renewable energy benefits: leveraging local industriesremember.irena.org/sites/documents/shared...
TRANSCRIPT
Renewable Energy Benefits:
Leveraging Local Industries
12th Meeting of the IRENA Council
November 2nd 2016
Renewable Energy Benefits:
Leveraging Local IndustriesOnshore Wind
2013
2015
2014
2016
2014
3
Activities and tasks for wind deployment
4
Project planning
Site selection Feasibility studies
Engineering design
Project development
2 580 human-days of labour for the planning of a 50 MW wind farm
70% labour
requirements
Equipment: resource assessment instruments, simulators, computers, software, CAD tools
Information: soil characteristics and the climatic features, policies and regulations
Legal, energy regulation, real
estate, and taxation experts
Financial analysts
Logistic experts
Engineers
Environment & geotech
Health & Safety
5
Manufacturing and Procurement
Onshore wind turbine cost breakdown
Component% of total investment of
wind farm
Wind Turbine 64% – 85%
Tower 16% - 18%
Rotor Blades 13% - 15%
Rotor Hubs 0.8% - 0.9%
Rotor Bearings 0.7% - 0.8%
Main Shaft 1.2% - 1.3%
Main Frames 1.7% - 1.9%
Gearbox 7.8% - 9.7%
Generator 2.1% - 2.3%
Yaw System 0.76% - 0.84%
Pitch System 1.6% - 1.8%
Power Converter 3.0% - 3.4%
Transformer 2.2% - 2.4%
Break System 0.8% - 0.9%
Nacelle Housing 0.8% - 0.9%
Others 7.7% - 8.5%
6
Manufacturing and Procurement
19 000 human-days to manufacture main components of 50 MW
Nacelle Blades Tower Monitor and control system
50% labour
requirements
Factory workers
Health and safety
Logistics
Quality control
Marketing and sales
EngineersAdmin Management
600
14010
2.5
1
Concrete Steel Fiberglass Plastic Copper Aluminum
7
Manufacturing and Procurement
Materials to manufacture and install a wind farm (tonnes/MW)
8
Manufacturing and Procurement
Materials to manufacture main components of a 3 MW turbine (tonnes)
Nacelle Blades Tower
Steel Aluminum Copper Fiberglass Concrete
6.7
1.2
75175
3.6
1.1
53.7
9
Transport
Manufacturing blades and towers close to project sites to minimize transport costs in the US
10
Transport
Truck drivers
Crane operators
Admin
Logistic experts
Regulation experts
Technical personnel to
supervise loading
875 human-days to transport main components of a 50 MW wind farm over 300 miles
USD 750 000 to transport main components of a 50 MW wind farm over 300 miles
11
Installation and grid connection
Site preparation and civil works
Assembling equipment
Cabling and grid connection
Commissioning
34 500 human-days required for the installation and grid connection of a 50 MW wind farm
50% labour
requirements
Equipment: found in the construction sector
Construction workers and
technical personnel
Professionals managing
cranes, trucks, etc.
Engineers and construction
foremen
H&S
EnvitonmentLogistics Quality control
12
Operation and maintenance
Onshore wind O&M cost breakdown
Component USD/MW/year % of total O&M cost
Wind turbine
maintenance20 100 – 24 500 47.6% - 49.3%
Electrical installation
maintenance1 100 – 1 300 2.6%
Insurances 7 500 – 9 800 18.9% - 18.4%
Land rental 4 000 – 6 000 11.7% - 9.8%
Management and
administration8 100 – 9 900 19.2% - 19.9%
Total 40 800 – 51 500 100%
2 665 human-days per year required for the O&M of a 50 MW wind farm
Management
Engineers
OperatorsCivil workers, technicians
Legal and regulation
EnvironmentAdmin
H&S
Telecomm
13
Decommissioning
8 400 human-days needed for the decommissioning of a 50 MW wind farm
Planning the decommissioning
Dismantling the project
Disposing/recycling the equipment
Clearing the site
74% labour
requirements
Engineers Environmental experts
Logistic experts
Technical personnel and civil workers
Lorry drivers and crane operators
Health and safety experts
Equipment: found in the construction sector
Renewable Energy Benefits:
Leveraging Local IndustriesSolar PV
2013
2015
2014
2016
2014
15
Activities and tasks for solar PV deployment
16
Cost breakdown of solar PV plant
Inverters 10%
Modules30%
Balance of System (BoS) 60 %
Detailed breakdown of solar PV BoS costs by country, 2015
(2015 USD/kW)
Source: IRENA (2016), The Power to Change
17
Project planning
Site selection Feasibility studies
Engineering design
Project development
2 120 human-days needed for the planning of a 50 MW PV plant
60% labour
requirements
Equipment: resource assessment instruments, simulators, computers, software, CAD tools
Information: climatic features, policies and regulations
Legal, energy regulation, real
estate, and taxation experts
Financial analysts
Logistic experts
Environment
Health & Safety
Engineers
18
Manufacturing and Procurement
14 000 human-days to manufacture main components of 10 MW
Solar cells Modules Inverters Structures and trackers
50% labour
requirements
Factory workers
Health and safety
Logistics
Quality control
Marketing and sales
Engineers
Admin & Management
Standardisation experts
19
Manufacturing and Procurement
0
50
100
150
200
250
Glass Steel Concrete Aluminium Silicon Copper Plastic
Materials to manufacture and install 1 MW of PV (tonnes/MW)
ton
nes
/MW
20
Transport
Truck drivers
Loading staff
Admin
Logistic experts
Shipping experts Quality
control
70 human-days to transport main components per 1 MW of solar PV over 100 miles
Cost of freight shipping can be estimated at average of USD 0.10 - 0.20 per tonne-mile
21
Installation and grid connection
Site preparation and civil works
Assembling equipment
Cabling and grid connection
Commissioning
40 000 human-days required for the installation and grid connection of a 50 MW PV plant
50% labour
requirements
Equipment can be found in the construction sector
Construction workers and
technical personnel
Engineers and construction
foremen
H&S
EnvironmentQuality control
22
Operation and maintenance
Onshore wind O&M cost breakdown
Component USD/MW/year % of total O&M cost
Maintenance 10 000 – 22 00041% - 52%
Land rental 8 000 – 12 00028% - 33%
Insurance 4 000 – 6 400 15% - 16%
Management and administration
2 500 – 3 0007% -10%
Total 24 500 – 43 400 100%
1 600 human-days per year needed for the O&M of 10 PV plants in one country
Management
Engineers
Operators
Civil workers, technicians
Legal and regulation
Environment AdminH&S
23
Decommissioning
Planning the decommissioning
Dismantling the project
Disposing/recycling the equipment
Clearing the site
60% labour
requirements
Engineers
Environmental experts Logistic
experts
Technical personnel and civil workers
Truck drivers & operators
H&S
Equipment: found in the construction sector
5 150 human-days needed for the decommissioning of a 50 MW PV plant
24
Recommendations
Research and
innovation
Strengthening firm-
level capabilities
Value is created along all the segments of the value chain
•Project development, site preparation and civil works offer opportunities
•Manufacturing locally can be driven by other factors
Strategy should be aligned with country overall objective
•Aligned with urgency of deployment and other support instruments
•Considering level of competition in the local, regional and global markets
Localisation should leverage on existing industries
•Existing resources such as skills, materials and equipment should be utilised
• Information needed should be made available to project developers
Mix of policies needed for an enabling environment
•Set targets and stable deployment policies ensure long-term demand
•Policies and measures to provide skills and strengthen local firms (quality standards and specifications, codes and trainings)
Thank you!