Page 1: RCM Applied to Achieve Best Life Cycle

Research Institute

Dr Bill Wessels PE CRE Principal Research Scientist

[email protected]

Reliability & Failure Analysis Laboratory http://rfal.uah.edu

Reliability Centered Maintenance Applied to Achieve Best Life Cycle Costs

Page 2: RCM Applied to Achieve Best Life Cycle

Research Institute

Dr Bill Wessels PE CRE Experience:

• 1975 – 1989 Tramp Engineer, mining mobile machinery & process equipment life-cycle sustainability

• 1989 – 2005 Contractor [Biomedical Devices, DoD and NASA] design-for- reliability, RCM

• 2005 – Research in design-for- reliability & life-cycle sustainability for mechanical and structural components

Credentials • BS USMA, West Point ’70 • PhD Reliability Systems Engineering, UAHuntsville ’96 • PE MechE, Pennsylvania, ‘82 • CRE, ASQ, ’96

Author – Practical Reliability engineering and Analysis for System Design and Life-Cycle Sustainment, CRC Press, 2010

SRE RAMS 2013 2

Page 3: RCM Applied to Achieve Best Life Cycle

Research Institute

Introduction

Reliability-centered maintenance serves to preserve system functionality by performing scheduled maintenance actions that prevent unscheduled system downing events during scheduled operations

RCM achieves its objective by developing an understanding of critical part failure

Understanding part failure is manifested by the ability to measure the consumed life of a critical part

Scheduled maintenance is defined by application of a risk threshold to the consumed life

SRE RAMS 2013 3

Page 4: RCM Applied to Achieve Best Life Cycle

Research Institute

RCM Roadmap

SRE RAMS 2013 4

Part Cost Objective Function· Labor Costs· Materials Costs· Overhead Costs

Logistics Downtime

Math Model

Spare Strategy

Math Model

PreventiveMaintenance Math Model

Resource Queuing

Math Model

PartReliability/Cost

Simulation

Assembly Reliability/Cost

Simulation

System Reliability/Cost

Simulation

PartFailure

Math Model

PartRepair

Math Model

Part ReliabilityLife-Cycle Affordability

Assembly ReliabilityLife-Cycle Affordability

System ReliabilityLife-Cycle Affordability

Condition Indicator

Time-to-Failure Reliability Failure

Math Model

CBM

TDM

SDMStress-Based

Reliability Failure Math Model

Single Fail MechSingle Fail Mode

f(t)

Y

E

S

Y

E

S

YES

NO

PartFailure Mode

Multiple Fail MechMultiple Fail Mode

f(s)

NO

Metric: Part Condition Indicator

Metric: Part Time in Service

Metric: Part Stress Profile

RCMDatabase

System

Subsystem

Critical Items List

Assembly

Part

ORFunctional

Failure

PartPart

RCMDatabase

Part Failure Consequences

Analysis

Perception of Part Failure

P-F Interval

Operator

Maintainer

Criticality A

nalysis

ORFailureMechanisms

FailureModes

PhysicalStress

ThermalStress

EnvironmetalStress

Change in Shape

(Strain)

Change in Geometry(Crack)

Change inMaterial Property

(Corrosion)

OR

Critical Items List

RCMDatabase

Part

FailureMechanisms

Sources

Transportation Storage Function

Operational Ambient

OR

OR

PartFailure Effects

Page 5: RCM Applied to Achieve Best Life Cycle

Research Institute

Part Reliability- Maintainability Cycle

SRE RAMS 2013 5

Page 6: RCM Applied to Achieve Best Life Cycle

Research Institute

System Downtime

SRE RAMS 2013 6

Page 7: RCM Applied to Achieve Best Life Cycle

Research Institute

Source of RCM Cost Benefit

SRE RAMS 2013 7

Part failsSystem down

Maintenance action initiated

Wor

k S

tart

s

Time

Time-to-Repair

post-Repair Logistics Downtime

pre-Repair Logistics Downtime

$Lost Opportunity

$Labor$Overhead

$Labor$Materials$Overhead

Wor

kRe

sum

es

$Labor$Overhead

$Benefit

Part failsSystem down

Maintenance action initiated

Wor

k S

tart

s

Wor

kRe

sum

es

$Labor$Overhead

$Labor$Materials$Overhead

Time

Time-to-Repair

post-Repair Logistics Downtime

pre-Repair Logistics Downtime

$Lost Opportunity

Total Downtime

$Labor$Overhead

Page 8: RCM Applied to Achieve Best Life Cycle

Research Institute

Top Level RCM Path Develop a rank ordered critical items list – CIL Perform reliability failure analysis to identify:

