maximum ambient temperature 500

    CMinimum ambient temperature -5

    0C

    Maximum humidity 90%

  • 8/16/2019 Rfq Fuel Farm Pakistan

    11/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    11

    1.4 Fuel Farm

    Most airports also have their own dedicated oil depots usually called "fuel farms" where

    aviation fuel (Jet A or 100LL) is stored prior to being discharged into aircraft fuel tanks.

    Fuel is transported from the depot to the aircraft either by road tanker or via a hydrantsystem.

    The fuel farm to be established at the New BBIA is expected to complement and support

    HRS. The daily intake is expected to be around 700 MT which will gradually increase.

    Initial storage capacity is expected to be at 10,000MT comprising of 4 to 6 tanks for 10

    days storage. The fuel farm is expected to supply fuel through the HRS at 12 Bar

    Pressure.

    Tank Packages must be designed to meet the needs of the majority of fueling facilities inthe shortest time possible. The following types of fuel tanks would be acceptable:

    1.  Horizontal tanks – above ground;

    2.  Horizontal tanks – partially buried;

    3.  Horizontal Tanks – below ground;

    4.  Vertical tanks above ground;

    The detail specifications will be provided at the time of RFP. However, the horizontal

    tanks must have the following fittings:

    Horizontal Tanks Vertical Tanks

    Person access  Internal drainage

    Sampling hatch  Self supporting roof

    Pressure/vacuum and emergency venting  A staircase to provide access to the

    top

    Floating suction  Foam inlets

    Earth boss  Pressure/vacuum and emergency

    ventingLevel control system  Tank drain pipe

    Pressure/vacuum breaker  Level control system

    Minimum two manholes  Two manholes

    Fuel level control system

    Concrete encasement allowance

  • 8/16/2019 Rfq Fuel Farm Pakistan

    12/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    12

    To maintain supply capability, fuel quality and safety compliance, fuel farm facilities

    shall conform to all applicable regulations and standards of the CAA. Furthermore, the

    fuel farm is expected to comply with the international best practices and is expected to

    include the following:

      Automatic tank gauging performing inventory control (leak monitoring and

    product reconciliation) must be installed. The tank gauging system should be

    capable of measuring product level, density (desirable), temperature, etc.

      Automatic shut down of pumping system at different tier including shut down

    prior to the tank contents reaching the overfill level, shut down at the normal fill

    level (design rated usable capacity); and at the low level when the floating off-

    take head contacts the low stop.

      Multipurpose pumps capable of producing adequate flow rate, as well as for

    controlling pressure, to control valves, etc.  Backup power generation facility

      Cathodic protection system design shall protect tank portions and piping in

    contact with soil, minimize stray current effects as well as effects on operations

    and maintenance, etc;

      Civil infrastructure to allow operations staff to be house at the fuel farm

  • 8/16/2019 Rfq Fuel Farm Pakistan

    13/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    13

    2.  RFQ Documentation Package

    The following document and information shall be provided by each Applicant to be

    considered for prequalification for the Project:

    1. 

    Name, contact details and profile of Applicant/Consortium (Appendix 2)

    2. 

    Legal status of the Applicant/ Consortium, organization structure and nature of

    business operations (Appendix 2). The Applicant/ Consortium should attach the

    certificate of incorporation. In addition, if the Applicant is a Consortium a Joint

    Venture Agreement (JVA) or a Memorandum of Understanding (MoU) should also

    be included.

    3.  Financial standing of the Applicant/Consortium supported by last 3 years Audited

    Annual Reports(Appendix 3)

    4. 

    Business plan of the Applicant/Consortium for undertaking the project along with

    credentials of technical experts who will be a part of the core team (Appendix 4)

    5.  A certificate / affidavit that Consortium is not blacklisted under the law by any

    Government or Autonomous Body

    6.  Any other information in support of capability and experience of the

    Applicant/Consortium.

    IPDF reserves the right to accept or reject any or all of the RFQs.

