revay -case study on eot claim

89
Case Study: Claim for Extension of Time and Additional Compensation Newhealth Hospital Redevelopment Presented in San Antonio, Texas

Upload: bahari

Post on 07-Dec-2015

25 views

Category:

Documents


2 download

DESCRIPTION

Schedule Analysis

TRANSCRIPT

Page 1: Revay -Case Study on Eot Claim

Case Study: Claim for Extension of

Time and Additional Compensation

Newhealth Hospital Redevelopment

Presented in San Antonio, Texas

Page 2: Revay -Case Study on Eot Claim

Agenda

I. Project Overview

II. Problems Encountered by the Contractor

III. How to Demonstrate Entitlement

IV. Workshop – Review of the Contractor’s Optimistic Claim

V. Delay Analysis

VI. Evaluation of Damages

VII. Problems/Solutions re. Disruption Claims

Page 3: Revay -Case Study on Eot Claim

I. PROJECT OVERVIEW

Page 4: Revay -Case Study on Eot Claim

Project Description

• Construction of the Newhealth Hospital redevelopment.

• Project consisted of interior finishes and fit-ups for the new

four-level addition to the hospital and renovations to the

existing structure.

Page 5: Revay -Case Study on Eot Claim

Project Layout

Page 6: Revay -Case Study on Eot Claim

Contract Dates

• On March 1, 2006, the Service and Supply Department of

Newhealth (“SSDN”) awarded a contract to Supreme

Contracting inc. (“Supreme”).

• This was a design-bid-build (fixed price) contract.

• Planned construction was to be executed from April 1, 2006 to

December 30, 2006.

Page 7: Revay -Case Study on Eot Claim

Delay Overview

9 months

Planned

Apr. 1, 2006 Dec. 30, 2006

Apr. 1, 2006 Jun. 15, 2007

Actual

14.5 months

ExtendedDuration

5.5 months

Jun. 15, 2007

Page 8: Revay -Case Study on Eot Claim

II. PROBLEMS ENCOUNTERED BY

THE CONTRACTOR

Page 9: Revay -Case Study on Eot Claim

Problems Encountered by the Contractor

• Level 3

– Unanticipated Interferences in the Ceiling on Level 3

– Incorrect Slab Openings for Ductwork Systems

• Level 1

– Unanticipated Interferences in the Ceiling on Level 1

– Excessive Modifications to Patient Service Units (PSU)

– Late Drawings of Device Location and Elevation

– Excessive Modifications to Door Frame and Layout

Page 10: Revay -Case Study on Eot Claim

Unanticipated

Interferences in the

Ceiling on Level 3

• Mechanical and electrical

systems located in the ceilings

of Level 3 had excessive

interference issues.

• The contractor discovered that

there was insufficient space to

accommodate the specified

mechanical and electrical

equipment.

• Several mechanical and

electrical systems, including the

ventilation, required significant

design modifications.

Page 11: Revay -Case Study on Eot Claim

Unanticipated Interferences

in the Ceiling on Level 3 (cont’d)

ITEMS TO BE INCLUDED

- Seismic hangers

- Lighting fixtures

- Spacings

- Cable tray

- Controls

- Vav box

- Medical equipment

Page 12: Revay -Case Study on Eot Claim

Installation Impossibility

• 758 mm of materials into a 650 mm space

• Someone did not CAD it, let’s see what the

contract says

• Whose pre-planning?

• Delayed for circumstances beyond the

contractor’s control

Page 13: Revay -Case Study on Eot Claim

Incorrect Slab

Openings for

Ductwork Systems

• Existing openings in the

concrete slabs did not have

the correct dimensions to

accommodate ductwork

systems as designed.

• No timely design was

provided by the design

professionals, so the

subcontractor proposed a

solution.

Page 14: Revay -Case Study on Eot Claim

Unanticipated

Interferences in the

Ceiling on Level 1

• Mechanical and electrical

systems located in the

ceilings of Level 1 had

excessive interference

issues.

• The contractor discovered

that there was insufficient

space to accommodate the

specified mechanical and

electrical equipment.

• Several mechanical and

electrical systems,

including the ventilation,

required significant design

modifications.

Page 15: Revay -Case Study on Eot Claim

Excessive Modifications

to Patient Service Units

(PSU)

• Owner requested

modifications related to

the medical gas located in

the PSUs

• As seen, this request

introduced changes to

many of the rooms located

on Level 1

Page 16: Revay -Case Study on Eot Claim

Distribution of Reasons for CCOs (QTY)

Incomplete Design 82%

User Requests13%

Site Conditions1%

Others4%

REASONS QTY % OF CCOS

Incomplete Design 450 82

User requests 74 13

Others 20 4

Site conditions 8 1

Page 17: Revay -Case Study on Eot Claim
Page 18: Revay -Case Study on Eot Claim

III. HOW TO DEMONSTRATE

ENTITLEMENT

Presented by: Phil Walters

Page 19: Revay -Case Study on Eot Claim

Entitlement Issues

• Does the contract permit the claim?

