CITY OF CEDAR HILL RFQ # 2022‐100‐01 Request for Qualifications (RFQ) FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES FOR THE LIBRARY in the PARK PROJECT RFQ# 2022-100-01 CITY OF CEDAR HILL 285 UPTOWN BOULEVARD CEDAR HILL, TX 75104 ISSUED DATE October 11, 2021

Upload: others

Post on 06-Dec-2021

12 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01 

  

Request for Qualifications (RFQ)

FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES

FOR THE

LIBRARY in the PARK PROJECT

RFQ# 2022-100-01

CITY OF CEDAR HILL 285 UPTOWN BOULEVARD

CEDAR HILL, TX 75104

ISSUED DATE October 11, 2021

Page 2: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 2 of 18 

TABLE OF CONTENTS

 Section 1 – Introduction and Overview ........................................................................................................ 4 

Project Information ................................................................................................................................... 4 

Key Dates .................................................................................................................................................. 5 

Section 2 – Scope of Work ............................................................................................................................ 5 

Preconstruction Services:...................................................................................................................... 5 

Bidding Services: ................................................................................................................................... 6 

Construction Services: .......................................................................................................................... 6 

Section 3 – Questions ................................................................................................................................... 6 

Section 4 – Proposal Submission Requirements ........................................................................................... 7 

Submission Format ............................................................................................................................... 7 

Proposal Organization Guidelines ......................................................................................................... 7 

Section I — Qualifications of the Team................................................................................................. 7 

Section II — Proven Success ................................................................................................................. 8 

Section III — Firm’s Stability ................................................................................................................. 8 

Section IV — Capability and Capacity to Perform Work ....................................................................... 9 

Section V — Proposed Project Schedule ............................................................................................... 9 

Section VI – Required Forms (provided) ............................................................................................... 9 

Section 5 – Evaluation ................................................................................................................................. 10 

Section 6 – Schedule of Events ................................................................................................................... 12 

Section 7 – Terms and Conditions .............................................................................................................. 13 

Section 8 – Sample Construction Manager at Risk Contract ...................................................................... 17 

Section 9 – Required Forms ........................................................................................................................ 18 

Page 3: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 3 of 18 

KEY DATES AND INTRODUCTION 

   

   PROJECT NAME  Library in the Park Project – CMAR Services 

  

DELIVERY LOCATION  PURCHASING DEPARTMENT 285 UPTOWN BLVD CEDAR HILL, TX 75104 [email protected]  

AWARDED BY   QUESTIONS/ CLARIFICATIONS/ GENERAL REQUESTS 

THE CITY OF CEDAR HILL    Greg Pervis at [email protected] or (972) 291‐5100 ext. 1064 

All questions must be submitted in writing by the deadline indicated in  

Section 6 – Schedule of Events of this solicitation. 

  

 

 

QUALIFICATIONS DUE DATE AND TIME: Monday, November 8, 2021, 3:00 pm (CST) 

Sealed qualification packets shall contain four (4) hard copies and one (1) PDF file format on a 

USB flash drive. The maximum number of pages may not exceed 30 PDF pages excluding this 

RFQ, required City forms, the sample contract and any addendum response documents.  All 

electronic materials shall be submitted in searchable Adobe PDF format including the required 

City forms. Proposals should clearly mark the firm’s name and indicate “Library in the Park – 

CMAR/ RFQ‐2022‐100‐01” on the packet submission.  All submissions must be received by the 

City of Cedar Hill on or before 3:00 pm, CST, Monday, November 8, 2021, addressed and 

delivered to Greg Pervis, Purchasing Coordinator, Cedar Hill Government Center, 285 Uptown 

Blvd., Cedar Hill, Texas 75104. 

The City will not provide compensation or defray any costs incurred by any firm related to the 

response to this request. The City reserves the right to negotiate with any and all persons or firms. The 

City also reserves the right to reject any or all Statements of Proposal (SOP) with or without cause; to 

accept any SOP deemed, in the City’s sole discretion, to be most advantageous to the City; or to waive 

any irregularities or informalities in any SOP received; and to revise the process schedule as 

circumstances arise.  

   

Page 4: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 4 of 18 

Section 1 – Introduction and Overview The City of Cedar Hill, Texas (“City”) is accepting qualifications for a Construction Manager at Risk 

(CMAR) to provide preconstruction and construction services for its Library in the Park Project. The City 

is seeking a Construction Manager at Risk in a two‐step process as outlined in Texas Government Code 

“Chapter 2269 ‐ Contracting and Delivery Procedures for Construction Projects”.  The CMAR will perform 

pre‐construction and construction services working with the City staff, City Firms and the Design Team. 