  • 8/16/2019 Rfq Fuel Farm Pakistan

    14/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    14

    3.  Evaluation Criteria

    The applicant securing a minimum of 70 marks  will qualify for issuance of RFP. The

    evaluation factors and marks are given hereunder:  

    Description Points Allocated Total Point

    3.1. 

    Relevant Experience and Past Performance 5

    a) 

    Applicant/Consortium experience in refueling system 10

    b) 

    Experience in all types of refueling systems inclusive

    of Hydrant Refueling System in Aviation Industry

    20

    c) 

    Specific Experience in Fuel Farm Development,

    operations and maintenance

    10

    d) 

    Experience in O&M of Hydrant Refueling Systems 15

    3.2. 

    Financial Standing 2

    a) 

    Net Worth 15

    b) 

    Annual Turnover 10

    3.3.  Approach towards the Project 2

    a) 

    Business plan 10

    b) 

    Details of technical abilities of consortium 10

    Total Marks 10

  • 8/16/2019 Rfq Fuel Farm Pakistan

    15/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    15

    3.1  Relevant Experience and Past Performance (55 points)

    a) 

    Applicant/Consortium experience in refueling system 10 points

    This would assess the operational history of the Applicant or LCM in case the

    Applicant is a Consortium. The points would be allocated as outlined in the table

    below:

    Years of operation Points Allocation

    Greater or equal to 10 years 10

    Greater than or equal to 7 years but less than 10 years 7

    Greater than or equal to 5 years but less than 7 years 5

    Less than 5 years 0

    b)  Experience in all types of refueling systems inclusive

    of Hydrant Refueling System in Aviation Industry 20 points

    This would assess the experience of LCM or OCM in Aviation Industry. The point

    allocation would be as outlined in the table below:

    Relevant Experience Points Allocation

    Greater or equal to 5 years 20

    Greater or equal to 4 years but less than 5 years 15

    Greater or equal to 3 years but less than 4 years 10

    Greater or equal to 2 years but less than 3 years 5

    Less than 2 years 0

    c)  Specific Experience in Fuel Farm Development,

    Operations and Maintenance 10 points

    This would assess the experience of LCM or OCM in establishment and operation

    Fuel Farm. The point allocation would be as outlined in the table below:

    Relevant Experience Points Allocation

    Greater or equal to 5 years 10

    Greater or equal to 4 years but less than 5 years 8Greater or equal to 3 years but less than 4 years 6

    Greater or equal to 2 years but less than 3 years 4

    Less than 2 years 0

  • 8/16/2019 Rfq Fuel Farm Pakistan

    16/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    16

    d) 

    Experience in O&M of Hydrant Refueling Systems 15 points

    This would assess the experience of LCM or OCM in development, operation and

    maintenance (O&M) of Hydrant Refueling System. The point allocation would be

    as outlined in the table below:

    Experience in Hydrant Refueling System Points Allocation

    Greater or equal to 5 years 15

    Greater or equal to 4 years but less than 5 years 10

    Greater or equal to 3 years but less than 4 years 5

    Less than 3 years 0

    3.2  Financial Standing (25 points)

    a) 

    Net worth 15 points

    This would assess the combined net worth of LCM and OCM. The point allocation

    would be as outlined in the table below:

    Net worth Points Allocation

    Greater or equal to PKR 700 million 15

    Greater or equal to 600 million but less than 700 million 11

    Greater or equal to 500 million but less than 600 million 7

    Greater or equal to 400 million but less than 500 million 3

    Less than 400 million 0

    b) 

    Annual Turnover 10 points

    This would assess the combined annual turnover of LCM and OCM. The point

    allocation would be as outlined in the table below:

    Net worth Points Allocation

    Greater or equal to PKR 500 million 10

    Greater or equal to 400 million but less than 500 million 8

    Greater or equal to 300 million but less than 400 million 6

    Greater or equal to 200 million but less than 300 million 4

    Less than 200 million 0

  • 8/16/2019 Rfq Fuel Farm Pakistan

    17/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    17

    3.3  Approach towards the project (20 points)

    a) 

    Business Plan 10 points

    Please refer to Appendix 4

    b) 

