www.ppaf.org.pk
A Solar Mini Grid project setup under HRE is providing electricity to 54O� Grid households in Sarobi village, Karak – Khyber Pakhtunkhwa
PPAF has so far supported the implementation of more than 1300 Renewable Energy (RE) projects of diverse types and various capacities. These include the design and implementation of mini & micro hydropower projects, solar lighting and water pumping systems, wind energy projects, solar-wind hybrid and biogas plants.
INTRODUCTION
OBJECTIVES
PROGRAMME IMPACT
Eradicate poverty (SDG-1) by increasing access to a�ordable, reliable, sustainable and modern energy (SDG-7) Combating climate change and its impacts (SDG-13) thus reducing use of fuel wood, kerosene & diesel based power generationStrengthen local civil society organisations and enhance participation of the population in the decision making at the local level (SDG-17)Standardise design and implementation model of RE projectsBuild/enhance the technical capacity of project implementing partnersIncrease employment and income opportunities, especially for the poor, through the promotion of productive use of energy
Renewable Energy Projects with installed capacity of 11.3 MW of clean energy generated from RE projects65,000 households electri�ed so far481,000 people bene�ting directly including 218,000 men, and 263,000 women. (Figures are rounded o�)Additional bene�ts are in the form of better health, improved livelihood and education opportunities
Hydropower ProjectsSolar Lighting Systems
Wind Energy ProjectsHybrid (Wind/Solar)
Solar Water PumpingBiogas Digesters
Grand Total
9.8 MW800 kW119 kW101 kW193 kW277 kW
11.3 MW
97674197101193941,356
PPAF funded renewable energy interventions
RENEWABLE ENERGY PROGRAMMEPakistan Poverty Alleviation Fund
COVERAGE
Disputed Area
Punjab: Bhakkar, Chakwal, Khanewal, Khushab, Layyah, Lodhran, Multan, Muzafar Garh, Nankana, Narowal, Okara, Rahim Yar Khan, Rajanpur, Sheikhupura and Sialkot
Khyber Pakhtunkhwa: Lower Dir, Upper Dir, Chitral, Swat, Swabi, Bajaur Agency, Buner, D.I.Khan, Karak, Kohistan, Lakki Marwat, Shangla and South Waziristan Agency Balochistan: Zhob, Ziarat, Killa Saifullah, Killa Abdullah, Pishin, Gwadar, Lasbela, Awaran, Panjgur, Kech, Barkhan, Chagai, Dera Bugti, Jhal Magsi, Kharan, Khuzdar, Musakhel and WashukSindh:Badin, Dadu, Ghotki, Jamshoro, Karachi, Khairpur, Mirpur Khas, Sanghar, Tharparkar, Thatta and Umerkot
AJK:Neelum GB:Ghanche, Ghizer, Gilgit, Hunza Nagar and Skardu
Funded by the Federal Republic of Germany through KfW and implemented by PPAF, the Mini/Micro Hydropower Project was initiated in 2013 and is planned for completion in 2019. Project comprises of two components i-e Micro Hydropower Projects and Solar Mini Grid Systems. Pakistan Poverty Alleviation Fund is implementing this project through indigenous and specialised partner organisations including Aga Khan Rural Support Programme (AKRSP), National Rural Support Programme (NRSP), Sarhad Rural Support Programme (SRSP), Community Motivation & Development Organisation (CMDO) and Social Action Bureau for Assistance in Welfare & Organisational Networking (SABAWON).
COMPONENTS
Mini/ Micro Hydro Power ProjectsFive mini/ micro hydropower plants with total capacity of over 800 kW (ranging from 36 kW to 306 kW) are planned to be implemented in Chitral, Upper Dir and Buner Districts of Khyber Pakhtunkhwa. The produced electricity will not only be used for lighting purposes but small and mini enterprises will also be established. This will increase the household income, add value to local products and transform lives of marginalised communities.
Solar Mini-grid SystemsAs many as 68 Solar Mini-grid Systems with total installed capacity of 500 kW are planned to be implemented in remote and o�-grid locations of Karak, Swabi and Lakki Marwat districts of Khyber Pakhtunkhwa. These Solar Mini-grid Systems will provide basic lighting requirements as well as support to village level businesses and local enterprises.
THE HYDROPOWER & RENEWABLE ENERGY PROJECT KHYBER PAKHTUNKHWA
Plot 14, Street12, Mauve Area, G-8/1, Islamabad, Pakistan; UAN: +92-51-111-000-102; Website: www.ppaf.org.pk
/theppaf/c/ppafofficial/ppafofficial/company/ppaf /ppaf/ppafofficial /theppaf
Pakistan Poverty Alleviation Fund
Project Cost: 10 Million €
Project Recepients: 13,000
Year of Commencement:
2013
Targetted Year of Completion:
2019
Project Implementing Partner Organisations:
05
COVERAGE
Districts in KP
1. Chitral2. Upper Dir3. Buner4. Swabi5. Karak6. Lakki Marwat
1
4
3
2
5
6
306 kW MHP Gazeen
136 kW MHP Gollain Astore
125 kW MHP Pursat
200 kW MHP Bishoo Patrak
32 Mini-grid Systems of 185 kW
24 Mini-grid Systems of 119.5 kW
12 Solar Mini-grid Systems of 195.5kW
36 kW MHP Bagaria Khwar
Mini/Micro Hydropower ProjectSolar Mini-grid SystemsProgramme Area
Project Locations
OVERVIEW
Cumulative June, 2019Source: Quality Assurance, Research & Design – PPAF