Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Upload: nicholas-simmons

Post on 21-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Real life demonstration plant for benchmarking hydrogen

technologies

Adwin MartensWaterstofNet

Sydney, 13 October 2015

Page 2: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

WaterstofNet

Page 3: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

WaterstofNet Non profit organisation, started in 2009

Area: Belgium / Netherlands

Working close together with industry/government

Activities

Owner of 2 HRS , based upon green electricity

Facilitating projects with buses, garbage trucks, fork lifts, vessels, cars

Making roadmaps: H2-Mobility Belgium, roadmap Power to Gas

Representing Belgium within IEA HIA

Page 4: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Don Quichote Development of a New Qualititive and Innovative

concept for hydrogen out of turbine electricity

In other words:

Power to gas with different components and applications

Funded by the European JU-FCH (GA 303 411)

Page 5: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Don Quichote Starting points:

800 kW solar, 1,5 MW wind

Interested enduser in the retail sector

Hydrogen combined with logistic applications and smart grid

Page 6: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Don Quichote Phase 1:

Alkaline electrolyser, 30 Nm³/h, membrame compressor, storage 50 kg (450 bar), dispenser, fuelling forklifts

Phase 2: PEM electrolyser, 30 Nm³/h, PEM fuel cell 100 kW,

storage 50 kg (450 bar), forklifts and feed back electricity to the grid

Phase 3: Electrochemical compressor, electrochemical expander

Page 7: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Don Quichote

Page 8: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Partners

Page 9: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Phase 1: operation since 2012

Page 10: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Fuelling equipment

Page 11: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Fluctuating demand

Page 12: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Phase 1: Results Starting with 2 forklifts means limited hydrogen

demand (underutilisation):

efficiencies reduced

how to define/judge availibility

Now 12 forklifts:

efficiencies higher

availibility fuelling station > 95%

Next step:

almost full loaded HRS by additional forklifts

Page 13: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Availability

Page 14: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Phase 2

Page 15: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Phase 2: Installed 2015

Page 16: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Phase 2: Installed 2015

Page 17: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Phase 2: tests starting

Page 18: Real life demonstration plant for benchmarking hydrogen technologies Adwin Martens WaterstofNet Sydney, 13 October 2015

Conclusions Best learning is learning by doing

Dedicated/complementary partners are crucial

Efficiencies and availibility are relevant if nominal use

Every phase has its own dynamics, permits, issues

Contact: [email protected]