Sealed qualification packets from CMARs consisting of four (4) hard copies and one (1) PDF file format 

on a USB flash drive, addressed to Greg Pervis, Purchasing Coordinator will be received at the 285 

Uptown Blvd, City of Cedar Hill Texas until 3 p.m. CST on November 8th, 2021. Late submittals shall not 

be accepted. All packages to be marked with the firm’s name and RFQ # 2022‐100‐01 

Firms intending on serving as contractors, subcontractors, sub‐subcontractors, vendors, or material 

suppliers should not submit qualifications in response to this request. The scope of services provided by 

the selected CMAR candidate will include, without limitation, assistance to the City and the Design Team 

during the process of preconstruction, construction, and the warranty period. Specific tasks to be 

performed by the selected CMAR will be more clearly identified in the negotiation process. 

The City reserves the right to reject all qualifications and re‐solicit for new qualifications, or to reject all 

proposals and temporarily or permanently abandon the project. The City makes no representations, 

written or oral, that it will enter into any form of agreement with any respondent to this RFQ for any 

project and no such representation is intended or should be construed by the issuance of this RFQ. By 

submitting qualifications in response to this RFQ, the respondent accepts the evaluation process and 

acknowledges and accepts that determination of the “most qualified” firm(s) will require subjective 

judgments by the City. Respondents acknowledge and accept that any costs incurred from the 

respondent’s participation in this RFQ process shall be at the sole risk and responsibility of the 

respondent. Respondents submit qualifications and proposals at their own risk and expense. 

Project Information 

The Library in the Park project will include:  

The 42,000 Sf Library facility   Site work required including landscaping, signage, fencing and lighting  Site utilities including water, sanitary, storm sewer and detention, electrical, gas and 

telecommunications 

Driveways, sidewalks, and parking lots  The Large Heart of the Park including a Great Lawn, Grand Promenade through Heart 

of the Park and up to Library Social Café, Amphitheatre, and Children’s play spaces 

Cedar Hill Road parking lot  1.2 miles of linear trail connecting Pleasant Run to Pioneer trail; Library project to 

Uptown Blvd 

Design Drawing are available at 

https://www.dropbox.com/sh/y57p281zx2qcoqa/AABSwYNFlEixBgelG6vc8kE_a?dl=0 

100% Design Drawing will be available on October 19th  

Page 5: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 5 of 18 

 The City of Cedar Hill, Texas is an equal opportunity employer and does not discriminate in awarding of contracts or employment of persons because of their race, color, age, national origin, religion, sex, disability, sexual orientation, or any other characteristic protected by law. The City of Cedar Hill, Texas requires companies with which it conducts business to be equal opportunity employers and comply with all applicable federal, state, and municipal laws and regulations regarding contracting and employment practices.  It is the policy of the City of Cedar Hill to actively encourage and seek qualified and certified HUBs, M/WBEs, DBEs, SBEs and local businesses to participate in all phases of the procurement process. In this effort, the City will take appropriate measures to assure that HUBS, M/WBEs, DBEs and SBEs have knowledge of, access, and equal opportunity to compete for the goods and/or services required by the City of Cedar Hill. For professional services, the participation shall include the respondent that demonstrates competence, qualifications, and the ability to perform the services for a fair and reasonable price based on the solicitation requirements.   The City Council has established a diversity goal of 30% for this project.  To qualify for the diversity goal, spending must be documented with vendors who are certified HUB, DBE, SBE or M/WBE per the City of Cedar Hill’s accepted certification partners.  For a listing of partners and for further information on Diversity in Procurement, please see the City’s website: http://cedarhilltx.com/2381/Purchasing‐Policy.   

Key Dates 

The following Schedule of Events represents the best estimate of the schedule the City will 

follow. Any significant change to the schedule will be published via RFQ Addendum. 

Event  Estimated Date 

Release RFQ  Monday, October 11, 2021 

Newspaper Advertisement Dates  October 11, 2021 – November 8, 2021 

Attend at least 1 MANDATORY:  

Pre‐Proposal Conference 

Thursday, October 28, 2021, 11:00 am (CST) OR 

Thursday, October 28, 2021, 3:00 pm (CST) 

285 Uptown Blvd., Cedar Hill, TX 75104 

Deadline for Proposal Submissions  Monday, November 8, 2021, 3:00 pm (CST)  

 

Section 2 – Scope of Work 

Preconstruction Services: The CMAR will work with the Design Team and the City during the design 

process to ensure the feasibility and constructability of the building. The CMAR will also be responsible 

for cost estimates during design development and construction document phases of the project. The 

CMAR will work with the Design Team and City to ensure that the cost of construction of the Project is 

within the estimated Construction Budget through the selection of construction systems and materials, 

detailed CSI format cost estimating, scheduling, and other means.  

Page 6: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 6 of 18 

The CMAR will also review the project schedule and identify critical path and long lead items. Upon the 

completion of the design development phase and prior to the completion of the 100% set of 

construction documents, the CMAR will submit a proposal of a Guaranteed Maximum Price (GMP) for 

the construction of the Project, which is within the City’s Construction Budget. 

