ramses project technical aspectsdperrin rsoc september 17, 2003 ramses project status report -...
Post on 18-Dec-2015
224 views
TRANSCRIPT
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES ProjectRAMSES ProjectStatus report - Technical aspectsStatus report - Technical aspects
RAMSES ProjectRAMSES ProjectStatus report - Technical aspectsStatus report - Technical aspects
Presented by D. Perrin (TIS/RP)Presented by D. Perrin (TIS/RP)
on behalf of the RAMSES teamon behalf of the RAMSES team
(ST/MA, TIS/IE & TIS/RP)(ST/MA, TIS/IE & TIS/RP)
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
• The RAMSES will provide LHC, and finally CERN, with an integrated The RAMSES will provide LHC, and finally CERN, with an integrated RARAdiation diation MMonitoring onitoring SSystem for the ystem for the EEnvironment and nvironment and SSafety afety covering acquisition, transmission, logging and display for the LHC covering acquisition, transmission, logging and display for the LHC machine, LHC experiments and experimental areas.machine, LHC experiments and experimental areas.
• TIS will exploit this system to assess radiation risks and to control TIS will exploit this system to assess radiation risks and to control the release of radioactivity.the release of radioactivity.
• The system will also be incorporated into the accelerator and The system will also be incorporated into the accelerator and experiment control rooms.experiment control rooms.
• The mandate of the project team covers the system specification, The mandate of the project team covers the system specification, prototyping, tendering, installation and integration of radiation prototyping, tendering, installation and integration of radiation monitors and monitors and industrial control equipment for safety systemsindustrial control equipment for safety systems..
RAMSES ProjectRAMSES ProjectRAMSES ProjectRAMSES Project
Mandate / ScopMandate / Scopee
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES ProjectRAMSES ProjectRAMSES ProjectRAMSES Project
Major functionsMajor functions Monitoring radiation variables (real-time)Monitoring radiation variables (real-time)
Measurement of dose rates during LHC operation around the accelerator, in experimental areas and their annexes, on the surface and in the environment (prompt radiation)
Measurement of radioactivity in released gases and fluids (radioactive nuclides)
Measurement of induced activity during LHC stop/shutdown
Generation of local radiation alarms and transmission of Generation of local radiation alarms and transmission of remote alarmsremote alarms
Generation of interlocksGeneration of interlocks Long term data storageLong term data storage
Measured values Events (radiation alarms, technical alarms, system faults, etc) System configuration
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES ProjectRAMSES ProjectRAMSES ProjectRAMSES Project
Major Major requirements and constraintsrequirements and constraints
LHC design (strong dependency)LHC design (strong dependency) Distributed Radiation Monitoring networkDistributed Radiation Monitoring network Flexible and modular design for easy configurationFlexible and modular design for easy configuration Integrated software infrastructure (control rooms and Integrated software infrastructure (control rooms and
networks)networks) Operational 24/24 hours a day, 365/365 days per yearOperational 24/24 hours a day, 365/365 days per year Industrial componentsIndustrial components
State-of-the-art radiation monitors and monitoring stations.
International standards for radiation protection International standards for radiation protection instrumentationinstrumentation
Valid for the replacement of the current radiation monitoring Valid for the replacement of the current radiation monitoring system (ARCON)system (ARCON)
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES ProjectRAMSES ProjectRAMSES ProjectRAMSES Project
Mandate / ScopMandate / Scopee
The radiological safety of the LHC will be ensured by the on-The radiological safety of the LHC will be ensured by the on-line measurement from aboutline measurement from about 350 radiations monitors 350 radiations monitors of of 15 different types 15 different types spread over the 8 access points, both spread over the 8 access points, both surface and underground installations.surface and underground installations.
