review for final in isqs 7342
DESCRIPTION
Review for Final in ISQS 7342. Final will take place: Saturday, December 7, 2013, 10.30-1.00 p.m., this room – BA 021. Format. 7 5 multiple choice worth 50% 3 discussion problems worth 50% exam is closed notes/closed book Exam will be comprehensive - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/1.jpg)
Review for Final in ISQS 7342
Final will take place:
Wednesday, December 10, 2014, 7.30-10.00 a.m., this room – BA 025Early Exam for those who signed on will be Saturday, December 6, 2014, 7.30-10.00 a.m., this room – BA 025
![Page 2: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/2.jpg)
Format
75-100 multiple choice worth 75% 2-3 discussion problems worth
25% exam is closed notes/closed book Exam will be comprehensive
• 70% of the exam will cover material since Exam 2
• 30% of the exam will cover prior material
No talking during the EXAM, please
![Page 3: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/3.jpg)
Bring
Pencils/Eraser Calculator Orange Scantron sheet
![Page 4: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/4.jpg)
Emphasis will be upon:
Human Resource Management Risk Management Procurement Management Communications Management Goldratt Concepts Finishing Projects Fast
![Page 5: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/5.jpg)
Possible Discussion Questions
Name ten characteristics of a project
Successful project management entails what exactly (4 ‘measures’)
Name the stages of the project lifecycle• Show their sequence
Why is project management important
Name the four core knowledge areas
Name the five facilitating knowledge areas
![Page 6: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/6.jpg)
More discussion questions
What is the tenth knowledge area and what is its purpose
Name some things we do poorly in projects
What term do we use to describe an event at which a major deliverable is completed?
What device or construct is often used to initiate a project?
What steps are used to launch critical chain project management?
![Page 7: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/7.jpg)
Typical discussion problems
Construct an activity on node network chart from a table; Determine duration, ES, EF, LS, LF and mark the critical path
Perform earned value analysis: BCWP, BCWS, ACWP, CV, SV, EV, PV, AC, CI, SI
Perform crashing of networks What are the five phases that make up
the CMMI? Illustrate the tradeoff triangle Assuming that half the durations are
safety, redraw a project network showing all feeding and project buffers and their lengths
![Page 8: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/8.jpg)
Multiple choice
Risk, Procurement, HR, and Communications knowledge mangement
Chapters 12, 14 of Burns Process maturity slides Finishing projects fast slides Critical chain concepts
![Page 9: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/9.jpg)
Why has Project Management become so in-vogue?
Diversity of new products and product markets
Shorter life span of products Rapid technological changes
![Page 10: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/10.jpg)
What are the major reasons for project failure?
Inadequate conceptualization and definition• Specifically, inadequate requirements
Absence of a plan Unavailable resources when
needed Scope and hope creep Unresponsive contractors who
deliver their product late
![Page 11: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/11.jpg)
What are the five stages of the project lifecycle?
STAGE 1:Initiating
STAGE 2:Planning
STAGE 3:Executing
STAGE 5:Closing
STAGE 4:Monitoring-and-Controlling
![Page 12: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/12.jpg)
In which of these stages is a WBS started?
Initiating (Conceptualizing and Defining)• First 3 levels
{The WBS is usually finished in the Planning and Budgeting stage}
![Page 13: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/13.jpg)
What are the ten knowledge areas?
Scope management Time management Cost management Quality managementIntegration management
Risk management Procurement management Human resource management Communications management Stakeholder Management
![Page 14: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/14.jpg)
In which stage is scope management most important?
The first stage: Initiating (Conceptualization and Definition) because that is where scope is defined
![Page 15: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/15.jpg)
Activity Definition (Define Activities) is ___
a subproject a process a problem a plan
WHICH???
![Page 16: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/16.jpg)
Activity Definition (Define Activities) is part of what knowledge area?
Time management
![Page 17: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/17.jpg)
Project Scope Management Processes
Collect Requirements Define Scope Create WBS Verify Scope Control Scope
![Page 18: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/18.jpg)
Project Time Management Processes
Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule
![Page 19: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/19.jpg)
Project Cost Management Processes
Estimate Costs Determine Budget Control Costs
![Page 20: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/20.jpg)
Project Quality Management Processes
Plan Quality Perform Quality Assurance Perform Quality Control
![Page 21: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/21.jpg)
The main purpose of a project plan is to ____
acquire resources guide project execution. meet standards expectations. reduce risk.