Bidding Services: Should the City exercise its option, the CMAR will serve as General Contractor to 

complete all work for the bidding and construction of the project. The CMAR will be responsible for 

coordination of all bids, advertisement, and solicitation, bid procurement, selection of sub‐Firms or 

trade contractors as outlined in Texas Government Code Chapter 2269. CMAR will also be responsible 

for issuance of pre‐purchase orders for long lead items, if required. 

Construction Services: Should the City exercise its option, the CMAR will serve as General Contractor 

to complete all work for the construction of the Project. The scope of Construction services will be 

determined based on the final Drawings and Specifications but may include, but not be limited to, one 

or more of the following areas of work: site clearing, excavation, fill, select fill and backfill; site utilities; 

concrete sidewalks, paving and roadway / parking lot work, rough and finish grading, topsoil and grass 

planting; fencing and gates, site lighting, retaining wall construction, landscape installation, irrigation, 

concrete piers, concrete slab‐on‐grade, concrete masonry (CMU) interior walls, cast stone lintels, 

limestone and plaster exterior veneer, concrete floor topping, masonry, structural steel frame (columns 

and joists), metal roof deck, metal wall and roof panels, miscellaneous metals and metal fabrications; 

rough and finish carpentry, millwork and casework; damp proofing and waterproofing, caulking and 

sealants, thermal insulation, flashing and sheet metal, metal soffit panels, metal roofing, modified 

bitumen roofing; other roofing, wood doors, metal doors and frames, aluminum doors and frames, glass 

and glazing, finish architectural hardware, acoustical ceilings, resilient flooring and base, carpeting, tile 

or wood flooring, metal studs and support systems, gypsum drywall, painting and special floor coatings, 

interior and exterior signage; reinforced extreme weather structural walls and windows; reinforced 

ballistic walls and windows; metal louvers and miscellaneous specialties; furnishings and appliances; 

equipment and specialty equipment; sound enhancement systems; fire protection; lightning protection; 

telecommunications, audio / visual and security systems and mechanical, plumbing and electrical 

systems, and any other requirements set out in the Contract Documents. 

Section 3 – Questions Any questions shall be submitted prior to the question deadline in writing and addressed to Greg Pervis 

via email only at [email protected]. No oral question or inquiry about this RFQ shall be 

accepted. The City reserves the right to provide questions and answers to all prospective respondents in 

the form of an addendum to the RFQ. All addendums will be posted to the City’s website at 

cedarhilltx.com/purchasing.  Firms shall not attempt to contact City Council members, City staff or 

Management directly during the pre‐proposal or post‐proposal period. 

 

 

 

  

Page 7: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 7 of 18 

Section 4 – Proposal Submission Requirements There is no actual, express, or implied obligation for the City to reimburse responding Firms for any costs 

or expenses incurred in preparing proposals in response to this Request for Proposal, and the City will 

not reimburse responding Firms for these costs or expenses, nor will the City pay any subsequent costs 

associated with the provision of any additional information or presentations, or to procure a contract for 

these services. The City is not responsible for any cost(s) incurred by a Firm in preparing and/or 

submitting a proposal in response to this RFQ. The City will not be responsible for any costs associated 

with preparing and/or participating in any systems demonstrations requested of the Firm’s services.  

Submission Format Sealed qualification packets shall contain four (4) hard copies and one (1) PDF file format on a USB flash 

drive. The maximum number of pages may not exceed 30 PDF pages excluding this RFQ, required City 

forms, the sample contract, any addendum response documents, the cover letter, resumes and 

attachments such as photographs or other exhibits.  Attachments are limited to five (5) pages. All 

electronic materials shall be submitted in searchable Adobe PDF format including the required City 

forms. Proposals should clearly mark the firm’s name and indicate “Library in the Park – CMAR/ RFQ‐

2022‐100‐01” on the packet submission.  All submissions must be received by the City of Cedar Hill on or 

before 3:00 pm, CST, Monday, November 8, 2021, addressed and delivered to Greg Pervis, Purchasing 

Coordinator, Cedar Hill Government Center, 285 Uptown Blvd., Cedar Hill, Texas 75104. 

Proposal Organization Guidelines The proposal must include the information noted in this section and be organized accordingly. The 

submitted response to this RFQ should be as concise as possible while adhering to the format and 

information requirements described below. Please limit your response to a maximum of thirty (30) 

single sided pages, excluding the cover letter, resumes and attachments such as photographs or other 

exhibits. Attachments are limited to five (5) pages. Font size of 11 or larger is required.  Global page 

numbers and a table of contents is recommended.  Absolutely no fee or cost proposal should be 

provided in response to the RFQ. The submitted response shall be divided into the following sections: 

Section I — Qualifications of the Team  

Section II — Proven Success 

Section III — Firm’s Stability 

Section IV — Capability and Capacity to perform work 

Section V — Proposed Project Schedule 

Section VI— Required City Forms 

The submittal shall include at a minimum the following information: 

Section I — Qualifications of the Team 

Provide a brief overview of your firm, including years in business, dollar volume per year for the 

last five years, and significant projects completed in that time. 