• Was proper notice provided?

• Reasonable efforts to mitigate?

• Was there a reservation for cumulative impact?

• Were the CCO’s agreed to?

• Were the delay events on the critical path?

• Were there concurrent activities (contractor vs owner)?

• Was there apportionment of liability?

• Is there a disruption claim without a delay?

• Is the quantification credible?

Page 20: Revay -Case Study on Eot Claim

IV. WORKSHOP – REVIEW OF THE

CONTRACTOR’S OPTIMISTIC CLAIM

Page 21: Revay -Case Study on Eot Claim

V. DELAY ANALYSIS

Presented by: John Owens

Page 22: Revay -Case Study on Eot Claim

Examples of Different

Delay Analysis Methods

• As-Planned vs As-Built

• Window or Snap Shot Analysis

• Impacted As-Planned

• Collapsed As-Built

• Time Impact Analysis

Page 23: Revay -Case Study on Eot Claim

Level 1 – Primary Problems

Page 24: Revay -Case Study on Eot Claim

Level 1 – Rough in Above Ceiling

DELAYS TO CONTRACTOR AND ITS

SUBCONTRACTOR’S ACTIVITIES RESULTING

FROM ABOVE CEILING COORDINATION

PROBLEMS

Page 25: Revay -Case Study on Eot Claim

Level 1 - Partitions

DELAYS TO CONTRACTOR AND ITS

SUBCONTRACTOR’S ACTIVITIES RESULTING FROM

ABOVE CEILING COORDINATION PROBLEMS

Page 26: Revay -Case Study on Eot Claim

Level 1 Delays

DELAYS TO CONTRACTOR AND ITS

SUBCONTRACTOR’S ACTIVITIES RESULTING FROM

ABOVE CEILING COORDINATION PROBLEMS

CLAIM 1

COMPLETION DATE

JUNE 10, 2008

DELAYS TO CONTRACTOR AND ITS

SUBCONTRACTOR’S ACTIVITIES RESULTING FROM

ABOVE CEILING COORDINATION PROBLEMS

EFFECT OF CEILING COORDINATION

PROBLEMS ON STEEL STUD INSTALLATION

CONTRACTUAL INITIAL

COMPLETION DATE

DEC 1, 2007

Page 27: Revay -Case Study on Eot Claim
Page 28: Revay -Case Study on Eot Claim
Page 29: Revay -Case Study on Eot Claim

VI. EVALUATION OF DAMAGES

Presented by: Steve Revay

Page 30: Revay -Case Study on Eot Claim

Contractor’s Evaluation of Damages

1. Extended Field Overhead…………………………………... $ 124,740

2. Extended Equipment………………………………………….. 160,000

3. Delayed Release of Holdback….…………………………… 42,000

4. Inclement Weather……………………………………………. 45,000

5. Overtime Premiums …………………………………………. 23,000

6. Productivity Loss …………………………………………….. 28,000,000

7. Material Handling …………………………………………….. 150,000

8. Safety …………………………………………………………. 75,000

9. Disputed Extras ………………………………………………. 457,000

10. Labour and Material Escalation …………………………….. 300,000

11. Loss of Revenue ……………………………………………… 135,692

SUBTOTAL : $ 29,512,432

12. Head Office Overhead & Profit (10%) ………………………. 2,951,243

SUBTOTAL : $ 32,463,675

13. Claim Preparation (3.5%) ………………………………………. 1,136,228

TOTAL : $ 33,599,903

Page 31: Revay -Case Study on Eot Claim

1. Extended Field Overhead

• Superintendent. ……………………………… $ 8,250

• Secretary/timekeeper (labour burden incl)…… 3,000

• Telephone (service & long distance) …………… 450

• Fax (rental, paper, long distance)……………… 250

• Couriers ………………………………………….. 250

• Sundry Trucking …………………………………. 400

• Temporary Power ……………………………….. 400

• Temporary Toilets ………………………………. 450

• Office Building & Supplies ……………………... 950

• Site Truck & Fuel ……………………………. $ 950

• Consumables ………………………………... 550

• Tools and Equipment ……………………….. 2,500

• Subsistence ………………………………….. 2,000

• Travel Time …………………………………... 2,200

• Bonds …………………………………………. 2,270

• Insurance ……………………………………... 600

• Extended Warranty ………………………….. 1 530

Total Cost per month ……………………………. $27,000

Total Cost ($27 000 x 4 months) ………………. $108,000

10% Office Overhead …………………………… 10,800

SUBTOTAL : $ 118,800

Profit (5%)…………………………………………. 5,940

TOTAL : $ 124,740

Page 32: Revay -Case Study on Eot Claim

Quantifying Overhead Costs

How much of the delay is truly compensable?(assume that 4 months delay is acceptable)

