REGIONAL FREEWAY AND HIGHWAY PROGRAM
RebalancingAmerican Society of Highway Engineers
March 14, 2017© 2017, All Rights Reserved. 1
-$1,000,000,000
-$750,000,000
-$500,000,000
-$250,000,000
$0
$250,000,000
$500,000,000
$750,000,000
$1,000,000,000
2012 2014 2016 2018 2020 2022 2024 2026
2016 Cash Flow 2012 Cash Flow
$908 million surplus*
$1.3 billion improvement
Source:
ADOT and MAG Estimates, September 2016. *Contingent upon final Loop 202 ROW costs.
Improving Cash Flow © 2017, All Rights Reserved. 2
2017 2021 2026
Loop 202/South Mountain Time Savings
Loop 202/South
Mountain project
delivery
advanced from
2023 to 2019.
Programming
I-10/I-17 Spine
L-101, I-17 to
Shea Blvd
I-10, L-202 to
Riggs Rd
L-303, I-10 to
MC-85/SR-30
© 2017, All Rights Reserved. 3
I-10/Fairway
I-17/Happy
Valley
I-17/ Pinnacle
Peak
L-101, US-60 to
L-202
*For Illustration Purposes Only. Not all projects noted in illustration.
Actual sequencing dependent upon project readiness and funding availability.
TI – Traffic Interchange
HOV – Add High Occupancy Vehicle Lane
GP – Add General Purpose Traffic Lane
2017 2021 2026
Loop 202/South Mountain Time Savings
I-10/I-17 Spine
L-101, I-17 to
Shea Blvd
I-10, L-202 to
Riggs Rd
L-303, I-10 to
MC-85/SR-30
Programming
Projects currently
funded under
Proposition 400.
© 2017, All Rights Reserved. 4*For Illustration Purposes Only. Not all projects noted in illustration.
Actual sequencing dependent upon project readiness and funding availability.
TI – Traffic Interchange
HOV – Add High Occupancy Vehicle Lane
GP – Add General Purpose Traffic Lane
I-10/Fairway
I-17/Happy
Valley
I-17/ Pinnacle
Peak
L-101, US-60 to
L-202
2017 2021 2026
Loop 202/South Mountain
I-10/I-17 Spine
L-101, I-17 to
Shea Blvd
I-10, L-202 to
Riggs Rd
L-303, I-10 to
MC-85/SR-30
Programming
SR-30 Phase I*
SR-24 Phase I*
I-10, SR-85 to
Verrado Way*
L-202, I-10 to
Gilbert Rd*
L-101, I-10 to
US-60 Grand*
L-101, US-60
Grand to I-17*
I-10/Fairway
I-17/Happy
Valley
I-17/ Pinnacle
Peak
L-101, US-60 to
L-202
*For Illustration Purposes Only. Not all projects noted in illustration.
Actual sequencing dependent upon project readiness and funding availability. © 2017, All Rights Reserved. 5
Sequencing and
Scheduling Principle:No distinction between
funded Proposition 400
projects and recommended
rebalanced projects.
ALL PROJECTS
COMPETE FOR ONE
RFHP CASH FLOW.
