RENAISSANCE CONSTRUCTION
Building Information Modeling 5D Project Management
Technical Office and Planning Director - Atilla Kemal Saglam ( [email protected] )
Renaissance Holding Company Overview
Business as Usual
BIM & 5D Project Management
21.09.2012
Agenda
2www.rencons.com
Company Overview
• Rönesans Holding A.Ş. is a group of companies specifically focused on construction, real estate investment and energy production operations and established Commonwealth of Independent States, Middle East and North African countries as its home markets with ongoing operations in Turkey, Russia, Turkmenistan, Ukraine, Austria, Azerbaijan, Libya, Iraq, Saudi Arabia and Qatar.
• Projects include shopping centers, offices, hotels, mixed-used projects, heavy industry plants (cement plants, petrochemical plants, fertilizers, metallurgy plants, power plants, etc.), infrastructure projects (airports, marinas, etc.), light manufacturing plants, chemicals and pharmaceutical plants, food and beverage processing plants, automotive and construction machinery plants, government buildings and power plants as a main contractor and investor.
21.09.2012 3www.rencons.com
• Construction REC International Construction Investment Industry and Trade Inc.
• Real Estate Investment Renaissance Real Estate Investment Inc.
• Energy Renaissance Energy Production and Trade Inc.
21.09.2012 4www.rencons.com
21.09.2012
HQ – St.Petersburg Russia
Porr-RC JV Vienna – Austria
5www.rencons.com
• Ranked 69th in ENR (Engineering News Record) Top 225 International Contractors List in 2011
• Owns 10,22% shares of PORR AG (Austria)• Consolidated Holding Revenue 1,42 bn$ in 2010• Consolidated Total Assets 2,3 bn$ in 2010• 19,000 Employees • Majority shares owned by Ilıcak Famıly and the President is Dr.Erman Ilıcak.
21.09.2012 6www.rencons.com
Operational DivisionGeneral Construction Division Industrial Projects Division Infrastructure and Sports Venues
• Shopping Centers• Hotels• Offices• Mixed Used Projects• Light Manufacturing Plants• Automotive and ConstructionMachinery Plants• Government Buildings• Warehouses• Educational Buildings• Food and Beverage Processing Plants• Skyscrapers
• Cement Plants• Petrochemical Plants• Power Plants• Oil & Gas Refineries• Chemical Plants• Waste Water Treatment Plants• Mining & Metallurgy• Pulp & Paper• Glass Production Plants
• Roads• Tunnels• Stadiums• Airports• Marinas
21.09.2012 7www.rencons.com
Commercial Real Estate Projects
June Mytischi Shopping Center – Moscow
Mega UFA Family Shopping Center – UFA
Galeria Shopping Center – St. Petersburg
City Palace – Moscow 21.09.2012 8www.rencons.com
Automotive & Construction Machinery Plants
21.09.2012
LIEBHERR Construction Machinery Plant – Nizhny Novgorod
HYUNDAI Motors Manufacturing Plant – St. Petersburg
9www.rencons.com
Industrial Plants
21.09.2012
Verkhnebakansky Cement Plant - Novorossiysk
Ammonia and Urea Plant Mary, Turkmenistan
10www.rencons.com
Land Development
21.09.2012
Istanbul Seaport - Turkey
11www.rencons.com
Business As Usual
21.09.2012
Tender Department Estimation Contract
Negotiations
Design Departments Structural Architectural Mechanical Electrical
Project Management Procurement Cost Control Scheduling
We have in-house estimation, design engineering and project management capabilities. Each of these functions have independent platforms which they work on and coordination is established manually by telephone or e-mails.
12www.rencons.com
Estimation
21.09.2012
• Both in the tender phase and during execution we use excel sheets to formulate our budgets and customer BOQs.
• We have direct and indirect budget workbooks with lots of sheets linked to each other with very complicated formulas and macros.
• We have predefined assemblies and BOQ items which are updated manually with feedback from construction sites.
• We use Primavera and Microsoft Project for scheduling purposes.