THREE OPTIONS :

Option 1: Average O/H during the peak period of work

• More common approach

• This will yield the highest result

• It is appropriate only when no delay occurred during the mobilization period

Option 2: Average O/H during the life of the project

• More common approach

Option 3: Average O/H during last 4 months of the project

• Much of the last period is demobilization

• A contractor will generally short change himself with this option

Page 33: Revay -Case Study on Eot Claim

Supreme’s Extended

Field Overhead Costs

Extra Work field O/H

• Supreme has received $1.5 million of extra work

• Duplication! Typical pricing of extra work contains monies for field O/H

• Explanation should be provided if this credit is not provided(i.e. “Extra work required additional resources which are not part of the extended field O/H”)

Actual O/H

Estimated costs

Extra work O/H

Optimum claimable O/H cost

Page 34: Revay -Case Study on Eot Claim

Supreme’s Extended

Field Overhead Costs

Home Office O/H & Profit

• In Principle, there is nothing wrong with claiming home office O/H and profit on its field O/H.

• The % should be based in the mark-ups defined in the contract

• Duplication! Supreme has claimed for home office O/H and profit on:- each individual item- within the charge out rates used to calculate labour impact- as a separate component at the end of the claim- under the guise of lost revenue

Page 35: Revay -Case Study on Eot Claim

Supreme’s Extended

Field Overhead Costs

Substantiation Should be Requested

• Claimed amount for each individual item is rounded off, undoubtedly upwards!

• It is possible that Supreme erred in making its claim and that some of the amounts are not as high as is suggested.

Time Related Costs

• Must ensure that Supreme is only claiming for ongoing time related costs

• Supreme should not be claiming for non-recurring costs such as:- Mobilization- Permits- Potentially insurance & bonds

Consumables and Tools

• Potential for duplication, if the charge out rates used by Supreme in claiming impact include an allowance for consumables and small tools.

Page 36: Revay -Case Study on Eot Claim

Supreme’s Extended

Field Overhead Costs

Extended Warranty Period

• Warranty period starts upon substantial completion with the owner but starts when the equipment is put in to service for the supplier.

• Due to delays, the gap between these two periods has extended considerably

• This is a valid item of claim. However:- How was the amount claimed determined?- Is there a more appropriate manner of dealing with this cost?

• The owner could simply indicate that it will accept a warranty period based on when the equipment was put into service.

• The owner could agree to pay actual costs if any occur.

There is ample room for discussion as to how this claimed cost might be addressed

Page 37: Revay -Case Study on Eot Claim

2. Extended Equipment

4 months x $ 40,000/month ………………… $ 160,000

• This is an extended overhead cost and as such, the aboveamount should be substantiated

• Supreme should be requested to demonstrate that the cranewas in fact on site for the additional four months claimed.

• It is not axiomatic that all overhead items will be extended bythe same duration as the project.

VALID

INVALID

� - Justification required

Page 38: Revay -Case Study on Eot Claim

3. Delayed Release of Holdback

Contract Value ……………………………………………. $ 31,500,000

10% Holdback……………………………………………… 3,150,000

Therefore, 4 months interest at 4% …………….. $ 42,000

VALID

INVALID

• Valid claim IF: the contract does not indicate that financing costs are part ofthe mark-up for profit and home office overhead

• The calculation, is incorrect!

• The contractor has suffered additional costs because it was required to financethe holdback for a longer period of time than would otherwise have occurred,as the project duration incurred from 9 months to 14.5 months. Thus, it isentitled compensation. It did not, however, finance the whole holdback for anadditional 5.5 months. Therefore, the calculation should be corrected to reflectthe varying level of holdback during the life of the project.

Page 39: Revay -Case Study on Eot Claim

4. Inclement Weather

Additional Heaters ………………………… $ 15,000

Temporary Protection ……………………. 15,000

Additional Labour ………………………….. 15,000

TOTAL: $ 45,000

This might be a valid claim subject to the following qualifications:• the amounts need to be substantiated• there has to be a demonstration that the delays being claimed did push the

work into winter• one has to ensure that no duplication exists with the costs claimed for

extended duration and impact.