TI – Traffic Interchange
HOV – Add High Occupancy Vehicle Lane
GP – Add General Purpose Traffic Lane
© 2017, All Rights Reserved. 6Funded Project Starts
I-10/Fairway Dr TI
FY 22 → FY 18 (+4 yrs)
Loop 303, MC-85 to I-10
(New Freeway)
FY 23 → FY 20 (+3 yrs)
I-17/Central Ave TI
FY 25 → FY 19 (+6 yrs) I-17, I-10 Split to
Thomas Rd (HOV, TI)
FY 25 → FY 24 (+1 yrs)
Loop 101, I-17 to SR-51
(GP)
FY 22 → FY 19 (+3 yrs)
Loop 101, SR-51 to
Pima Rd (GP)
FY 2020
Loop 101, Pima Rd to
Shea Blvd (GP)
FY 20 → FY 21 (-1 yr)
I-10, Sky Harbor West
Traffic Interchange
FY 25 → FY 23 (+2 yrs)
I-10, I-17 Split to
Loop 202 (GP, TI)
FY 2019
Loop 101, US-60 to
Loop 202 (GP)
FY 2023
I-10, Loop 202 to
Riggs Rd (GP, HOV)
FY 21 → FY 25 (-4 yrs)
TI – Traffic Interchange
HOV – Add High Occupancy Vehicle Lane
GP – Add General Purpose Traffic Lane
I-17/Happy Valley Rd
Traffic Interchange
FY 22 → FY 18 (+4 yrs)
I-17/Pinnacle Peak Rd
Traffic Interchange
FY 22 → FY 18 (+4 yrs)
I-17/Indian School Rd TI
FY 22 → FY 24 (-2 yrs)
I-17/Camelback Rd TI
FY 22 → FY 20 (+2 yrs)
© 2017, All Rights Reserved. 7Rebalanced Project Starts
I-17, North of
Anthem Way (GP)
FY 2020
I-10, SR-85 to
Verrado Way (GP, TI)
FY 2019
Loop 303, Northern Ave
to Olive Ave (TI)
FY 2022
Loop 303,
Happy Valley Rd to
Lake Pleasant Pkwy (GP)
FY 2019
US-60/Grand Ave,
Greenway Rd to
Thunderbird Rd (FR)
FY 2018
US-60/Grand Ave, 35th
Ave/Indian School Rd TI
FY 2025
Loop 101, 75th Ave
to I-17 (GP)
FY 2021
SR-30, Loop 303 to
Loop 202
ROW FY 2022,
Construct FY 2025
Loop 202/Lindsay Rd TI
FY 2021
SR-24, Ellsworth Ave to
Ironwood Dr (Phase 1)
FY 2020
Loop 202, Gilbert Rd
to I-10 (GP)
FY 2023
Loop 202, Gilbert Rd to
SR-24 (HOV)
FY 2021
TI – Traffic Interchange
HOV – Add High Occupancy Vehicle Lane
GP – Add General Purpose Traffic Lane
© 2017, All Rights Reserved. 8Recommended RFHP Projects and Schedule
18
18
19
1919
18
18
20 20
21
21
23
23
24
20
19
19
20
21
21
21
22
24
ROW 22
BUILD 25
25
OPEN 2019 23
25
Under Construction
Start by 2022*
Start after 2022
XX Fiscal Year of Construction
© 2017, All Rights Reserved. 9Recommended RFHP Projects and Schedule
18
18
1919
20 20
21
21
23
23
24
20
19
19
20
21
21
22
ROW 22
BUILD 25
OPEN 2019 23
25
Under Construction
Start by 2022*
Start after 2022
19
25 24
21
18
18
XX Fiscal Year of Construction
Next Steps
Funded Projects:
Will be part of the draft
Transportation Improvement
Program (TIP) and Regional
Transportation Plan (RTP) for TPC
action next month.
Rebalanced projects (e.g., SR-24, SR-
30, etc.):
Additional scheduling and financing
study to refine project start dates for
TPC action this Summer.
© 2017, All Rights Reserved. 10
1
13
4
56
7
8
9
13
14
15
15
12
17
18
19
19
21
10
10
2224
24
27
28
29
29
30
31
32
33
34
35
36
37
38
39
40
I-17 at Loop 303
Finish System Interchange
SR-24, Ellsworth Ave to
Ironwood Dr, Final Freeway
Construction
SR-24 at Loop 202
Finish System InterchangeLoop 303, SR-30 to Riggs Rd
ROW Protection
SR-74, US-60 to Loop 303
ROW Protection
SR-30, Loop 303 to SR-85
ROW, Phase I Roadway
SR-30, Loop 303 to Loop 202
Final Freeway Construction
US-60, Loop 101 to I-10
Additional Grade Separations
SR-51, Shea Blvd to Loop 101
Add Lanes
Loop 202 at Mesa Dr, Construct
Half Interchange
US-60 at Lindsay Rd
Construct Half Interchange
Loop 202 at US-60
Construct DHOV
I-17 at Loop 101
Construct DHOV
I-17, SR-74 to Anthem Way Add
HOV Lanes
I-17, Anthem Way to New River
Rd, Add Lanes
Loop 202, Gilbert Rd (Mesa) to
Val Vista Rd, Add Lanes
0 New Construction
0 Traffic Interchange
0 ROW Protection
0 Technology
24
Continuing Deferrals © 2017, All Rights Reserved. 11
I-11/Hassayampa
New Freeway, Interstate 10 to US-93
Arizona SR-30Freeway Conversion, SR-85 to Loop 303
Add Lanes, Loop 303 to Loop 202
New Freeway, Loop 202 to I-17
Loop 303New Freeway, SR-238 to SR-30
SR-24/GatewayMeridian Rd to US-60/SR-79
Pinal North-SouthNew Freeway, SR-287 to US-60
Arizona SR-85Freeway Conversion, I-8 Interchange
Interstate 8 to Interstate 10
Loop 303Add Lanes, SR-30 to Interstate 17
Interstate 17Add Lanes, Anthem Way to Yavapai County
Interstate 10/Interstate 17 SpineAdd Lanes, Loop 202 to Loop 101
SR-238Add Lanes, Loop 303 to SR-347
SR-347Add Lanes, Maricopa to I-10
Interstate 10Add Lanes, Riggs Rd to SR-
387
SR-79Add Lanes, SR-79B (South)
to Hunt Hwy
Interstate 10/PapagoAdd Lanes, 459th Ave to Verrado Way
US-60/Grand AveCOMPASS Improvements
REPRESENTATIVE PROJECTS FOR PRESENTATION PURPOSES ONLY.Final determination will be made with the fiscally-constrained NextGen Regional Transportation Plan.
