Republic of the Philippines Republic of the Philippines Department of Public Works and Highways (DPWH) Department of Public Works and Highways (DPWH) Office of the Secretary Office of the Secretary National Building Code Review Committee ( National Building Code Review Committee ( NBCRC NBCRC ) and the Board of Consultants ( ) and the Board of Consultants ( BoC BoC) New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) July 2005 Metropolitan Manila by Archt. Armando Dominador N. ALLÍ, fuap, piep, aaif Member, DPWH Board of Consultants (2002-2005) IAPOA

Upload: bridget-keyte

Post on 15-Dec-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

Republic of the PhilippinesRepublic of the Philippines Department of Public Works and Highways (DPWH)Department of Public Works and Highways (DPWH)Office of the Secretary Office of the Secretary National Building Code Review Committee (National Building Code Review Committee (NBCRCNBCRC) and the Board of Consultants () and the Board of Consultants (BoCBoC))

New Architectural Rules under the

2005 Revised IRR of PD 1096 (The National Building Code) July 2005Metropolitan Manila

by Archt. Armando Dominador N. ALLÍ, fuap, piep, aaif

Member, DPWH Board of Consultants (2002-2005)

(Resource Person)

IAPOA

Page 2: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

1. Hierarchy of Building Laws & Status1. Hierarchy of Building Laws & Status

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. Basic Law (PD 1096 or the NBC); unchanged for now but may still be repealed by an act of Congress (depending on the progress of DPWH BOC legislative work);

2. IRR of PD 1096/ NBC; revised by the BoC and NBCRC from 2000 through 2003; the 2005 Revised IRR was published April 2005 and took effect 02 May 2005; future revisions still possible depending on the outcome of the repeal effort on the basic law;

3. Manual of Procedure; a new DPWH executive issuance for completion by the BoC and NBCRC;

4. Additional IRR Guidelines and Building and Material Standards; other executive issuances that may still follow depending on need assessment by the BoC & NBCRC;

Page 3: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

2a.What was done to the National Building2a.What was done to the National Building Code (NBC)? Is it still “the Law”? Code (NBC)? Is it still “the Law”?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. The present NBC was promulgated 19 March 1977 as PD 1096 by President FM; its various Implementing Rules and Regulations (IRRs) were issued by the MPWTC until 16 July 1979; in 1992, only the IRR section on Permit Fees were amended;

2. In the year 2000, the DPWH re-organized the Board of Consultants (BoC) composed of representatives of accredited professional organizations (APOs) and reconstituted the Building Research and Development Staff (BRDS) into the NBC Review Committee (NBCRC);

3. the BoC was headed by a past UAP President (Angel Lazaro, Jr.) and 36 other member-professionals took part in the 3-year effort to revise only the IRR, which was signed by the DPWH Secretary on 03 Nov

2004, published April 2005 and which took effect 02 May 2005;4. as of 2005, PD 1096 (NBC) is still the only law on buildings as

it was neither amended nor repealed;

Page 4: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

2b. What will come next and when?2b. What will come next and when?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. With the 02 May 2005 effectivity date of the 2005 Revised IRR, the following may now take place:

a. possible DPWH issuance of general information materials for the public; members of APOs like the UAP and the PICE may have their members trained in dissemination work and will be asked to help disseminate information on the IRR; and

b. issuance of the manual of procedure for use by the Building Officials tasked to enforce the 2005 R-IRR; and

2. sometime in 2006, crafting of the bill (the “Building Law”)

that shall fully repeal PD 1096 (NBC) and fully assimilate the Revised IRR of 2005, should be completed; however, this new legislative effort may extend to 2007 and beyond;

Page 5: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

3. What are the 3. What are the generalgeneral features features of the 2005 of the 2005 Revised IRR that may be of interest to Revised IRR that may be of interest to ProfessionalsProfessionals??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. The 2005 Revised IRR applies particularly to all new structures located in new developments, i.e., along new road rights-of-way (RROWs), new subdivision or estate developments, particularly reclamation areas; rules on foot-printing and setbacks may be somewhat relaxed for new construction within built-up areas or for renovation/ rehabilitation projects; 2. The Revised IRR integrates general design and physical planning concerns, particularly on the matter of the development and usage of RROWs and ROWs and their collective effect on the determination of building bulk inside properties facing RROWs; 3. The building permit shall become a general permit to be first supported by ancillary or accessory permits; and 4. Architectural & Structural Permits are types of ancillary permits.