Provide a description of the composition and management structure of your team. Provide a 

description and separate graphic organizational chart complete with working titles. Identify the 

lines of authority, responsibility and coordination. 

Page 8: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 8 of 18 

Identify the firm’s roles, responsibilities, and relevant experience with projects of similar scope 

and complexity, specifically focused on municipal public Library experience of a similar size 

and/or budget. 

Include the qualifications and relevant experience of the proposed project manager and 

superintendent. 

Describe how the team’s experience will relate to the success of this project. 

Provide a description of how your team will meet the City’s 30% MWBE requirement. 

Provide a description of how your team selects qualified sub‐contractors, gets vigorous 

participation from them, and manages them effectively in a challenging construction 

marketplace. 

Provide your team’s CMAR’s Experience Modifier Rate (EMR) over the last five years and 

describe your teams’ safety program. Provide the resume of the safety manager for your firm, 

and a brief description of the unique features of your safety program. 

Section II — Proven Success 

Select your three (3) most relevant projects from the last five (5) years and provide, at a 

minimum, the following: 

The name of the project Library in the Park – CMAR/ RFQ‐2022‐100‐01 

The amount of your firm’s original contract 

The current contact information for the Owner 

The current contact information for the Architect 

Completion date 

Submitted letters of reference from past clients 

Total contract value at completion, together with a short description of change orders (e.g., 

owner initiated; design document ambiguity; unforeseeable condition; capricious building 

official’s direction, etc.). 

Brief description of each project including size, scope, type of building and budget. 

Provide at least one example of a construction cost estimate prepared by your firm from 100% 

Schematic Design (or earlier) documents in any format you believe appropriate. The example(s) 

are not required to be of a library or park project, but examples of this type would be the most 

illustrative of your team’s experience. 

Provide your firm’s approach to cost and change management. In addition, list the average 

percentage of change orders in your firm’s final project costs typically driven by changes that 

were not owner initiated, or driven by unforeseeable conditions. 

Section III — Firm’s Stability 

Please provide your firm’s total bonding capacity for the last five (5) years. In addition, please 

provide your firm’s bonding unused (available) capacity as of October 18th, 2021. The City 

understands this amount may have changed since that date. 

Provide the following financial information for your firm: 

The most recent balance sheet, profit/loss statement, and income statement. 

The most recent twelve month certified financial statement from a CPA; and 

The contact information (including email) for the representative most familiar with your account 

at the bonding and general liability insurance companies you propose to use, as well as the CPA. 

Page 9: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 9 of 18 

Authorization to discuss your firm’s financial history with the CPA and bonding/insurance history 

with the appropriate representatives of those firms. 

Provide the contact information for three (3) additional municipal references and permission to 

contact them. 

Current workload and availability to perform the work 

Provide information on any past, current, or anticipated claims (i.e., knowledge of pending 

claims) on respondent contracts; explain the litigation, the issue, and its outcome or anticipated 

outcome. 

Section IV — Capability and Capacity to Perform Work 

Describe the firm’s workload and availability to meet schedule 

Describe the project management plan, including project organization chart and resumes 

Describe the firm’s knowledge of Cedar Hill processes and procedures 

Section V — Proposed Project Schedule Please provide a proposed project schedule which emphasizes key milestones and the proposed 

completion date. 

Section VI – Required Forms (provided) 

Construction Manager at Risk Contract (sample provided) – PDF 

Business Diversity Form – Fillable PDF 

Insurance Agent Affirmation Form 

References Form – Fillable PDF 

Financial Statement Form – Fillable PDF 

Statement of Acknowledgement of Addendums (if applicable) 

 

   

Page 10: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 10 of 18 

Section 5 – Evaluation All proposals will be evaluated by a City of Cedar Hill Selection Committee (Committee). The Committee 

may be composed of City of Cedar Hill staff and other parties that may have expertise or experience in 

the services described herein. The Committee will review the submittals and will rank the proposers. 

The evaluation of the proposals shall be within the sole judgment and discretion of the Committee. All 

contacts during the evaluation phase shall be through the City of Cedar Hill’s Purchasing Coordinator 

only.  Proposers shall neither contact nor lobby evaluators during the evaluation process. Attempts by 

Proposer to contact members of the Committee may jeopardize the integrity of the evaluation and 

selection process and risk possible disqualification of Proposer. 

The Committee will evaluate each proposal meeting the qualification requirements set forth in this RFQ.  

Any proposal that is unrealistic in terms of the technical or schedule commitments may be deemed 

reflective of an inherent lack of technical competence or indicative of a failure to comprehend the 

complexity of the project requirements as set forth in this RFQ. 