VALID

INVALID

- Justification required�

Page 40: Revay -Case Study on Eot Claim

5. Overtime Premiums

Total Cost of Premium O/T Worked…………..……………... $ 25,000

Premium Cost Agreed by Owner …………….……………… (5,000)

SUBTOTAL: $ 20,000

a) Premium Portion of Overtime

Total Second Shift Premium ……………….………….…... $ 4,000

Amount Agreed by Owner …………………………….…… (1,000)

SUBTOTAL: $ 3,000

b) Second Shift Differential

TOTAL PRICE: …….………….…... $ 23,000

VALID

INVALID�

Page 41: Revay -Case Study on Eot Claim

5. Overtime Premium

• Supreme contends that it accelerated the work with the knowledge of theowner who should pay for the cost.

• The owner contends that whereas it was aware that an acceleration programwas ongoing, it was not aware that it was to the owner’s account. It assumedthe contractor was making good its own delays.

Arguments:

Valid Claim?

• A review of the records is required before deciding conclusively

• Supreme has a problem. It should have acquired a change order, asapparently occurred for other acceleration efforts. In this case, it is likely thatSupreme's silence will be his undoing.

• It is quite surprising how often one sees an acceleration program discussedin detail at site with neither party seeking to ascertain who is paying for theprogram and how inefficiency costs are going to be addressed.

Page 42: Revay -Case Study on Eot Claim

6. Loss of ProductivityHours Expended (includes subcontractors): ……………………... 400,000 manhours

Hours Estimated at Bid: …………………………………………………… 120,000 manhours

Includes scaffolding

The following list identifies all the adverse conditions experienced in executing the work. Pursuant to industry

averages and taking a very conservative approach, we have calculated the following efficiency losses.

Adverse Productivity Factors Manhours

Inclement Weather (5%) ………….......... 20,000

Shift Work (5%) ………………………….. 20,000

Overtime (5%) …………………………… 20,000

Impact from Changes (10%) …………… 40,000

Owner Interference (10%) ……………… 40,000

Congestion (5%) ………………………… 20,000

Adverse Productivity Factors Manhours

Overmanning (5%) ……………………… 20,000

Learning Curve (5%) …………………… 20,000

Site Access (5%)………………………… 20,000

Dilution of Supervision (5%) …………… 20,000

Stop-and-Go (5%) ………………………. 20,000

Errors and Omissions (5%)……………… 20,000

TOTAL LOSS OF EFFICIENCY… 280,000 manhours

COST ($100/hr. x 280,000 mhrs) : $ 28,000,000

VALID

INVALID

Page 43: Revay -Case Study on Eot Claim

7. Material Handling

Additional equipment costs arising from

down time and standby time…………………………….. $ 150,000

• This is an extended field overhead cost and as such, theabove amount should be substantiated

• The lack of detail raises a number of questions, such aspotential duplication.

VALID

INVALID

� - Justification required

Page 44: Revay -Case Study on Eot Claim

8. Safety

Additional tool box meetings

and indoctrination down time……………………………….$ 75,000

VALID

INVALID

� - Justification required

• Supreme is arguing that because of the extended duration, ithas experienced additional down time.

• Can be a valid claim, but is likely in this case a duplication ofamounts claimed for impact.

Page 45: Revay -Case Study on Eot Claim

9. Disputed Extras

Justified extras refused by consultant…………………..….$ 457,000

VALID

INVALID

• Depending on the contract there may be some potential entitlement problems. Oneshould ascertain if the contractor has satisfied the requirement to provide theappropriate Notice of Dispute.

• Potential duplication may exist with the impact claim.

• If the alleged extra is deemed not to be an extra then the allocated hours and materialare in fact an underbid. If they were in the bid they would obviously not be an extra.

These disputed extras are frequently very telling about the project and the personalitiesinvolved. The reasonableness of the parties becomes quite apparent as one reviews theseextras. Additionally, it is surprising how often one can resolve the claim by dealing withthese extras which are frequently the root source of the friction between the parties.

Page 46: Revay -Case Study on Eot Claim

10. Labour and Material Escalation

120,000 hrs. x $1.25 ……………………………. $ 150,000

Material Increase ………………………………… 150,000

TOTAL: $ 300,000

VALID

INVALID

� - Justification required

• If the project is extended, the contractor can be pushed into a period ofhigher wage rates or simply expend more labour in the period of higherwages. The same of course can apply to material.

• In Supreme’s case, whereas there might be some validity to the claim, the amount is clearly considerably inflated. A five and half month delay to a 14.5 month project should not cause 40% of the labour to be expended in a higher wage rate.