Page 6: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

4. What is the most important 4. What is the most important architecturalarchitectural provision of the 2005 Revised IRR? provision of the 2005 Revised IRR?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Under Sec. 302.3 (Application for Permits) of the 2005 Revised IRR, the signing and sealing of architectural documents shall be limited to Architects*, a provision fully harmonized with stipulations of RA9266:

SEC. 302. Application for Permits. 1. Any person desiring to obtain a building permit XXX . . . XXX shall file applications therefore on the prescribed application forms 2. XXX . . . XXX 3. Five (5) sets of survey plans, design plans and specifications and other documents prepared, signed and sealed over the printed names of the duly licensed and registered professionals: a. XXX . . . XXX; b. Architect, in case of architectural documents; in case of architectural interior/ interior design documents, either an architect or interior designer may sign; c. Civil Engineer, in case of civil/ structural documents; d. XXX . . . XXX

*Important Notes: 1) Temporary Restraining Order (TRO) replaced by Writ of Preliminary Injunction (WPI) dated 24 May 2005 issued by Manila RTC Branch 22 with NO final decision to date; and 2) the QC RTC Branch 219 in its order dated 23 May 2005 dismissed claims by Civil Engineers (CEs) that they can sign and seal architectural documents.

Page 7: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

5. What is 5. What is RA 9266RA 9266 and its relation to and its relation to Sec.302.3Sec.302.3 of the 2005 Revised IRR? of the 2005 Revised IRR?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1) Republic Act or RA 9266 is The Architecture Act of 2004 which took effect 10 April 2004, while its IRR took effect 01 December 2004;

2) Section 302.3 of the 2005 Revised IRR of the NBC (PD1096) is already fully harmonized with RA9266 and its provisions limiting the preparation, signing and sealing of architectural documents only to Registered Architects;

3) Civil Engineers (CEs) who shall continue to sign and seal architectural plans, specifications and documents shall still be subject to the application of the severe penalties under RA 9266 & its IRR (reference Sec. 29 of RA 9266);

4) The DPWH can still legally bar CEs from signing and sealing architectural plans, specifications and documents by invoking multiple provisions under RA 9266 (Sections 20, 29, 31, 32, 34, etc.) and its IRR, specifically Sec. 20.2 of RA 9266 which prohibits acting Building Officials/ Building Officials (or any other officer or employee of the republic) from accepting or approving any architectural plans or specifications not prepared in accordance with RA9266 and Sec. 44 which mandates all public officials to enforce RA9266.

Page 8: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

6. What are the 6. What are the Architectural (A) DocumentsArchitectural (A) Documents under the 2005 Revised IRR? under the 2005 Revised IRR?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Following is a list of architectural documents appearing under Sec. 302.4 of the Revised IRR of PD 1096 which took effect 02 May 2005. The definitions are omitted for brevity.

a. Architectural Plans/ Drawings i. Vicinity Map/ Location Plan . . . XXX. ii. Site Development Plan . . . XXX. iii. Perspective . . . XXX. iv. Floor Plans . . . XXX. v. Elevations, at least four (4) . . . XXX. vi. Sections, at least two (2) . . . XXX. vii. Reflected Ceiling Plan . . . XXX. viii.Details, in the form of plans, elevations/ sections: (a) accessible ramps . . . XXX (p) all types of partitions. ix. Schedule of Doors and Windows . . . XXX. x. Schedule of Finishes . . . XXX. xi. Details of Other Major Architectural Elements.

Page 9: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

7. What are the 7. What are the Architectural Interior (AI)Architectural Interior (AI) Documents Documents under the 2005 Revised IRR?under the 2005 Revised IRR?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Following is a list of architectural interior/ interior design documents appearing under Sec. 302.4 of the Revised IRR of PD 1096 which took effect 02 May 2005. The definitions are omitted for brevity.

b. Architectural Interiors/ Interior Design i. Space Plan/s or layout/s of architectural interiors. ii. Architectural interior perspective/s. iii. Furniture/ furnishing/ equipment/ process layout/s. iv. Access plan/s, parking plan/s and the like v. Detail design of major architectural interior elements. vi. Plan and layout of interior, wall partitions, furnishing, furniture, equipment/ appliances . . . XXX. vii. Interior wall elevations . . . XXX. viii.Floor/ ceiling/ wall patterns and finishing details . . . XXX. ix. List of materials used. x. Cost estimates.