The selection process may include oral interviews. Proposers will be notified of the time and place of 

oral interviews and of any additional information that may be required to be submitted.  

Proposals shall be evaluated in accordance with the following criteria: 

 

Criteria  Description  Points 

Qualifications 

The Firm and Individual Qualifications:  

Firm’s number of years in business, size and staffing 

Firm’s experience on similar projects of similar scope, size and 

quality 

Firm’s safety record and successful completion of municipal projects

Experience of proposed personnel on similar projects and as a 

project team 

40 

Capability & 

Capacity 

Capability and Capacity to perform work 

Workload and availability to meet schedule 

Project management plan, including project organization chart and 

resumes 

Knowledge of Cedar Hill processes and procedures 

30 

References  The firm’s references based on similar project scope and size  20 

Project Schedule 

Proposed Project Schedule  10 

Interview Successful presentation, interaction, communication skills and responses to proposed questions  25 

Diversity and 

Inclusion 

The Firm’s approach to diversity and inclusion in the staffing and 

subcontracting of counselors. The Firm’s plan and capacity to meet the 30% 

M/WBE Diversity Goal 

10 

  Total Number of Possible Points 135 

Page 11: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 11 of 18 

Final scoring for these criteria may be adjusted based on the results of reference calls, or other 

supplemental information requests. In addition to the foregoing criteria, the award of a contract will be 

based on the criteria responses and an evaluation of the best overall value and benefit to the City. 

Note: It is the Firm’s sole responsibility to submit information related to the evaluation categories. The 

City is under no obligation to solicit such information if it is not included in the Firm’s original proposal. 

Failure to do so may result in your Proposal being disqualified from further review and consideration. 

The City makes no guarantees or representations that any award will be made and reserves the right to 

cancel this solicitation for any reason, including: 

Reject any and all proposals received as a result of this RFQ, with or without cause. 

Waive or decline to waive any informality and any irregularities in any proposal or responses 

received. 

Negotiate changes in the scope of services to be provided. 

Withhold the award of contract(s). 

Select Firm(s) it deems to be most qualified to fulfill the needs of the City. Firm(s) with the 

lowest priced proposal(s) will not necessarily be selected, since a number of criteria other than 

price are important in the determination of the most acceptable proposal(s). 

Terminate the RFQ process. 

   

Page 12: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 12 of 18 

Section 6 – Schedule of Events The following Schedule of Events represents the best estimate of the schedule the City will follow. Any 

significant change to the schedule will be published via RFQ Addendum. 

 

Event  Estimated Date 

Release RFQ  Monday, October 11, 2021 

Newspaper Advertisement Dates  October 11, 2021 – November 8, 2021 

Release 100% Design Development 

Plans as RFQ Addendum Monday, October 18, 2022 

Deadline for Written Questions   Friday, October 22, 2021, 3:00 pm (CST) 

Response to Written Questions   Tuesday,  October 26, 2021, 4:00 pm (CST) 

Attend At Least 1 MANDATORY:  

Pre‐Proposal Conference 

Thursday, October 28, 2021, 11:00 am (CST) OR 

Thursday, October 28, 2021, 3:00 pm (CST) 

285 Uptown Blvd., Cedar Hill, TX 75104 

Deadline for Proposal Submissions  Monday, November 8, 2021, 3:00 pm (CST)  

Evaluation Period Begins  November 8, 2021 – November 12, 2021 

Finalist(s) Notification   Monday, November 15, 2021 

Finalist Interviews  November 15, 2021 – November 19, 2021 

City Council Consideration  Tuesday, December 14, 2021 

Notice to Proceed  Wednesday, December 15, 2021 

 

 

Page 13: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 13 of 18 

Section 7 – Terms and Conditions The following terms and conditions apply to this RFQ solicitation process and will be incorporated into 

the resulting contract as applicable. 

 

The successful/selected Firm will be required to enter into a written Construction Manager At Risk 

Agreement (the “Agreement”) in a form substantially similar to the attached example. Such agreement 

will be prepared by the City and approved by the City Attorney. Firms submitting a response to the RFQ 

should make themselves fully aware of the terms and conditions in the attached example including, but 

not limited to, the indemnification and insurance requirements, incorporated herein for all purposes.  

This Request for Qualifications shall become part of the Agreement. 

Term / Termination 

The Agreement shall be effective upon the date it is executed by the City after execution by the Firm and 

shall expire upon completion of the Services covered by the Agreement.   The City reserves the right to 

extend/renew the contract(s) awarded as a result of this solicitation. The Agreement may be terminated 

by the City upon thirty (30) days written notice of such termination. In the event of termination by the 

City there shall be no further obligation on the part of the City to the Firm to save and except for 

payment of sums due and owing for expenses and work incurred by the Firm prior to the date of 

termination, minus any City incurred damages if such termination is for cause. In the event of any 

termination, Firm shall agree to cooperate in connection with any necessary transition services and shall 

be reimbursed for such transition services at Firm’s standard rates. The beginning of the term of any 

licensing or subscription fees for software may be subject to the negotiation of the City and the Firm, 

such that they do not coincide with the contract execution date. 