• Sources of failure mechanisms (Conditions of use) • Failure mechanisms action on the critical part (Cause of

part failure) • Failure modes (Damage to part) • Failure effects – part (Symptoms of the damage) • Failure effects – assembly (Consequences of part

failure)

Select appropriate RCM Path • CBM • TDM • SDM

SRE RAMS 2013 8

Page 9: RCM Applied to Achieve Best Life Cycle

Research Institute

Condition-Based Maintenance CBM

Consumed life characterized by a condition that defines the failure mode/damage • Change in shape • Change in geometry • Change in material properties

Method for investigating the damage, NDI • Visual inspection of condition indicator • Manual measurement of condition indicator • Sensor measurement of condition indicator

Metrics that characterize the damage Risk Threshold

SRE RAMS 2013 9

Page 10: RCM Applied to Achieve Best Life Cycle

Research Institute

Notional Linear CBM Concept

SRE RAMS 2013 10

Page 11: RCM Applied to Achieve Best Life Cycle

Research Institute

Notional CBM Concept

SRE RAMS 2013 11

Page 12: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 12

Page 13: RCM Applied to Achieve Best Life Cycle

Research Institute

Decreasing Condition Indicator

SRE RAMS 2013 13

Page 14: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 14

Page 15: RCM Applied to Achieve Best Life Cycle

Research Institute

Diverging Condition Indicator

SRE RAMS 2013 15

Page 16: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 16

Page 17: RCM Applied to Achieve Best Life Cycle

Research Institute

Diverging Condition Indicator

SRE RAMS 2013 17

Page 18: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 18

Page 19: RCM Applied to Achieve Best Life Cycle

Research Institute

Converging Condition Indicator

SRE RAMS 2013 19

Page 20: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 20

Page 21: RCM Applied to Achieve Best Life Cycle

Research Institute

Converging Condition Indicator

SRE RAMS 2013 21

Page 22: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 22

Page 23: RCM Applied to Achieve Best Life Cycle

Research Institute

Fatigue Condition Indicator

SRE RAMS 2013 23

Page 24: RCM Applied to Achieve Best Life Cycle

Research Institute

Fatigue Condition Indicator

SRE RAMS 2013 24

Page 25: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 25

Page 26: RCM Applied to Achieve Best Life Cycle

Research Institute

Step Condition Indicator

SRE RAMS 2013 26

Page 27: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 27

Page 28: RCM Applied to Achieve Best Life Cycle

Research Institute

Step Condition Indicator

SRE RAMS 2013 28

Page 29: RCM Applied to Achieve Best Life Cycle

Research Institute SRE RAMS 2013 29

Page 30: RCM Applied to Achieve Best Life Cycle

Research Institute

Notional Attribute CBM Concept

SRE RAMS 2013 30

Page 31: RCM Applied to Achieve Best Life Cycle

Research Institute

Time Directed Maintenance, TDM

Consumed life characterized by time in service, but…

Single failure mechanism with single failure mode

Failure mode correlated to operating time

SRE RAMS 2013 31

Page 32: RCM Applied to Achieve Best Life Cycle

Research Institute

Time-to-Failure Data

SRE RAMS 2013 32

Page 33: RCM Applied to Achieve Best Life Cycle

Research Institute

Time-to-Failure Histogram

SRE RAMS 2013 33

Page 34: RCM Applied to Achieve Best Life Cycle

Research Institute

Fit Data to 3-Parameter Weibull Median Ranks Regression

First: Fit the 2-Parameter Weibull

Then: Select a value for the location parameter, g

• Choose the mid-time between 0 and Tmin

• Calculate Xg = Xi – g

• Calculate r2 for Xg & Y

If: r2 for Xg < r2 for the 2-Parameter Weibull, use the 2-Parameter Weibull

If: r2 for Xg > r2 for the 2-Parameter Weibull,

fit the 3-Parameter Weibull

SRE RAMS 2013 34

Page 35: RCM Applied to Achieve Best Life Cycle

Research Institute

Fit Data to 2-Parameter Weibull Median Ranks Regression

SRE RAMS 2013 35

Page 36: RCM Applied to Achieve Best Life Cycle

Research Institute

2-P Weibull Median Ranks Regression

SRE RAMS 2013 36

Page 37: RCM Applied to Achieve Best Life Cycle

Research Institute

2-P Weibull Median Ranks Regression

SRE RAMS 2013 37

Page 38: RCM Applied to Achieve Best Life Cycle

Research Institute

TTF Location Parameter, g

SRE RAMS 2013 38

Page 39: RCM Applied to Achieve Best Life Cycle

Research Institute

TTF Location Parameter, g

SRE RAMS 2013 39

Page 40: RCM Applied to Achieve Best Life Cycle

Research Institute

3-P Weibull Failure Math Model - TTF

SRE RAMS 2013 40

Page 41: RCM Applied to Achieve Best Life Cycle

Research Institute

3-P Weibull Failure Math Model

SRE RAMS 2013 41

Page 42: RCM Applied to Achieve Best Life Cycle

Research Institute

Failure Math Model pdf – f(t)