Page 10: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

8. What are the 8. What are the Other Architectural (OA)Other Architectural (OA) Documents Documents under the 2005 Revised IRR?under the 2005 Revised IRR?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Following is a list of other architectural documents appearing under Sec. 302.4 of the Revised IRR of PD 1096 which took effect 02 May 2005. The definitions are omitted for brevity.

c. Plans and specific locations of all accessibility facilities . . . XXX. d. Detailed design of all such accessibility facilities outside and around buildings/ structures including parking areas, and their safety requirements . . . XXX. e. Fire Safety Documents i. XXX ii. XXX iii. XXX iv. XXX v. XXX

f. Other related documents

Page 11: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

9. 9. What do the terms What do the terms carrying capacity, development carrying capacity, development controlcontrol and and development potentialdevelopment potential actually mean (under actually mean (under the 2005 Revised IRR of the NBC/ PD 1096)? the 2005 Revised IRR of the NBC/ PD 1096)?

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Carrying Capacity of Lot – the optimized extent of physical development that may be introduced into the lot without causing undue damage, effects or hardship on the end-users of the proposed development or on neighboring occupants, entities, properties, lands, developments or the environment (whether man-made or natural) and with the proposed building/structure capable of being supported by existing utility, transportation and service systems or by proposed expansions/upgrading of such systems within the immediate future;

Development Control (for Lots and Buildings/ Structures) – a set of inter-acting regulations concerning the physical utilization of a lot and likewise governing the planning/design of spaces and/or the use/occupancy of a building/structure to be introduced (or already existing) on a lot; development controls help determine in detail the development potential and/or the carrying capacity of all lots and/or of proposed developments on lots; and

Development Potential of Lot – the maximum extent of physical development that may be introduced into the lot, i.e., the erection of the proposed buildings/ structures, after full compliance with the applicable regulations that need to be satisfied, specifically those found in the Code, i.e., the PNBC.  

Page 12: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

10. What are the new 10. What are the new architecturalarchitectural features features under under Rule VIIRule VII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. Under Rule VII (Classification & Requirements of Buildings by Use and Occupancy), a schedule of principal, accessory and conditional uses/ occupancies for buildings was prepared and matched with specific zoning classifications;

2. Rule VII, Sec. 704 : firewalls relative to foot-printing of buildings/ structures shall be strictly implemented; for instance, firewalls are explicitly prohibited for low density residential uses (R-1); allowed lengths of firewalls in relation to lot perimeter dimensions are prescribed for all other uses, specifically for residential condominium uses (R-5);

3. Rule VII, Sec. 705 - 707 : prescribes Allowable Maximum Total Gross Floor Areas (TGFAs), which is the product of the Building Height Limit (BHL), i.e., defined in both number of storeys and height in meters, and the Allowable Maximum Building Footprint (AMBF) for each type of building use/ occupancy;

4. Rule VII, Sec. 707, Subsection 4 : prescribes more detailed parking requirements for each type of building use/ occupancy; parking must be integral parts of building projects and all parking located outside shall be considered buffer parking;

Page 13: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

11a.What are the new 11a.What are the new architecturalarchitectural features features under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. Rule VIII (Light and Ventilation), Section 803 : maximum Percentage of Site Occupancy (PSO) is discussed at length; the identifiable Total Open Space within a Lot (TOSL) are sub-classified and limits prescribed for all building uses and occupancies, e.g., the Maximum Allowable Impervious Surface Area (ISA), the Minimum Unpaved Surface Area (USA);

2. Rule VIII, Section 804 : a) prescribes a minimum front setback of only 4.50 meters for a low density residential (R-1) structure on a minimum lot size of 301 sq.m. (14.0 m frontage x 21.5 m depth); b) prescribes a minimum front setback of 8.00 meters at the ground floor level only for medium and high density residential (R-2 and R-3) buildings/ structures that are more than 3 storeys/ 9.0 m in height; and c) prescribes front setbacks of from 5.0 to 8.0 meters for all types of commercial, industrial, institutional and recreational developments plus incremental side and rear setbacks for such buildings/ structures.

Page 14: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

11b.What are the new 11b.What are the new architecturalarchitectural features features under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 15: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

11c.What are the new 11c.What are the new architecturalarchitectural features features under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 16: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

11d.What are the new 11d.What are the new architecturalarchitectural features features under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 17: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

12. What are the new 12. What are the new architecturalarchitectural features features under under Rule XXRule XX of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Rule XX (Signs), Section 2004, Subsection 1.c.ii : Ground sign structures shall be located within the property line and under no circumstances shall these occupy the RROW/ street or sidewalk/ arcade or similar access-ways.