Page 47: Revay -Case Study on Eot Claim

11. Loss of Revenue

Background:

� The revenue guaranteed towards the support of his home office will be reduced (if not eliminated) when a contractor encounters compensable delays

� Home office costs are real and unavoidable

� Home office costs (in majority of cases at least) include:

- Estimation for projects to be tendered

- Accounting for the job and the corporation

- Purchasing

- Management of the overall direction of the corporation and frequently for individual projects

� Head Office, per se, does not generate revenue

Page 48: Revay -Case Study on Eot Claim

11. Loss of Revenue

Background:

� No construction project could function without the head office.

� Revenue for a construction organization is earned on the field

� Project bids must include an allowance towards the support of Home Office functions. Usually as a % of estimated project costs.

� This allowance will yield the required contribution to allow the head office to function

� This unabsorbed portion of the contractor's overhead, in case of a compensable delay, is a proper valid claim. The Supreme Court of Canada has addressed this issue in the case of Shore & Horwitz Construction Co. vs. Franki Canada Ltd.

� Eichleay Formula - most commonly used by contractors to calculate loss of revenue

Therefore:

� when project completion is extended without commensurate increase in the overall revenue, then the "take home" pay generated by that project will fall below the required (and estimated) level and therefore the home office is left with some of its costs "unabsorbed".

Page 49: Revay -Case Study on Eot Claim

COMPENSABLE DELAY

ACTUAL

PROJECTED

REVENUE

11. Loss of RevenueHome Office & Margin

RE

VE

NU

E

TIME

LOSS OF

REVENUE

PLANNED

Page 50: Revay -Case Study on Eot Claim

11. Loss of Revenue

Contract Billing

Total Billing X Total Overhead = Overhead Allocatable to the Contract

Actual Contract Duration

Allocatable Overhead= Allocatable Overhead Per Day

Daily Overhead X Delay Days = Loss of Revenue

Step 1:

Step 2:

Step 3:

Eichleay Formula

Note:

• Eichleay formula has been accepted in Canada several times.

• In the USA, it is generally accepted when the delay is akin to a suspension during

the work but is still greeted with some skepticism as a means of calculating

compensable overhead at the end of the job.

• The amount of money calculated may have absolutely no relation to the actual

losses of the contractor, who in fact may not even have suffered damages.

Page 51: Revay -Case Study on Eot Claim

11. Loss of Revenue

Per the foregoing formula, Supreme’s costs for this item are as follows:

500 million$ 441,500Step 1: 31.5 million X 7 million =

13 monthsStep 2:

$ 441,500 = $ 33,923/month

Step 3: $ 33,933 X 4 months = $ 135,692

VALID

INVALID

In the case at hand Supreme has several problems with the calculation.

• the calculation for loss of revenue duplicates the amount charged for overhead andprofit in the next item

• this claim item also duplicates the overhead and profit charged on individual items forif they are paid Supreme has not suffered unabsorbed overhead

• there also exists duplication with the amounts included for overhead and profit in theextra work.

This claim item is a hard sell and Supreme is better off simply applying the mark-up allowable in the contract, even if it yields a lower result. Applying the mark-up will cause less confusion and controversy and will usually be resolved much quicker with the same or a higher end result - i.e., money.

Page 52: Revay -Case Study on Eot Claim

11. Loss of Revenue (American)

Eichleay Formula:

Contract Billing

Total BillingX Total Overhead = Overhead Allocatable to the Contract

Actual Contract DurationAllocatable Overhead = Allocatable Overhead Per Day

Daily Overhead X Delay Days = Unabsorbed Overhead

Step 1:

Step 2:

Step 3:

Modified Eichleay Formula:

Step 1:

Step 2:

Step 3:

Contract BillingTotal Billing X Total Overhead = Overhead Allocatable to the Contract

= Allocatable Overhead Per Day

Daily Overhead X Delay Days = Unabsorbed Overhead

Original Contract DurationAllocatable Overhead

Page 53: Revay -Case Study on Eot Claim

11. Loss of Revenue

• HUDSON

• Overhead calculation based on Bid

• EMDEN

• Overhead calculation based on historical average over 2 to 3

years

Originated in Britain

Used in Canada

Page 54: Revay -Case Study on Eot Claim

12. Head Office Overhead & Profit

� Utilities

� Building

� Computers

� Administration

� Management

� Financing

� Insurance

� Bonding

� Extended Warranty

� Business Development

$ 29,512,432 x 10% = $ 2,951,243

VALID

INVALID

� - Justificationrequired

• Duplication. This item duplicates costs that have been included in the otherheads of claim.

• Typically, as is suggested in the previous item, this amount will be accepted ifone does not duplicate cost and treats the claim as a disputed extra/changedwork.

• The mark-up used in pricing this item should be equivalent to the mark upallowance in the contract for extra work.