 

Payment Terms 

Net 30. 

 

No Obligation, Right of Rejection, and Multiple Award 

The inquiry made through this RFQ implies no obligation on the part of the City. This RFQ does not 

constitute an offer or a contract with any Firm or other party. 

 

As previously stated, and to emphasize, the City reserves the right to reject any or all Proposals, in whole 

or in part, or to accept or reject all or any part of any Proposal. Proposals deemed to be received from 

debarred or suspended vendors will be rejected. The City may reject any Proposal that is not responsive 

to all of the material and substantial terms, conditions, and performance requirements of this RFQ. The 

City further reserves the right to award all, part, or none of the components/functional areas included in 

this RFQ. In addition, the City reserves the right to make one or more awards to competing Firms for 

subsets of functionality as a result of this RFQ. The City reserves the right to reject any Proposal 

determined to be nonresponsive. The City reserves the right to negotiate with any or all Firms with 

respect to any or all terms of a Proposal or Contract, including but not limited to the fees. The City also 

reserves the right to refrain from making an award if it determines it to be in its best interest. The City 

reserves the right to abandon the Project and/or to re‐advertise and solicit other Proposals. 

 

 

Page 14: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 14 of 18 

Contract Changes 

Written requests for price changes in a resulting term contract after the Firm price period must be 

submitted in writing to the City at least one‐hundred eighty (180) days prior to the commencement of 

any extension period. Any proposed price increase will be based on the Firm’s actual cost increase only, 

as shown in written documentation provided to the City. All requests for price increases must be in 

writing, must not constitute increases in profit, and must contain data establishing or supporting the 

increase in cost. In connection with any request for price increases in term contracts after the Firm price 

period, at the option of the City, (1) the request may be granted; (2) the contract may be cancelled by 

either party; or (3) the contract may be extended without change with the consent of both parties. 

 

Contract Approval 

Proposers understand that this RFQ does not constitute an offer or a contract with the Firm. This RFQ 

does not, by itself, obligate the City to award a contract. The City’s obligation will commence only 

following City Council approval of a contract and the parties’ execution of the contract. Upon written 

notice to the Firm, the City may set a different starting date for the contract. The City will not be 

responsible for any work done or expense incurred by the Firm or any subcontractor, even if such work 

was done or such expense was incurred in good faith, if it occurs prior to the contract start date set by 

the City. 

 

Contract Dispute 

In the event of contract dispute, dispute proceedings will be held in Dallas County, Texas and pursuant 

to and in accordance with the terms of the Agreement.  

 

Confidential Information 

Any written, printed, graphic, electronic, or magnetically recorded information furnished by the City for 

the Firm’s use are the sole property of the City. This proprietary information includes, but is not limited 

to, customer requirements, customer lists, marketing information, and information concerning the City 

employees, products, services, prices, operations, security measures, and subsidiaries. 

 

The Firm and its employees shall keep this confidential information in the strictest confidence and will 

not disclose it by any means to any person except with City approval, and then only to the extent 

necessary to perform the work under the contract or as may be required by law. These confidentiality 

obligations also apply to the Firm’s employees, agents, and subcontractors and Firm shall be liable for a 

breach of the confidentiality obligations by any such party. On termination of the contract, the Firm, its 

employees, agents, and subcontractors will promptly return any confidential information in its 

possession to the City. 

Insurance Requirements 

The insurance requirements applicable to the successful/awarded Firm are set for in the Agreement 

included herewith. 

 

Conflict of Interest 

Firms shall at all times observe and comply with all federal, state, and local laws, ordinances, and 

regulations including all amendments and revisions thereto, which in any manner affect Firms or the 

services and/or items to be provided, specifically and not limited to any laws relating to conflicts of 

Page 15: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 15 of 18 

interest. Failure to comply with any applicable laws may result in: i) the termination of the contract; ii) 

the forfeiture by Firms of all benefits of the Contract; iii) the retainage by the City of all Services 

performed by Firm and iv) the recovery by the City of all consideration, or the value of all consideration, 

paid to Firm pursuant to any awarded contract. The City will require the selected Firm to sign a Conflict 

of Interest (CIQ) form and other vendor forms upon selection. 

 

Pending and Recent Litigation 

Firms must disclose any pending or recent litigation they are involved in as a company. Recent is defined 

as the past three (3) years. Information provided should include the timeline of the litigation history, the 

subject of the litigation, and the current status of the litigation. Proposals must also disclose any 

pending litigation of any third‐party partners in the Proposal. 