13www.rencons.com
Estimation
21.09.2012 14www.rencons.com
21.09.2012
Structural Design
Autodesk Robot Structural Tekla StructuresMicroFESTAAD ProSAP 2000ETABSAtena 2D – Atena 3DPlaxis 2D – Plaxis 3DNormCAD
3D Software as well as industry specific solutions
15www.rencons.com
21.09.2012
Structural Design
Autodesk Robot Structural Analysis 2012 – Mytishi Shopping Mall – Moscow
16www.rencons.com
21.09.2012
Architectural & Civil Design
AutoCAD 2011
3D Studio Max
17www.rencons.com
21.09.2012
Architectural & Civil Design
Mozaika Shopping Center – Moscow
18www.rencons.com
21.09.2012
Electrical - Mechanical Design
AutoCAD MEP 2013Autodesk REVIT MEP 2013LINDAB Dim Silencer CARRIER E20-II HAP TYCO SprinkCAD OmniCADD MagiCAD ASHRAE PsychometricIDA ICE DIALux
19
2D/3D Software as well as industry specific solutions
www.rencons.com
21.09.2012
Electrical - Mechanical Design
Volvo Assembly Building- Kaluga
20www.rencons.com
21.09.2012
Project Management
Scheduling
Actuals
SPI, CPIEarned Value Analysis
Business Intelligence
21www.rencons.com
21.09.2012
We already have;
3D VirtualDesign Scheduling
Cost
So, What is the Problem?
Why do we need anything else ?
Business Intelligence Reporting
22www.rencons.com
Problems
• Estimation No centralized database
Different estimation results based on different teams
No direct link to financial system, procurement or design
Separate excel sheets with links open to user manipulation
Estimation is not transparent for execution phase
Complicated format, hard to adapt for new comers, hard to understand
the underlying assumptions
Can easily distribute company knowledge to outside, security issues
No direct feedback from execution and update of assemblies
21.09.2012 23www.rencons.com
Design No common design platform for all disciplines
Coordination and clash problems between disciplines
Revision update problems
Can not evaluate financial results of different design alternatives and change orders easily
Project Management Change management, transparency to clients
No direct link to design or estimation
No standardized processes
Managerial Reporting Issues, (Currency effects, comparison with tender,..etc.)
Coordination problems
Variation between estimation and actual costs
21.09.2012
Problems
24www.rencons.com
21.09.2012
BIM & 5D Project Management
3D VirtualDesign
4thD - Time
5thD - Cost Technology
We decided that, we need to combine all of these functions on the same platform
25www.rencons.com
Blueprint Excel 3D Modeling 5D Solution
From Excel to Digital Construction
21.09.2012 26www.rencons.com
21.09.2012
Our BIM Partner
We needed a BIM software partner which;
1- Combines 3D Design , Scheduling and Cost
2- Specifically designed and dedicated to construction industry
3- Able to work with different CAD and ERP Systems (We use SAP at holding level and 1C in Russia)
3- Understands specific needs of our company and make necessary adjustments to the program
4- Gives consultancy support for all functions
27www.rencons.com
21.09.2012 28
Road & Bridges / Tunnels &
Dams
Government Investment
Residential,Commercial &
Industrial BuildingOil & GasRailway Airports Mining
RIB iTWO® BIM ERP 5D Solution covering construction processes in AEC and EPC markets including Civil Infrastructure, Process and Energy, Manufacturing and Public Sectors
www.rencons.com
InteroperabilityAutodesk Revit, ArchiCAD, Tekla
FlexibilityWork with the design engineer of your choice
IntegrationEnd-to-End solution
21.09.2012 29www.rencons.com
30
ProposalsBudgets
Estimates
Subcontracting Process
Purchasing / Procurement Officer
2
Contract Manager
Negotiation / Project Contract
Control/ Scheduling
Project Controller
3
6
Client Billing Subcontractor Payment
Change Orders
Project Manager5
4
iTWO BIM ERP 5D Solution for
Whole Lifecycle(Integration End to End)
Designer Pre-Construction
Estimator
1
CEO
21.09.2012 www.rencons.com
21.09.2012 31
• CPI – Construction Process Integration
iTWO CPIXMLBIM Portal
BIM ERP Solution
www.rencons.com
32
Customization of Connectors to ERP Systems (Phase II)Like SAP, Oracle, 1C, MS Dynamics, UFIDA, KINGDEE etc
ERP
Connector
Quotation
iTWO Bi-Directional Connection to ERP System
21.09.2012 www.rencons.com
21.09.2012 33
RenaissanceConstructioniTWO BIM ERP model-based
Strategy
Setup Team(iTWO BIM ERP
COE)
Define Processes (workflows)
3D DesignConstruction
Operation
Create Master Data
Quantities Estimating Scheduling
SimulationControl
ManagementDashboard
RIB iTWO BIM ERP Construction Process Workflow
www.rencons.com
21.09.2012 www.rencons.com 34
Project Kick-off
1
2
Project Scoping 5
4
6
3
iTWO Installation
RC iTWO Roll-out Process
Master Data Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RCData: tests &
system acceptance
End User Training -
Project end
CAD / QTO
Functional Implementation Workflow
21.09.2012 www.rencons.com 35
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO
InstallationMaster Data
Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RC Data: tests &
system acceptance
End User Training -
Project end
Project start-up & set-up Establish project charter
Define roles & responsibilities Project owner at site management level
Implementation & resource timeline
Reporting channel & means
KPIs & monitoring
Change requests01.04.2012
Project Team – Total 19 people
21.09.2012 36
1- 3D Design Team
- Total of 10 people
- 1 Design Coordinator- 3 Architects- 2 Structural Engineers- 2 Mechanical Engineers- 2 Electrical Engineers
- Sample BIM Compliant REVIT Projects using work sets
- Preparation of modeling standards, families
www.rencons.com
21.09.2012 37
2- Technical Office & Planning Team
- Total of 6 people
- 2 Civil Cost Engineers - 1 Electrical Cost Engineer - 1 Mechanical Cost Engineer- 1 Architect - 1 Planner
- Tender Budget and Execution Budget Templates
- Preparation of Catalogues (Commodity, Cost Code, Assemblies..etc.)