Page 55: Revay -Case Study on Eot Claim

12. Head Office Overhead & Profit

• Administration

• Purchasing

• Engineering

• Tendering

• Financing

Page 56: Revay -Case Study on Eot Claim

13. Claim Preparation

Based on the costs expended,

claim preparation costs are 3.5% of the total claim:

$ 32,463,675 x 3.5% = $ 1,136,228

VALID

INVALID

�- Rationale:

• The amount and method of calculation is quite difficult to accept.

• Generally speaking, this item will infrequently be paid.

• It is usually considered part of doing business.

• It should be noted, however, that if the dispute enters the arena of arbitration or litigation the costs of experts are considered valid compensable costs.

Page 57: Revay -Case Study on Eot Claim

Recap: Evaluation of Damages

1. Extended Field Overhead…………………………………... $ 124,740

2. Extended Equipment………………………………………….. 160,000

3. Delayed Release of Holdback….…………………………… 42,000

4. Inclement Weather……………………………………………. 45,000

5. Overtime Premiums …………………………………………. 23,000

6. Productivity Loss …………………………………………….. 28,000,000

7. Material Handling …………………………………………….. 150,000

8. Safety …………………………………………………………. 75,000

9. Disputed Extras ………………………………………………. 457,000

10. Labour and Material Escalation …………………………….. 300,000

11. Loss of Revenue ……………………………………………… 135,692

SUBTOTAL : $ 29,512,432

12. Head Office Overhead & Profit (10%) ………………………. 2,951,243

SUBTOTAL : $ 32,463,675

13. Claim Preparation (3.5%) ………………………………………. 1,136,228

TOTAL : $ 33,599,903

Page 58: Revay -Case Study on Eot Claim

VII - How to Succeed in Disruption

Claims and improve the chances of a

Successful Project

to CCA Conference held March 2015

Presented by: Gerard Boyle

Page 59: Revay -Case Study on Eot Claim

Objectives

• Discuss how and why Disruption claims are

failing

• Describe a better way to get more or all of

your Rightful Entitlement earlier, and possibly

even avoid performance impediments that

would otherwise continue or worsen

Page 60: Revay -Case Study on Eot Claim

My Experience

• GC/CM

• At Revay:

– Claims Review

– Project Planning and Control on major

infrastructure, ICI, tunnelling, heavy civil, road,

airport projects

– Negotiated settlement of delay and disruption

claims

Page 61: Revay -Case Study on Eot Claim

Typical Setting and Outcome of

Disruption Claims

• Submitted late: before Substantial?

• Sub Claim Pass-thru by GC? Not much collaboration in preparation

• Negotiations fail or unsatisfactory (30 cents on the dollar; arbitrary award; even if agreement payment is delayed)

• Dispute Resolution approaches similarly unsatisfactory

• If no agreement, Liens, job disruption and delayed finish

• Since project probably finishes late, may be indirect claim as well

• Litigation uncertainty & cost compels contractor to absorb losses

• Hope for the best in the end

• Potential exposure to owner claims

Page 62: Revay -Case Study on Eot Claim

A Better Result

• Recover rightful

entitlement in a timely

fashion

• Improved project

performance thru more

efficient and effective

execution improves

bottom line

Page 63: Revay -Case Study on Eot Claim

1. PROBLEMS WITH THE CURRENT

APPROACHES TO DISRUPTION CLAIMS

Identify current problems

How to correct them

Page 64: Revay -Case Study on Eot Claim

Definitions – Impact/Disruption

• Impact Costs: “increased costs of one or several related construction activities, in excess of those which would have been but for an incident, action or omission relating to a separate (discrete) item of work. Often referred to as ripple effect, because originate in one or more isolated problems and spread like ripples through the project”. Not the direct (or discrete) cost of making a change. – Sometimes referred to as disruption costs or loss of productivity

costs.

• Disruption: “Loss of productivity, disturbance, hindrance or interruption to progress.”– “Local (Direct) Disruption”: direct impact that change works has

on other unchanged work around it.” Foreseeable!

– “Cumulative disruption”: disruption between two or more changes … and is exclusive of local disruption …Synergistic effect of changes on unchanged work and on other changes.”

Page 65: Revay -Case Study on Eot Claim

Example of “Local Disruption” or One-

to-One “Impact”

• Increased quantity of

embedded conduit

increases cost of

formwork

• Or delay into winter

work conditions

• Foreseeable,

quantifiable,

Page 66: Revay -Case Study on Eot Claim

Definitions: Cumulative Impact

• “When there are multiple

changes and they act in

sequence or concurrently, then

there is a compounding effect

– this is the most damaging

consequence for a project and

the most difficult to

understand and manage. The

net effect of the individual

changes … greater than sum

of individual parts.”