    Details of technical abilities of consortium 10 points

    Please refer to Appendix 4

  • 8/16/2019 Rfq Fuel Farm Pakistan

    18/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    18

    Appendix-1

    FORMAT FOR LETTER OF RFQ APPLICATION

    Date: ------------

    Chief Executive

    Infrastructure Project Development Facility

    House # 2, Street 59, F-7/4,

    Islamabad

    Dear Sir,

    Being duly authorized to represent and act on behalf of _________________

    (hereinafter referred to as "the Bidder"), and having reviewed and fully understood all

    of the qualification requirements and information provided, the undersigned hereby

    expresses its interest and apply for qualification for the [insert name of Project].

    We are enclosing our Request for Qualification (RFQ), in one Original and three Copies,

    with the details as per the requirements of the RFQ, for your evaluation.

    The undersigned hereby also declares that the statements made and the information

    provided in the RFQ is complete, true and correct in every detail.

    Yours faithfully,

    (Signature of Authorized Signatory)

    (Name, Title and Address of the Bidder)

    Bidder seal & stamp

  • 8/16/2019 Rfq Fuel Farm Pakistan

    19/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    19

    Appendix-2

    GENERAL INFORMATION ABOUT THE ORGANIZATION1, 2

     

    Particulars  Details a) Name of organization

    (indicate complete legal name of the

    organization)

    b) Operating name of the organization (if different from legal name) 

    c) Country of incorporation

    d) Ownership of the Organization

    Sole Proprietorship/

    Partnership/

    Private Limited Company/

    Public Unlisted/

    Public Listed Company/

    Other (please specify) 

    (strike out whichever is not applicable) 

    e) Date of establishment/ incorporation

    f) Brief description of the business

    g)Details of main business lines/ services/

    products offered

    h)Communication address along with

    telephone and fax numbers

    i) Website

     j) Status in the Project

    Single Bidder/

    Lead Consortium Member/

    Operating Consortium Member/

    Other Consortium Member

    (strike out whichever is not applicable)

    k)

    List of stakeholders / members who own

    10% or more stocks & their interest in the

    company

    l) List of current directors

    m) Key Contact Person(indicate their name, designation/ title

    and contact address along with

    telephone, fax and email address)

    n) Other key management personnel

    o) International affiliations, if any

    p) Professional membership(s), if any

  • 8/16/2019 Rfq Fuel Farm Pakistan

    20/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    20

    q) Tax registration number

    1  Individual firms/ consortia may, in addition to the above, attach their company

     profiles as an annexure to this form2  In case the consortium comprises of more than one firm, the above information

    shall be provided in respect of each of the firm. 

  • 8/16/2019 Rfq Fuel Farm Pakistan

    21/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    21

    Appendix-3

    FINANCIAL INFORMATION SUMMARY1,2,3

    Particulars Details

    Paid up Capital

    Net Worth

    Balance Sheet Totals

    Annual Turnover 

    Past three years 

    Year PKR.

    1  Based on latest audited financial statements, attach copies

    2  Attach audited financial statements for the last three years

    3In case the Consortium comprises of more than one firm, the above information

    shall be provided in respect of each of the firm. 

  • 8/16/2019 Rfq Fuel Farm Pakistan

    22/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    22

    Appendix-4

    Business Plan

    Particulars Details

    Overview of layout and operation of Fuel Farm 

    Managerial capability to operate and maintain the

    Hydrant Refueling System including the fuel farm

    Strategy to operate and maintain the hydrant refueling

    system 

    Proposed international affiliation, if any.

  • 8/16/2019 Rfq Fuel Farm Pakistan

    23/23

    Request For Qualification - Establishment of Fuel Farms and Operation and Maintenance of Hydrant

    Refueling System on Public Private Partnership (PPP) Basis

    Details of technical abilities/associated consultant

    The applicant shall provide Infrastructure details including available Tools and

    Plants (T&P) and machinery for the said projec.

    The Applicant must provide the details of professionals who will be a part of its

    core team. Please include CV’s /resume of the core team