© 2017, All Rights Reserved. 12
Regional Transportation Plan Program
Interstate 10 – widen between 40th
St and Pecos Stack . . . program
amount of
$648.5 million.
Interstate 17 – no project specified;
awaiting EIS outcome . . . program
amount of
$821.6 million.
Total RTP Funding of
$1.47 billion.
© 2017, All Rights Reserved. 13
Aging Infrastructure Four Light Rail Crossings of I-17
Planning for Bicycles and Pedestrians
Issues© 2017, All Rights Reserved. 14
Technology Constrained Corridor Increasing Demand
Issues© 2017, All Rights Reserved. 15
Improves safety by modernizing interstates to
current design standards.
Add a minimum of one-lane throughout entire
corridor.
Expanded Managed Capacity operation along:
Interstate 10, from Interstate 17 to US-60;
and
Interstate 17, from Interstate 10 Split to
Loop 101.
Improve/reconstruct 24 of the 31 traffic
interchanges throughout the corridor.
Add five DHOV ramps and new interchanges.
Plan and enhance bicycle/pedestrian
connections across the corridor at 20
locations including 9 new structures.
spine.azmag.gov50 Improvements in the Corridor Master Plan
3D
© 2017, All Rights Reserved. 16
I-10/SR-143/
Broadway Rd
Interchange
ImprovementsProposed interchange reconstruction to target problem areas.
-
© 2017, All Rights Reserved. 17
Interchange ImprovementsExample of a Platform Diamond Interchange concept from Redford Township, MI
I-96 (Jefferies Fwy)/US-24 (Telegraph Rd)
(Photo: Bing Maps)
© 2017, All Rights Reserved. 18
Technology
EnhancementsIllustration of connected vehicle
and transportation infrastructure
technology.
(Photo Source: USDOT Volpe Center,
Cambridge MA)
© 2017, All Rights Reserved. 19
Direct High
Occupancy
Vehicle (DHOV)
RampExample of direct high occupancy
vehicle (DHOV) ramp at 3rd
Street and I-10.
(Photo source: Google Earth.)
© 2017, All Rights Reserved. 20
Direct High
Occupancy
Vehicle (DHOV)
RampExample of direct high occupancy
vehicle (DHOV) connectors
between Loop 202 (Santan
Freeway) and I-10.
Photo Source: Google Earth.
© 2017, All Rights Reserved. 21
Bicycle/
Pedestrian
Bridge Over
FreewayExample of pedestrian bridge
over Loop 101 at 63th Avenue.
(Photo Source: ADOT)
© 2017, All Rights Reserved. 22
Light Rail
Transit CrossingValley Metro Light Rail Train
undercrossing Loop 202 (Red
Mountain Freeway) in Tempe.
© 2017, All Rights Reserved. 23
Transportation: To What End? Diversify the Economy!
© 2017, All Rights Reserved. 21
Best Driving Experience in the World – Phoenix
Waze is the world's largest community-based
traffic and navigation app.
© 2017, All Rights Reserved. 25
Bob Hazlett
602 254-6300© 2017, All Rights Reserved.
REGIONAL FREEWAY AND HIGHWAY PROGRAM
Rebalancing
26