Page 67: Revay -Case Study on Eot Claim

1.1 TIMING IS EVERYTHING! DELAYING

UNTIL THE END IS HIGH RISK!

Page 68: Revay -Case Study on Eot Claim

“End-of-project Total-Cost

Disruption Claim”

Forecast Delay

Changes

priced/

approved

without

disruption

(or time-

based) costs

C.O. with direct

cost only

“The amount(s) set forth in this change order are for full

reimbursement for the direct cost of all labor, material,

and equipment … to perform the work described in this

change order. All rights are reserved and not accorded

or satisfied by this change order regarding any additional

time required or costs incurred to perform any and all

other work of the contract (including other change orders)

caused by this change order. For greater clarity, no

amount has been included for delay, disruption, impact,

cumulative impact of changes, productivity, acceleration

or consequential costs, and we reserve the right to claim

for any such costs.”

Contractor delays disruption cost

submission to end of project

As Built

Total Cost

Impact Claim

Page 69: Revay -Case Study on Eot Claim

What about “Direct Disruption”

(or 1-to-1 Impact)?

• Why isn’t this forward priced?!

• Can the contractor rely on “reservation of rights” to claim later?

• Does owner know real cost of this change? Informed decision?

Forecast Delay

Electrical

conduit in

formwork; or

winter work

C.O. with direct

cost only

Contractor postpones forward pricing

to end of project

As Built

Total Cost

Impact Claim

Page 70: Revay -Case Study on Eot Claim

What about Cumulative

Impact of Changes?

• Lost Productivity has been incurred to date and was discoverable …

• There will be future costs

• Can the Contract change process be used to address this?

• How does the owner know the significance of this issue and therefore really make an informed decision based and mitigate its own damages?

Forecast Delay

Contractor postpones disruption cost

submission to end of project

As B. Impact

• Numerous changes

over past 5 months

• For past 3 months,

productivity below

plan & declining

• Base contract

activities delayed,

taking longer.

Total Cost

Impact Claim

Page 71: Revay -Case Study on Eot Claim

Can Contractor rely on Reservation

Clause instead of Compliant Notice?

• While cumulative impact may not be foreseeable at early stage, a contractor should be able to identify productivity (and time) effects once they start to appear.

• “20 years ago Appellant might justifiably have taken position … it could not foresee any sort of impacts … We consider more plausible [now] that complete cost of change, including impact, [could be estimated].”

Page 72: Revay -Case Study on Eot Claim

Doyle vs. Carling – Failure to Notify on

Cumulative Impact Claim

• “The grumblings of this contractor, … in site minutes, display no intention to claim until December, 1983 [completion February, 1984]. Even then, no claim was actually advanced, but intent was indicated. But no details were given: an owner would be hard put to know exactly what it is to meet, and hence what it is to do. The purpose of the notice is to give the owner an opportunity of considering his position and perhaps taking corrective measures, and he is prejudiced by not being able to do it.”

Page 73: Revay -Case Study on Eot Claim

1.2 QUALITY PROBLEM: OVER-RELIANCE

ON, AND IMPROPER USE OF, INDUSTRY

STUDIES & FACTORS

Page 74: Revay -Case Study on Eot Claim

The Good News re. Quantifying

Productivity Claims

• Heavy burden of proof with respect to causation, but less so with the amount. Causation important because Contractor may be claiming for its own inefficiencies or a bad estimate.

• But if causation is established, even if amount defies precision, there may be leniency in quantification: “… there was uncertainty with respect to the extent of damage, but none as to the fact of damage; and there is a clear distinction between the measure of proof necessary to establish the fact [contractor] sustained some damage and measure of proof necessary to enable the jury to fix the amount.”

Page 75: Revay -Case Study on Eot Claim

Methods to Calculate Productivity Loss

• 1. Project-Specific damage calculations supported by contemporaneous project documentation preferred:– Measured Mile

– Earned Value Analysis

• 2. Industry Studies and Factors: (not project specific)– Cumulative Impact:

• Industry Studies– Leonard, CII, IBBS

• Factors:– MCAA

– Overtime/Over-crowding/Congestion:• US Dept of labour; NECA; CII; Army Corps

• Studies re. work density, manpower pl.v. act

Page 76: Revay -Case Study on Eot Claim

Assumptions & Inherent Limitations of

Productivity Loss Calculation Methods

• General:

– All will have element of subjectivity

– Causation must be established for each

• Measured Mile: (preferred but …)

– Unimpacted period? Similar work? Long enough?

Owner-caused? Apportionment possible?