Rule XX (Signs), Section 2004, Subsection 1.d.i : On non-arcaded RROW/ streets, signs shall not extend more than 1.20 meters over the sidewalk measured horizontally from the wall line

or building line. On arcaded RROW/ streets, the signs shall not project more than 0.60 meters from the outermost portion of the wall line of the allowed structure over the arcade.

Page 18: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

13a.What are the new 13a.What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIRule VII of the 2005 Revised IRR of the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

1. Under Rule VII Guidelines, building bulk limitations are suggested through the interaction of Floor-Lot Area Ratios (FLAR), the Allowable Maximum Building Foot-print (AMBF), the Outermost Faces of the Building (OFB), the width of the road right-of-way (RROW) and all other applicable provisions for natural light and ventilation; 2. Under Rule VII Guidelines, examples are shown as to the manner of sizing buildings or establishing the development potentials of a lot/ property with the proper interactive application of the foregoing development controls; and 3. Under Rule VII Guidelines, the following are also included: a) floor to lot area (FLAR) designations for all major building occupancies; b) factors are also suggested to convert Gross Floor Areas (GFA) to Total Gross Floor Area (TGFA); c) determination of the outermost face of building (OFB) and outermost limit of building projection (OLBP) using angles drawn from the centerline of the road right-of-way (RROW); d) establishing the OFB through the interactive use of the allowed maximum building footprint (AMBF), the building height limit (BHL), the allowable maximum volume of building (AMVB) and the angular plane along the RROW; and e) buildings and accessory structures within cemeteries & memorial parks.

Page 19: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

13b. What are the new 13b. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIRule VII of the 2005 Revised IRR of the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 20: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

13c. What are the new 13c. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIRule VII of the 2005 Revised IRR of the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 21: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14a. What are the new 14a. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Under Rule VIII Guidelines, the following are included: a) suggested treatments for easements/ waterside rights-of-way (ROW), e.g., esplanades and promenades and stipulations on structures allowed/ disallowed along or within designated easement areas ; b) view corridors/ sight lines along road rights-of-way (RROWs); c) suggested median and lane widths within RROWs; d) suggested minimum RROW provisions for developments with multiple dwelling units; e) access to interior lots; f) suggested development components within RROWs at all its levels; g) use, treatment and development of arcades, sidewalks, curbs and driveways; h) incremental front setbacks for tall structures using RROW widths; i) detailed open space requirements for all building types/ occupancies; j) basement configurations for tall buildings; and k) design of public buildings and structures.

Page 22: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14b. What are the new 14b. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 23: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14c. What are the new 14c. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 24: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14d. What are the new 14d. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 25: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14e. What are the new 14e. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 26: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14f. What are the new 14f. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Page 27: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14g. What are the new 14g. What are the new architecturalarchitectural features features of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Rule VIII

Rule VIII

Guidelines

Page 28: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

14h. What 14h. What are some of theare some of the new new architecturalarchitectural of the of the GuidelinesGuidelines under under Rule VIIIRule VIII of the 2005 Revised IRRof the 2005 Revised IRR??

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

Rule VII

Page 29: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

15.Caveat15.Caveat

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)

To prevent illegal rule insertions in the printed version of the 2005 Revised IRR (which happened so many times in the past to

previous editions of the NBC IRR), the following steps should be taken:

a) the DPWH must be the only and solely designated copyright holder to the 2005 Revised IRR;

b) the only official source of the document (in either hard or soft versions) should be the DPWH; and

c) the only official publisher should be the National Printing Office (NPO) located along EDSA in Quezon City (between East Ave.

& Quezon Blvd.), i.e., not the National Bookstore!

Page 30: Republic of the Philippines Department of Public Works and Highways (DPWH) Office of the Secretary National Building Code Review Committee (NBCRC) and

DPWHDPWH Office of the SecretaryOffice of the Secretary BOC & NBCRC BOC & NBCRC IAPOAIAPOA

Thank You Thank You and and

a Pleasant Morning a Pleasant Morning to You All!to You All!

_________________________________________________________________________________________________________________________________

_New Architectural Rules under the 2005 Revised IRR of PD 1096 (The National Building Code) b y Archt. Armando Dominador .N. ALLI, fuap, piep, aaif

July 2005, Metropolitan Manila Member, DPWH Board of Consultants (2002-2005)