Radiation monitorsRadiation monitors
The choice and position of the radiation The choice and position of the radiation monitors depend on: monitors depend on: - Quantities to detect;- Quantities to detect;- LHC Design (strong dependency);- LHC Design (strong dependency);- Monte-Carlo simulations;- Monte-Carlo simulations;- Extensive professional experience in RP;- Extensive professional experience in RP;
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
Stray radiation monitoring station: Stray radiation monitoring station: (x 13) Gamma and muons monitor [EPIC]; Neutrons monitor [ERC];
Ventilation monitoring station (Emissions): Ventilation monitoring station (Emissions): (x 18) Gas monitor [VGM]; Aerosol sampler [VAS];
Water monitoring station (Effluents): Water monitoring station (Effluents): (x 9) Release water monitor [RWM]; Release water sampler [RWS];
Radiation MonitorsRadiation MonitorsInventoryInventory
Radiation MonitorsRadiation MonitorsInventoryInventory
For the Environment For the Environment 11/2/2
Ventilation flow;
Water discharge flow;
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
Radiation MonitorsRadiation MonitorsInventoryInventory
Radiation MonitorsRadiation MonitorsInventoryInventory
For the Environment For the Environment 2/22/2
Meteorological data :Meteorological data :((wind speed, wind direction, atmospheric stability classwind speed, wind direction, atmospheric stability class) :) :
Ultrasound anemometer [USA]; (x 5)
Samples from the environment :Samples from the environment : Environmental aerosol sampler [EAS]; (x 4)
Conventional parameters in released water Conventional parameters in released water (x 9) pH; Temperature Conductivity Turbidity Flow rate
Non-ionising radiation fields Non-ionising radiation fields (x 13) Electromagnetic fields
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
For radiation protectionFor radiation protection
Radiation MonitorsRadiation MonitorsInventoryInventory
Radiation MonitorsRadiation MonitorsInventoryInventory
LHC accelerator and experimental areas :LHC accelerator and experimental areas : Area REM-counter monitor [ARC]; (x 17) Area Gamma dose rate monitor [AGM]; (x 2) Area Mixed field radiation monitor [AMF]; (x 10) Tunnel Gamma dose rate monitor [TGM]; (x 15) Tunnel Mixed field radiation monitor [TMF]; (x 7) X rays monitor [XRM]; (x 6) Induced activity monitor [IAM]; (x 151)
Other monitors & equipment :Other monitors & equipment : Hand&Foot monitor [HFM]; (x 8) Site Gate monitor [SGM]; (x 5) Tools & material controller [PCM]; (x 18) Alarm radiation display [PAD]; (x 40)
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
EAS
EPIC+
ERC
VENTILATIONSTATIONS
VENTILATIONSTATION
USASGM
Rack
ARC
ARC
WATERSTATION
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
C5.L5C7.L5C6.L5 C4.L5 C3.L5 C2.L5 C1.L5
R541R532 R542
All PMILxxxx monitors are of the IAM type
Rack PYMR01=USC55
PMIL5311
PMIL5313PMIL5314 PMIL5312
PMIL5412
PMIL5315
PMIL5411
(- 253000)(- 190500) (- 150000) (- 142450)
(- 83500) (- 56500) (- 31000)
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
R561 R562 R571
RR57
R572
C5.R5C4.R5C3.R5C2.R5C1.R5 C6.R5 C7.R5
UJ57
UJ56
All PMILxxxx monitors are of the IAM type
PMIL5611 PMIL5711
PMIL5712 PMIL5713 PMIL5714 PMIL5715
PMIL5612(+ 31000) (+ 56500) (+ 83500)
(+ 142450) (+ 150000) (+ 190500) (+ 253000)
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
CMS
TGMTGM TMF TGM
ARC
ARC
ARC
ARC
PAD
PAD (ground floor)
PAD
PAD PAD (1rst floor)
PCMPCM
PCM
PAD = Alarm Display
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
All PMILxxxx monitors are of the IAM type
PMIL5521 PMIL5522PMIL5511 PMIL5513PMIL5501
PMIL5502 PMIL5512 PMIL5514
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
RAMSES RAMSES Installation example atInstallation example at
LHC point 5LHC point 5
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
(For surface and underground installations)
Integration in the LHC ProjectIntegration in the LHC Project Reservation of space for radiation monitors (PSIWG, ST/CV)Reservation of space for radiation monitors (PSIWG, ST/CV)