Productivity data available?

Page 77: Revay -Case Study on Eot Claim

Assumptions & Inherent Limitations:

Industry Studies, Factors, Formulas

• Not project specific;

• “… viewed with scepticism by the courts.

Studies, factors, formulaic approaches … relied

upon by experts must be shown relevant … to

project at issue.”

Page 78: Revay -Case Study on Eot Claim

Assumptions and Limitations:

MCAA Factors

• MCAA Factors:

– Arbitrary and subjective

– Added or adjusted to obtain pre-determined

result

– Addition of multiple factors may be unreliable

– Objectivity? Mechanical contractor group

– Not based on empirical study

Page 79: Revay -Case Study on Eot Claim

Flawed Practice in using Productivity

Loss Methods

• Timely (or any) productivity data not available.

• Use of Studies or factors instead of project

specific methods like measured mile

• No attempt to apportion responsibility

• No attempt to identify causes

Page 80: Revay -Case Study on Eot Claim

Test the “End-of-Project Total Cost

Disruption Claim” against Claim Pillars

�Entitlement to claim for prod. per Contract: ?

�Notice: Just “grumblings”

�Critical Path Schedule Analysis: No reference to schedule at all, or only at the end.

�Mitigation: Owner deprived of opportunity?

�Apportionment (only owner-caused?): No effort to determine or apportion cause/ effect.

�Quantum fair and reasonable: Total Cost rarely justified.

Page 81: Revay -Case Study on Eot Claim

2. A SUCCESSFUL APPROACH

Page 82: Revay -Case Study on Eot Claim

Using the Contact to Succeed in

Disruption Claims

• Follow the Contract – especially change procedures

• Don’t wait until the end

• Changes to include all “reasonable costs”

• Include “reservation of rights clause”, but also …

• Forward price “direct impact” cost and time effects

• Quantify Cumulative Impact: – Identify effect and notify!

– Quantify historical effect

– Cause and effect: matrix, other

– Compare to studies (use in support of project specific analysis such as Measured Mile or Earned Value)

– Forward price (with qualifying assumptions): estimate based on current productivity, added Factors, etc.?

– Negotiation, dispute resolution

Page 83: Revay -Case Study on Eot Claim

Connecting Time to Production and

Productivity

Forming Wall – 12-Day Activity Duration

Activity Duration(w.d.) =Quantity of Work (s.f.)

Daily Production Rate (s.f./w.d.)

Daily Production Rate

(s.f./w.d.)

=

=11,184 s.f.

932 s.f./w.d.

Productivity (s.f./m.h.) x Effort m.h./w.d.

= 9.75 s.f./m.h. x 96 m.h./w.d. = 932 s.f./w.d.

Page 84: Revay -Case Study on Eot Claim

Measured MileImpacted vs. Non-Impacted Period

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2,000H

ou

rs p

er

Mo

nth

Oct

-92

Nov -

92

Dec -

92

Jan -

93

Feb -

93

Mar

-93

Apr

-93

May

-93

Jun -

93

Jul -

93

Aug -

93

Sep -

93

Oct

-93

Nov -

93

Dec -

93

Jan -

94

Feb -

94

Mar

-94

Apr

-94

May

-94

Jun -

94

Jul -

94

Aug -

94

Sep -

94

NON-IMPACTED PERIOD IMPACTED PERIOD

Hours per Month

Non-Impacted Hours per Unit

Bid Hours per Unit

Actual Hours per Unit

Lost Productivity

Underbid

25

50

75

100

125

175

200

225

250

Ho

urs

per

Un

it

150

Page 85: Revay -Case Study on Eot Claim

Cause Effect Matrix

RESULTED IN

RESULTED IN

Page 86: Revay -Case Study on Eot Claim

Productivity Monitoring

• To gain experience and

expertise, and support

in your productivity

claims.

Page 87: Revay -Case Study on Eot Claim

Conclusions• Contract compliance requires timely notice of reasonably

discernable effects so owner can mitigate its own damages

• Deferring disruption claims until the end of the project is high risk for the contractor

• The project is best served by identifying performance problems early so as to possibly avoid further delay and disruption

• Contract change mechanism usually affords an opportunity to claim for damages contemporaneously

• Distinguish between cumulative and other types of impact in quantifying claim

• Even cumulative impact claims can be resolved contemporaneouslyif the parties are willing and reasonable

• Track project-specific productivity data to feed MM and EV analysis

• 3rd party monitoring

• Negotiate settlement at the time, or make use of dispute resolution provisions

Page 88: Revay -Case Study on Eot Claim

References – Revay Reports –

available at the back of the room

Page 89: Revay -Case Study on Eot Claim

89