Project Team
www.rencons.com
21.09.2012 38
3- ERP Integration Team
- Total of 3 people
- 1 Project Manager - 1 ERP Liaison - 1 IT Liaison
Project Team
www.rencons.com
21.09.2012 www.rencons.com 39
ProjectKick-off
1
2
ProjectScoping 5
4
6
3iTWO
InstallationMaster Data
Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RCData: tests &
system acceptance
End User Training -
Project end
Define blueprint workflows ‘As-is’ business workflow
‘To-be’ business workflow with iTWO
Define localization development Based on blueprints
Third part system inputs
21.09.2012 www.rencons.com 40
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO Installation
Master Data Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RC Data: tests &
system acceptance
End User Training -
Project end
Create IT landscape structure for iTWO
iTWO Installation Server
User
Train iTWO Admins Installation and updates/upgrades
Security & integration to IT environment
21.09.2012 www.rencons.com 41
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO
InstallationMaster Data
Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RC Data
EnvironmentFine-tuning RC Data: tests &
system acceptance
End User Training -
Project end
Understand iTWO in all phases Bidding (pre-contract)
Contract (pre-contract)
Execution (post-contract)
RIB iTWO 5D “Quick Win”
21.09.2012 www.rencons.com 42
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO
Installation Master Data Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RCData: tests &
system acceptance
End User Training -
Project end
Project Catalogue – Creation Master Data Project templates (formulas, reports)
BoQ (Converter)
Cost codes
Commodities
Assemblies
Schedule: December 2012
21.09.2012 www.rencons.com 43
Project Kick-off
1
2
Project Scoping 5
4
6
3iTWO
InstallationMaster Data
Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
Environment
End User Training -
Project end
Customization Global settings
System options
Authorizations /Profiles
Key figures & variables for additional needs
Schedule: December 2012
Development Additional connectors (third part systems)
New functions
Schedule: December 2012 & June 2013
21.09.2012 www.rencons.com 44
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO
InstallationMaster Data
Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RC Data
EnvironmentFine-tuning RCData: tests &
system acceptance
End User Training -
Project end
Use real data for all phases Bidding (pre-contract)
Contract (pre-contract)
Execution (post-contract)
Schedule: December 2012
21.09.2012 www.rencons.com 45
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO
InstallationMaster Data
Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RC Data: tests &
systemacceptance
End User Training -
Project end
Adjusting Master/project catalogue data Estimating resources (cost codes,…)
Configuration and process integration
Adjusting system customization Global settings
System options
Authorization
Schedule: December 2012
21.09.2012 www.rencons.com 46
ProjectKick-off
1
2
Project Scoping 5
4
6
3iTWO
Installation Master Data Creation
Key User Training
7
89
Customization
Training Key User on
Finalised RCData
EnvironmentFine-tuning RCData: tests &
system acceptance
End User Training -
Project end
Use real data for all phases Bidding (pre-contract)
Contract (pre-contract)
Execution (post-contract)
Schedule: June 2012
Project End
21.09.2012 www.rencons.com 47
3D ModelBIM information
√ Better Visualization √ Cross Checking √ Avoid Mistakes
BIM Information Model
21.09.2012 www.rencons.com 48
Project Information Model
3D Model Project Actual Information
√ Visualize Result √ Fast Evaluation √ Transparency √ Real time budget control
21.09.2012 www.rencons.com 49
iTWO 5D Simulation, Real Time Forecasting
21.09.2012 www.rencons.com 50
CHALLENGES UNTIL TODAY;
1- Organized Catalogues (Commodity, Assemblies, Cost Codes, ..etc.)
2- Company specific requirements in estimation and control
3- Motivation of qualified engineers in the project (Real Life vs. System Development)
4- Resistance within the company
5- Limited 3D Revit Knowledge of new designers