rcac 09sep 10 escorts 197 ... • response vessel of opportunity training: – 23–28 sep: cordova...
TRANSCRIPT
9/15/10
1
Valdez Operations
PWS RCAC Board Meeting September 16-17, 2010
● HSE: Safety/Spill Stats ● Projects ● Operations, incl. Prevention ● Preparedness for Response
Valdez Operations
9/15/10
2
HSE
Safety As of 31 Aug 2010
Days Away From Work Cases 0
Recordable 1
Environment As of 31 Aug 2010
Spill Volume (Gallons) 3.04 Number of Spills 8
Projects • VMT Operations (OM&S & Marine)
– IWWS System: Work continues • VMT Utilities (BWT & P/V)
– BWT Renovation Continues: • DAF Cell renovation: in progress – • NPDES Permit renewal: Application under review by EPA
• SERVS Operations – Prince Wm Snd Comms System Upgrades:
• Work at Reef Island is underway.
• 31 Oct 2010: “End Construction” Target
9/15/10
3
Operations incl. Prevention 2010 As of
31 August 2010
Tankers Loaded 188
Tanker Escorts 197
Barrels Loaded 137 MM
Since Start-up As of 31 August 2010
Tankers Loaded 20,301 Tanker Escorts 11,486 Barrels Loaded 15,600 MM
Operations / Prevention
• SERVS Operations • 38 Non-Emergency Tanker Assists:
– Maintaining 6 knots in the Narrows
• 0 Emergency Tanker Assist: • 12 Tether Exercises Conducted • 6 Towing Exercises conducted in 2010.
– 2 More planned
9/15/10
4
Operations Preparedness for Response
• C-Plan: • VMT Plan rewrite ongoing
• Drills & Exercises • 21 Apr: VMT C-Plan Scenario 4 • 7-10 Jun: PWS C-Plan SeaRiver Drill • 23 Jul: ADEC No Notice Call Out Drill • 6 Oct: VMT C-Plan Scenario 4 (continued from spring) • Response Vessel of Opportunity Training:
– 23–28 Sep: Cordova
Questions?