 

Contract Negotiation 

After final evaluation, the City may negotiate with the offeror(s) of the highest‐ranked Proposal. If any 

Firm fails to negotiate in good faith, the City may terminate negotiations and negotiate with the offeror 

of the next highest‐ranked Proposal or terminate negotiations with any or all Firms. 

 

If contract negotiations are commenced, they may be held at the City or via teleconference at a date 

and time to be determined. If contract negotiations are held, the Firm will be responsible for all of Firm’s 

costs including, without limitation, its travel and per diem expenses and its legal fees and costs. 

 

Failure to Negotiate If the selected Firm: 

1. Fails to provide the information required to begin negotiations in a timely manner; 

2. Fails to negotiate in good faith; 

3. Indicates it cannot perform the contract within the designated timeframes or within budgeted 

funds available for the Project; and/or 

4. If the Firm and the City, after a good‐faith effort, cannot come to terms; then the City may 

terminate negotiations with the Firm initially selected and commence negotiations with the next 

highest‐ranked Firm. At any point in the negotiation process, the City may, at is sole discretion, 

terminate negotiations with any or all Firms. 

 

Policy Compliance 

The Firm shall, as a condition of being considered for award of the contract, require each of its agents, 

officers, and employees to abide by the City policies prohibiting sexual harassment and smoking, as well 

as all other reasonable work rules, safety rules, or policies regulating the conduct of persons on City 

property at all times while performing duties pursuant to the contract. The Firm agrees and understands 

that a violation of any of these policies or rules will constitute a breach of the contract and will be 

sufficient grounds for immediate termination of the contract by the City. 

 

Procurement Policy 

The City of Cedar Hill Purchasing Policy and Procedures Manual March 2018 is pursuant to current State 

of Texas and local purchasing laws.  

  

Page 16: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 16 of 18 

Public Information 

All Proposals, responses, inquiries, or correspondence relating to or in reference to this RFQ, and all 

reports, charts and Proposals or referencing information submitted in response to this RFQ, shall 

become the property of the City, and will not be returned. The City will use discretion with regard to 

disclosure of proprietary information contained in any response but cannot guarantee information will 

not be made public. As a governmental entity, the City is subject to making records available for 

disclosure pursuant to applicable public record disclosure laws, and Proposers, including the Firm 

ultimately awarded the contract, shall cooperate in complying with such public disclosure laws at no 

additional cost to the City. 

 

Ownership of Data and Transition 

Any and all City data stored on the Firm’s servers, or within the Firm’s custody, is the sole property of 

the City. The Firm, its subcontractor(s), officers, agents, and assigns shall not make use of, disclose, sell, 

copy, or reproduce the City’s data in any manner, or provide to any entity or person outside of the City 

without the express written authorization of the City. In the event resulting Agreement is terminated for 

any reason, or upon expiration, and in addition to all other rights to property set forth, the Selected Firm 

shall: 

a) Incur no further financial obligations for materials, Services, or facilities under the Agreement 

without prior written approval of the City; 

b) Terminate all purchase orders or procurements and any subcontractors and cease all work, 

except as the City may direct, for orderly completion and transition; and 

c) Make available to the City, at no cost, all City data stored within the system, stored on the Firm’s 

servicers, or within the Firm’s custody, within fifteen (15) days of termination or at the City’s 

request. 

d) In the event resulting Agreement is terminated for any reason, or upon expiration, and in 

addition to all other rights to property set forth, the City shall retain ownership of all data, work 

products, and documentation created pursuant to the resulting Agreement. 

 

   

Page 17: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 17 of 18 

Section 8 – Sample Construction Manager at Risk Contract 

 

Page 18: Request for Qualifications (RFQ)

CITY OF CEDAR HILL    RFQ # 2022‐100‐01  

 Library in the Park‐CMAR RFQ    Page 18 of 18 

Section 9 – Required Forms  1. Sample Constriction Manager at Risk Contract  

2. Business Diversity Form 

3. Insurance Agent Affirmation Form 

4. References Form – Fillable PDF 

5. Financial Statement Form – Fillable PDF 

6. Statement of Acknowledgement of Addendums (if applicable) 

 

 

 

Page 19: Request for Qualifications (RFQ)

BUSINESS DIVERSITY

The City of Cedar Hill is committed to increasing participation by minority/woman-owned business enterprises (“M/WBE’s”) in all phases of its procurement processes and to support, to the greatest extent feasible, their efforts to compete for purchases of equipment, supplies, services, and construction-related services on a fair and equitable basis as either prime contractors or sub-contractors.

Contractors/s are to provide the opportunity for competent M/WBE subcontractors and/or suppliers to work under a prime contract. This form is to be completed by all respondents.