![Page 22: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/22.jpg)
The most important output of project execution is
Not---change requests Not—the WBS Not—project plan Not—requirements doc
But—work products—the deliverables of the project
![Page 23: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/23.jpg)
The Principle…
That work tends to fill up the time allotted for it is known as…..
![Page 24: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/24.jpg)
Most core knowledge areas have a
Planning process
And a
Control process
![Page 25: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/25.jpg)
During the …
Conceptualization and definition stage, it is important that the project manager get
![Page 26: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/26.jpg)
What are the five steps of the Theory of Constraints (Goldratt)?
IDENTIFY the project constraint Decide how to EXPLOITE that
constraint SUBORDINATE everything to that
decision ELEVATE the system’s constraint Go back to step a
![Page 27: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/27.jpg)
NOT…
SUBORIDNATE that decision to everything else
![Page 28: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/28.jpg)
According to Goldratt…
Team players put too much ____ into their estimated durations
![Page 29: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/29.jpg)
As Goldratt sees it, ….
The ultimate constraint in projects is….
![Page 30: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/30.jpg)
Which of the following does Goldratt regard as a positive thing
Safety Multitasking Student syndrome Lose/lose contracting None of the above
![Page 31: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/31.jpg)
An activity has probabilistic completion times of 20, 50 and 80 for the optimistic, most likely and pessimistic durations. What is the average time
(duration) assuming a beta distribution?
30 40 50 60 70
![Page 32: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/32.jpg)
You should know
How to construct a NETWORK chart from a table
How to construct a Gantt chart from a table
How to perform NETWORK crashing
How to do EVAAll of the above
![Page 33: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/33.jpg)
A work package…
Has $100,000 budgeted for it Is 50% complete What is its BCWP = EV?? $30,000 $40,000 $50,000 $60,000
![Page 34: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/34.jpg)
A task with a $10,000 budget has a start date in the future
Its BCWS (planned value) is• $0• $5,000• $10,000• Can’t be determined
![Page 35: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/35.jpg)
A task with a $10,000 budget has a stop date in the past.
Its BCWS (planned value) is• $0• $5,000• $10,000• Can’t be determined
![Page 36: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/36.jpg)
A task with a $10,000 budget and a 6 day duration has just finished day 3
Its BCWS = PV is• $0• $5,000• $10,000• Can’t be determined
![Page 37: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/37.jpg)
A task has a budget of $20,000 and a scheduled duration of 5 days
What is its daily burn rate? $4,000 What is its PV rate? $4,000 If the project is 20% complete
what is its BCWP? $4,000
![Page 38: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/38.jpg)
A task has a budget of $20,000 and a scheduled duration of 5 days
What is its PV rate? $4,000 If the project is 20% complete
what is its BCWP? $4,000 If day three has just transpired,
what is the BCWS? $12,000 What is the task’s SV (schedule
variance)? -$8,000 Is the task ahead or behind
schedule???
![Page 39: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/39.jpg)
Questions about MS Project
Which key for subordination?• The Indent arrow
Which key for linking, for sequencing?• The linking tool
How to view project duration and cost on the project information dialog box?• Click on the Project tab and then the
Project Information Icon
![Page 40: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/40.jpg)
Questions about MS Project
How to see all of the cost and duration detail in the entry table in the ? view, including total PROJECT cost and duration
How to see all of the activity costs
![Page 41: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/41.jpg)
For MS Project to cost your project, it needs to know
Resource hourly costs• Specified in what view????
– The Reource sheet
Activity fixed costs• Specified on the Cost table
THIS IS ALL
![Page 42: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/42.jpg)
In MS Project, durations/costs of phases (summary tasks) …..
Containing one or more subordinate tasks can be specified only by MS Project
Is it a good idea to assign resources to summary tasks as well as to subordinate tasks?
No!!! Never!!
![Page 43: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/43.jpg)
Summary Tasks…..
Always appear in black or in blue?
Occur when….