SRE RAMS 2013 42

Page 43: RCM Applied to Achieve Best Life Cycle

Research Institute

Risk Threshold & Hazard Function

SRE RAMS 2013 43

Page 44: RCM Applied to Achieve Best Life Cycle

Research Institute

Risk Threshold Logic

SRE RAMS 2013 44

Page 45: RCM Applied to Achieve Best Life Cycle

Research Institute

Part Alternatives Hazard Functions & Risk Threshold

SRE RAMS 2013 45

Page 46: RCM Applied to Achieve Best Life Cycle

Research Institute

Parts Alternatives Risk-based Scheduled Maintenance Interval, SMI

SRE RAMS 2013 46

Page 47: RCM Applied to Achieve Best Life Cycle

Research Institute

Exponential v Weibull Failure Math Models

SRE RAMS 2013 47

Page 48: RCM Applied to Achieve Best Life Cycle

Research Institute

Exponential v Weibull Hazard Function w/Risk Threshold

SRE RAMS 2013 48

Page 49: RCM Applied to Achieve Best Life Cycle

Research Institute

Time-to-Repair Data

SRE RAMS 2013 49

Page 50: RCM Applied to Achieve Best Life Cycle

Research Institute

Time-to-Repair Histogram

SRE RAMS 2013 50

Page 51: RCM Applied to Achieve Best Life Cycle

Research Institute

3-P Weibull Failure Math Model

SRE RAMS 2013 51

Page 52: RCM Applied to Achieve Best Life Cycle

Research Institute

Repair Math Model

SRE RAMS 2013 52

Page 53: RCM Applied to Achieve Best Life Cycle

Research Institute

LDT Math Model - Baseline

SRE RAMS 2013 53

Page 54: RCM Applied to Achieve Best Life Cycle

Research Institute

pre-Repair LDT Math Model

SRE RAMS 2013 54

Baseline

Page 55: RCM Applied to Achieve Best Life Cycle

Research Institute

post-Repair LDT Math Model

SRE RAMS 2013 55

Baseline

Page 56: RCM Applied to Achieve Best Life Cycle

Research Institute

pre-Repair LDT Math Model

SRE RAMS 2013 56

Page 57: RCM Applied to Achieve Best Life Cycle

Research Institute

post-Repair LDT Math Model

SRE RAMS 2013 57

Page 58: RCM Applied to Achieve Best Life Cycle

Research Institute

Deterministic Reliability, Maintainability & Availability

SRE RAMS 2013 58

Page 59: RCM Applied to Achieve Best Life Cycle

Research Institute

Reliability Simulation Inputs

SRE RAMS 2013 59

Page 60: RCM Applied to Achieve Best Life Cycle

Research Institute

Baseline Maintenance Labor Inputs

SRE RAMS 2013 60

Page 61: RCM Applied to Achieve Best Life Cycle

Research Institute

PM Maintenance Labor Inputs

SRE RAMS 2013 61

Page 62: RCM Applied to Achieve Best Life Cycle

Research Institute

Maintenance Costs Inputs

SRE RAMS 2013 62

Page 63: RCM Applied to Achieve Best Life Cycle

Research Institute

Part Life-Cycle Simulation Factors

SRE RAMS 2013 63

Page 64: RCM Applied to Achieve Best Life Cycle

Research Institute

Baseline Reliability Simulation Report

SRE RAMS 2013 64

Simulation Report for Part 1 Baseline

Results from 259 runs of sim time 40000-hrs