Bid/RFP/RFQ Number Bid/RFP/RFQ Title

Name

Address Complete the following questions: Yes No 51% or more of the company is owned, controlled and operated by a U.S. citizen(s) who is a non-minority woman

If yes, WO – Women Owned (excludes women who identify as AA, AI, AP, BL, or HI women)

Yes No 51% or more of the company is owned, controlled and operated by a U.S. citizen(s) whose

ethnic origin is: AA – Native American BL – Black American AI – Asian Indian HI – Hispanic American AP – Asian Pacific American Gender M - Male F - Female

Yes No The company has been certified as minority/woman-owned?

If yes, attach a copy of current certification

document. Expiration Date: __________________

If yes, list all Certifying Agencies NCTRCA State of Texas HUB DFWMBC (Dallas Fort Worth Minority Business Council) Women’s Business Council

Other: ___________________________

Does your firm have an internal supplier diversity program?

Yes No

If yes, please provide the program contact information:

Name

Phone Number

Title E-mail Address

Page 20: Request for Qualifications (RFQ)

If your firm is not a certified M/WBE, describe your approach for accomplishing diversity (specify partnerships/ subcontracting opportunities, the labor, trade, suppliers and/or professional services, etc.):

To the best of my knowledge, I certify that the information on this form is true and correct

Signature Printed Name Officer Title Date

Page 21: Request for Qualifications (RFQ)

INSURANCE AGENT AFFIRMATION

TO BE COMPLETED BY THE RESPONDING COMPANY AND SUBMITTED WITH THE NOTED RFQ/RFP.

THIS DOCUMENT APPLIES ONLY TO THIS SOLICIATION AND IS NOT TO BE DUPLICATED OR RE-SUBMITTED FOR ANY OTHER RFQ.

Name of Company Submitting the RFQ I, , affirm that the company listed above CURRENTLY HAS, by submission of the attached insurance certificate, the types of insurance in the respective amounts of coverage as specified in this Request for Submittals. I, , affirm that the company listed above HAS MADE ARRANGEMENTS TO OBTAIN the types of insurance in the respective amounts of coverage as specified in this Request for Submittals through the insurance agency named below.

Name of Insurance Agency:

Address of Agency: City/State/Zip:

Telephone Number: Facsimile Number:

Contact Name: Email: NOTE: Once the contract is awarded, the City of Cedar Hill must be named as an additionally insured and you must provide a certificate in effect. The insurance must be obtained from a company or companies acceptable to the owner, licensed to transact business in the State of Texas, and have a minimum financial security rating by A.M. Best of “A- (A minus)” or better, or the equivalent from any other rating system. In some cases, the solicitation may not call for insurance such as (professional services, equipment or other services). In the event the solicitation does not require a specified insurance, please mark N/A on each line and submit with the RFP/RFQ.

Page 22: Request for Qualifications (RFQ)

Company must provide three (3) client references for which projects of a comparable nature, value, scope, and complexity have been performed by the Company.

a. References must be for contracts done in the name of the Company submitting a proposal. b. References must be for contracts in progress or completed by Company; pending contracts are not

acceptable. c. References for contracts performed by Company as a subcontractor are not acceptable. d. References for contracts performed by Company’s staff while in the employment of another company are

not acceptable. e. The City of Cedar Hill is under no obligation to provide Companies a second opportunity to provide

references.

The City of Cedar Hill seeks competent, qualified and experienced contractors and the reference information shown below is a critical factor in determining to whom a contract will be awarded to. FAILURE TO PROVIDE ALL OF THE REQUESTED REFERENCE INFORMATION WITH YOUR PROPOSAL RESPONSE MAY RESULT IN THE DISQUALIFICATION OF YOUR PROPOSAL.

Client Information

Organization Name (Client):

Contact Name: Contact Title: Phone Number: Email Address: Date Work was Completed _____________________________ or mark as in Progress

Client Information Organization Name (Client):

Contact Name: Contact Title: Phone Number: Email Address: Date Work was Completed _____________________________ or mark as in Progress

Client Information Organization Name (Client):

Contact Name: Contact Title: Phone Number:

Email Address: Date Work was Completed _____________________________ or mark as in Progress

References

Page 23: Request for Qualifications (RFQ)

FINANCIAL STATEMENT To Whom It May Concern:

Re: /

(Company Name) (Owner’s Name) We confirm the following details regarding and :

(Company Name) (Owner’s Name) Initial the following statements:

( ) I confirm that is in Good Standing* (Federal, State, and Local taxes). (Company Name)

( ) I confirm that is permitted to do business in the State of Texas. (Company Name)

( ) I confirm to the best of our knowledge that

(Company Name) can pay all liabilities and is financially stable. This information is true to the best of my knowledge and our business records can confirm if an independent inquiry is requested.

Should you require any additional information, please contact:

(Name) (Business Phone Number) (Cell Phone Number)

To the best of my knowledge, I certify that the information on this form is true and correct.

Signature Printed Name Officer Title Date *The definition of Good Standing is no delinquent taxes and not debarred in the State of Texas or excluded from doing business with the federal government.