    9 Replies Latest reply: Jan 5, 2013 7:47 AM by Mayank Malpani

    Share 0Like

    1809 Views

    Average User Rating

    (0 ratings)

    Regarding Reversal of PGI in wrong date

    This question is Assumed Answered.

    Hi

    I have a problem regarding PGI done on April 17, 2009 and the user after realising that the Goods

    Issued were wrong so he reversed the PGI using VL09 Tcode. But while reversing user did it on03.05.2009.

    Can we reverse this posting as on April 17 2009? If yes, than please reply coz i want the stock to be

    available on April 17 2009 which is lying on 03 May 2009 after the reversal of PGI.

    Thanks

    Anup Deshmukh May 5, 2009 8:23 AM

    Helpful Answerby ramanathan raja

    Re: Regarding Reversal of PGI in wrong date

    Hi,

    Yes you can reverse the goods issue.

    by VL09, the posting is reversed automatically.

    Thanks,

    Raja

    Like (0)

    Raja Singh Chhabeda May 5, 2009 8:34 AM (in response to Anup Deshmukh)

    Re: Regarding Reversal of PGI in wrong date

    well the user has already reversed it through Vl09 but he forgot to change the Define date in

    Vl09 and the system took the date 03 May 2009.

    Now i want the stock to be available as on April 17 2009 which aftr reversing is still lying on 03

    May 2009.

    how am i going to do it..plz check the dates

    plz help

    Anup Deshmukh May 5, 2009 8:43 AM (in response to Raja Singh Chhabeda)

    https://scn.sap.com/people/anup.deshmukh4https://scn.sap.com/people/rajasingh.chhabeda2https://scn.sap.com/welcomehttps://scn.sap.com/message/7477570#7477570https://scn.sap.com/people/anup.deshmukh4https://scn.sap.com/actionshttps://www.sapstore.com/?url_id=banner-US-2015-SCN-HeadLinkhttps://scn.sap.com/people/rajasingh.chhabeda2https://scn.sap.com/community/feeds/messages?thread=1329414https://scn.sap.com/people/anup.deshmukh4https://scn.sap.com/community/developer-centerhttps://scn.sap.com/community/uachttp://-/?-https://scn.sap.com/people/anup.deshmukh4https://scn.sap.com/thread/login.jspahttps://scn.sap.com/message/7477660#7477660https://scn.sap.com/people/anup.deshmukh4https://scn.sap.com/community/getting-startedhttp://scn.sap.com/login.jspahttps://scn.sap.com/community/newslettershttps://scn.sap.com/message/7477570#7477570https://scn.sap.com/people/anup.deshmukh4https://scn.sap.com/message/7477771#7477771https://scn.sap.com/people/rajasingh.chhabeda2https://scn.sap.com/communicationshttps://scn.sap.com/community/downloadshttps://scn.sap.com/contenthttps://scn.sap.com/activityhttps://scn.sap.com/welcome
  • 7/24/2019 Reversal of PGI in Wrong Date

    2/3

    Like (0)

    Re: Regarding Reversal of PGI in wrong date

    Hi,

    As the PGI is reve rsed in 3rd so stock wil l be availab le o nly o n 3rd . I don t think you can get it

    back on 17h April.

    Thanks,

    Raja

    Like (0)

    Raja Singh Chhabeda May 5, 2009 8:48 AM (in response to Anup Deshmukh)

    Re: Regarding Reversal of PGI in wrong date

    Once reversed a PGI, you cannot change the posting date. So in your case, since the end

    user has already reversed, do PGI once again with current period. Once the goods are

    posted with current period, you have to open previous period in MMPIand now while

    reversing define the date as 17-04-09.

    Not sure on inventory implications whi ch you have to check with FI colleag ues. Better test in

    development client and if found okay, go ahead in production.

    thanks

    G. Lakshmipathi

    Like (0)

    G Lakshmipathi May 5, 2009 8:48 AM (in response to Anup Deshmukh)

    Re: Regarding Reversal of PGI in wrong date

    Yes As Mr Lakshmipathi said once again you can do goods issue for that delivery on that 17

    th april provided your MM period is open for that VL09 reversed deliveryIn the delivery doc you have to put the actual GI date as 17 th april or otherwise it will take as

    5 th may that is today

    If MM period is not open you can open the same in MMPI

    SAP doesnt recommend this practise

    Ususally SAP allows a month grace time to do post into previous period

    So in the month of may posting in april is not a problem (like your scenario) no need of

    MMPI

    suppose the delive ry is in 26 th feb 09 and reversed in may 2 that is 2009 and then once

    again you wan t to do PGI or process the delivery in the feb 26 th itself then you need MMPI

    Regards

    Raja

    Helpful Answer

    ramanathan raja May 5, 2009 9:06 AM (in response to Anup Deshmukh)

    Re: Regarding Reversal of PGI in wrong date

    Dear Lakshmipathi,

    I'm currently also in the same situation as subjected. As you mentioned, "do PGI once

    again with current period" & "now while reversing define the date as" I've done but

    system showing an error like below.