Part 1 Minimum Mean Maximum St.Dev 95% CL SEM 95% CL

Availability 0.98984 0.99051 0.99137 0.00030 0.99002 0.00002 0.99048

MTBF 628.51 683.68 734.35 19.74 651.09 1.23 681.65

MDT 6.32 6.54 6.80 0.08 6.68 0.005 6.55

MMT 1.67 1.76 1.88 0.03 1.81 0.002 1.76

LDT 4.79 4.86 4.79

System Failures 54 58.00 63 1.66 0.10 58.17

Page 65: RCM Applied to Achieve Best Life Cycle

Research Institute

PM Reliability Simulation Report

SRE RAMS 2013 65

Simulation Report for Part 1 - PM

Results from 259 runs of sim time 40000-hrs

Part 1 Minimum Mean Maximum St.Dev 95% CL SEM 95% CL

Availability 0.99305 0.99328 0.99342 0.00006 0.99318 0.000004 0.99328

MTBF 467.32 467.43 467.49 0.03 467.38 0.00 467.42

MDT 3.10 3.16 3.27 0.03 3.73 0.00 3.16

MMT 0.75 1.71 2.38 0.04 1.78 0.00 1.71

LDT 0.83 1.40 2.19 1.95 1.45

System Failures 85 85 85

Page 66: RCM Applied to Achieve Best Life Cycle

Research Institute

Reliability Simulation Summary

SRE RAMS 2013 66

Page 67: RCM Applied to Achieve Best Life Cycle

Research Institute

Labor, Materials, Overhead & Lost Opportunity Costs Table

SRE RAMS 2013 67

Page 68: RCM Applied to Achieve Best Life Cycle

Research Institute

Engineering Economics Basics

SRE RAMS 2013 68

,

0

, ,

1 1

1

n

i t

t

t

i t i t t

NPV PV

iPV A

i i

1

1 1

n

eqv n

i iA NPV

i

Page 69: RCM Applied to Achieve Best Life Cycle

Research Institute

Economic Analysis Expensed Costs &

Lost Opportunity Costs

SRE RAMS 2013 69

Page 70: RCM Applied to Achieve Best Life Cycle

Research Institute

Part Uniform Recurring Equivalent Cost

SRE RAMS 2013 70

DetMean Det95%CL BSimMean BSim95%CL PMSimMean PMSim95%CL

A(CICC+Event) -$335 -$490 -$332 -$348 -$425 -$432

A(CExp+LostOp) -$2,118 -$3,816 -$2,090 -$2,239 -$1,452 -$1,747

Page 71: RCM Applied to Achieve Best Life Cycle

Research Institute

Part Operational Availability

SRE RAMS 2013 71

Baseline RCM

Part AO 0.99051 0.99328

Page 72: RCM Applied to Achieve Best Life Cycle

Research Institute

Stress-Directed Maintenance, SDM

Consumed life characterized by applied stress profile

Measures failure mechanisms acting on part

Not well developed for use by practioner

SRE RAMS 2013 72

Page 73: RCM Applied to Achieve Best Life Cycle

Research Institute

SDM - The Present – Static Loading

SRE RAMS 2013 73

sop sdesign g

f (s) 1

f e

s

s s

s

95%LCLStrength

h(x)

x

1

( )x

h x

g

r

xr

Page 74: RCM Applied to Achieve Best Life Cycle

Research Institute

SDM - The Future - Wearout

SRE RAMS 2013 74

Page 75: RCM Applied to Achieve Best Life Cycle

Research Institute

Summary

RCM yields definition of scheduled maintenance interval for critical parts

RCM measures part consumed life constrined by a risk threshold

RCM metrics: • CBM – Condition indicator

• TDM – Time in service

• SDM – Stress load profile

SRE RAMS 2013 75