Black, always
There are tasks subordinate to it
![Page 44: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/44.jpg)
Task info is entered in which view of MS Project, usually??
The Network View The Gantt view, using the Entry
Table The Resource Sheet The Tracking Gantt view
![Page 45: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/45.jpg)
When using the standard calendar, MS Project assumes
a. 8-hour work daysb. No work on Sat or Sunc. Two persons can do the work in
half o f the timed. All of the above
![Page 46: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/46.jpg)
Questions over CRITICAL CHAIN
Major conclusions, recommendations
Goldratt’s view of EVA What to Measure What to Focus on
![Page 47: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/47.jpg)
More Questions on CRITICAL CHAIN
To avoid non critical paths from becoming critical you should…
Critical chain is the sequence of tasks performed by key persons both on and off the critical path
![Page 48: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/48.jpg)
Measurements should
Induce the parts to always do what is good for the system as a whole
![Page 49: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/49.jpg)
Why does Goldratt not like BCWP, BCWS, ACWP?
Because they have no sensitivity to the critical path
![Page 50: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/50.jpg)
If you have a task on the critical path and …..
Your time to complete that task has arrived, then Goldratt recommends that you drop everything and just focus (150%) on that task until you get it done!! • No multitasking• No procrastination (student syndrome)
![Page 51: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/51.jpg)
Project Performance Measurement and Control
The first step is to…. SET A BASELINE…. The second step is to MEASURE PROGRESS AND
PERFORMANCE The third step is to COMPARE PLAN AGAINST
PERFORMANCE
![Page 52: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/52.jpg)
Project Performance Measurement and Control
The last step is TAKE APPROPRIATE ACTION
Project schedule status is usually communicated with a
Tracking Gantt Chart showing a progress line
![Page 53: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/53.jpg)
Notes on shortening project durations
This should be done in the Planning and Budgeting stage
Crashing• Reducing the duration of tasks on the
critical path Fast-tracking
• Starting tasks sooner Adding resources?? Checking for parallelism opportunities in
the schedule• Pull as much work off of the critical path as
you can
![Page 54: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/54.jpg)
More Tips on shortening project durations
REUSE, REUSE, REUSE Do it right the first time Avoid enhancements to
requirements Instead, consider scrubbing
requirements (reducing scope) If its early in the project, consider
• outsourcing some project work• Adding resources in-house• Using overtime
![Page 55: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/55.jpg)
More techniques for shortening projects
Scrub the requirements, as we mentioned• Remove from the requirements those items
that add little or no value, but nevertheless are significant contributors to cost
• Remember the Pareto principle—80% of the value comes from 20% of the functionality
Do everything right the first time (AGAIN)
REMOVE SAFETY--GOLDRATT
![Page 56: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/56.jpg)
Crashing Problem (Burns, Ch. 8)
For the network diagram below, find the best crashing strategy considering that you have $1300 in the crashing budget and the following:
Task Crash cost/da
y
Minimum duration
Duration
A $200 8 10B $300 10 12C $300 8 10D $400 10 13E $400 6 10F $350 5 7G $100 6 10Note from above that A can only be crashed
2 days, from 10 down to 8 days, etc.
10 22 22 35 0 0 10 22 22 35 0 10 35 42 42 52 0 0 0 0 10 35 42 42 52 10 20 20 30 5 5 15 25 25 35
A/10 F/7 G/10
B/12 D/13
C/10 E/10
PATHS LENGTH (Days)
CRASH G 6 Days
CRASH A 2 Days
CRASH B 1 Day
ABDFG 52 46 44 43 ABDG 45 39 37 36 ACEFG 47 41 39 39 ACEG 40 34 32 32 BUDGET SPENT 0 $600 $400 $300 BUDGET LEFT $1,300 $700 $300 $0
![Page 57: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/57.jpg)
Network diagrams, drawn by commercial software
Do they use • Activity-on-Node, or • Activity-on-Arrow representations?
![Page 58: Review for Final in ISQS 7342](https://reader035.vdocuments.mx/reader035/viewer/2022062423/56814d94550346895dbaebdb/html5/thumbnails/58.jpg)
That’s all folks
{I enjoyed having you as a class—one of the best classes I’ve had)