    Error: Cancellation date 2012.03.31 is before the goods issue date 2012.04.03

    As this is an error, I can't p roceed forward. Plea se ad vice w hat can I do.

    Like (0)

    Zaiedul HoqueApr 3, 2012 8:57 AM (in response to G Lakshmipathi)

    https://scn.sap.com/people/rajasingh.chhabeda2https://scn.sap.com/message/7477956#7477956https://scn.sap.com/message/7477821#7477821https://scn.sap.com/message/7477820#7477820https://scn.sap.com/message/13156391#13156391https://scn.sap.com/people/ramanathan.raja2https://twitter.com/intent/tweet?hashtags=scn&original_referer=https%3A%2F%2Fscn.sap.com%2Fthread%2F1329414&text=Regarding%20Reversal%20of%20PGI%20in%20wrong%20date&tw_p=tweetbutton&url=https%3A%2F%2Fscn.sap.com%2Fthread%2F1329414&via=SAPCommNethttp://twitter.com/search?q=https%3A%2F%2Fscn.sap.com%2Fthread%2F1329414https://scn.sap.com/people/zaiedhttps://scn.sap.com/people/zaiedhttps://scn.sap.com/people/lakshmipathi.ganesanhttps://scn.sap.com/people/rajasingh.chhabeda2https://scn.sap.com/people/ramanathan.raja2https://scn.sap.com/people/lakshmipathi.ganesan
  • 7/24/2019 Reversal of PGI in Wrong Date

    3/3

    Follow SCNSite Index Contact Us SAP Help Portal

    Privacy T erms of Use Legal Disclosur e Copyr ight

    0 Tweet 0Share 0Like

    Re: Regarding Reversal of PGI in wrong date

    Anup Deshmukh ,

    Yes, you can do reversal of PGI on 17th April it is possible.

    Execute VL09

    Enter Shipping Point and Enter outbound delivery no.

    Click Execute

    Choose the line item Click "Reverse" tab provided above

    Click on "Define date" enter the date and click tick mark and then click reverse.

    Regards

    Sathya

    Like (0)

    Sath

    Pava

    Sathya Pavan Yedavalli venkata May 5, 2009 8:49 AM (in response to Anup Deshmukh)

    Re: Regarding Reversal of PGI in wrong date

    Thanks for the replies problem is solved...!

    Like (0)

    Anup Deshmukh May 12, 2009 9:18 AM (in response to Anup Deshmukh)

    Like (0)

    Re: Regarding Reversal of PGI in wrong date

    Hi anup

    i am facing same problem can you please suggest how could you solved this issue

    Like (0)

    Mayank Malpani Jan 5, 2013 7:47 AM (in response to Anup Deshmukh)

    https://scn.sap.com/message/7516740#7516740https://scn.sap.com/people/sathyapavan.yedavallivenkatahttp://help.sap.com/http://www.sap.com/corporate-en/our-company/legal/copyright/index.epxhttp://bit.ly/SCNFBhttps://scn.sap.com/message/7477824#7477824https://scn.sap.com/people/mayanksapsdhttps://scn.sap.com/people/anup.deshmukh4http://bit.ly/SCNyouThttps://scn.sap.com/message/13757760#13757760https://scn.sap.com/people/mayanksapsdhttp://-/?-http://bit.ly/SCNTwRhttps://scn.sap.com/docs/DOC-18476http://www.sap.com/corporate-en/our-company/legal/impressum.epxhttp://www.sdn.sap.com/irj/scn/policyhttps://scn.sap.com/people/sathyapavan.yedavallivenkatahttps://scn.sap.com/docs/DOC-19361http://-/?-https://scn.sap.com/people/anup.deshmukh4http://www.sdn.sap.com/irj/scn/policy?view=PPhttp://spr.ly/SCNgoogleplus