~ 350 radiations monitors~ 350 radiations monitors (~ 50 non-RP monitors);(~ 50 non-RP monitors); Reservation of space for associated electronics (PSIWG)Reservation of space for associated electronics (PSIWG)
24 racks equivalent (30 locations);24 racks equivalent (30 locations); Evaluation of cabling needs (ST/EL)Evaluation of cabling needs (ST/EL)
~ 60 km (~30 km for Induced Activity Monitors);~ 60 km (~30 km for Induced Activity Monitors); Evaluation of powering needs (ST/EL)Evaluation of powering needs (ST/EL)
< 25kVA;< 25kVA; Network communication (TCP/IP)Network communication (TCP/IP)
Requests underway through CEIWG (~200 connections);Requests underway through CEIWG (~200 connections); Preliminary planning of installation and EVM Preliminary planning of installation and EVM (~(~ 100100 work units)work units);;
RAMSES RAMSES Monitoring hardware Monitoring hardware
infrastructureinfrastructure
RAMSES RAMSES Monitoring hardware Monitoring hardware
infrastructureinfrastructure
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES RAMSES Integration in the LHC ProjectIntegration in the LHC Project
RAMSES RAMSES Integration in the LHC ProjectIntegration in the LHC Project
Induced Activity Monitor [IAM]
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES RAMSES Integration in the LHC ProjectIntegration in the LHC Project
RAMSES RAMSES Integration in the LHC ProjectIntegration in the LHC Project
PX15
AMF+
PAD
PAD
PCM
ARC
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES Project
Fully redundant serverCentralises data coming from the stationsStores the data in the database (measured values, alarms, configurations)Surveys the correct operation of the RAMSES (technical alarms)Acts as server for the different HCI of the system (real-time and historic data)Integrates RAMSES into CERN control infrastructure
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES Project
CERN will use Data Exchange Module to integrates RAMSES in the LHC control infrastructure:
Transfer radiation alarms to the LHC control room (CAS)Transfer technical alarms to the TCR (CAS)Provide displays for radiation monitoring in the LHC control roomProvide displays for monitoring conventional parameters in water releases (for TCR)Sharing measured values with external system (e.g. LHC Experiences…)
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
20042004 20052005 20062006 20072007 20082008 2009200920012001 20022002 20032003
Installation and calibration Installation and calibration
Commissioning Commissioning
Minimum time before LHC 1st beam Minimum time before LHC 1st beam
Production by industry Production by industry
Qualification of InstrumentationQualification of Instrumentation
Development by industry Development by industry
Procurement procedure Procurement procedure
Evaluation & Specifications Evaluation & Specifications
RF test 4RF test 4thth quarter quarter
10/2001 : Project Launched10/2001 : Project Launched
7/2002 : Market Survey7/2002 : Market Survey launchedlaunched
11stst LHC beam LHC beam
Sector testSector testTI8 -> LHC-7TI8 -> LHC-7
7/2003 : Invitation to Tender7/2003 : Invitation to Tender
12/2003 : FC -> Contract12/2003 : FC -> Contract AdjudicationAdjudication
LHC Underground cables installation campaignsLHC Underground cables installation campaigns
17 September 200317 September 2003
Integration in LHCIntegration in LHC
RAMSES RAMSES StatusStatus
RAMSES RAMSES StatusStatus
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
OrganisationOrganisation
RAMSES ProjectRAMSES ProjectRAMSES ProjectRAMSES Project
Product Owner L. Evans DG (for LHC)(Maître d'Ouvrage): W. Weingarten TIS (for other CERN sites)
Product Manager P. Proudlock AC (for LHC) (Maître d'Ouvrage Délégué): H. Menzel TIS (for other CERN sites)
Project Owner: H. Menzel TIS(Maître d'Oeuvre)
Project Leader: L. Scibile ST/MA (Maître d'Oeuvre Délégué)
Project Engineers‘Radiation Protection‘ : D. Forkel-Wirth TIS/RP‘Environmental Safety’: P. Vojtyla TIS/IE‘Radiation Monitors’: D. Perrin TIS/RP ‘Software Infrastructure’: G. Segura, R. Bartolome TIS/IE and ST/MA
RAMSES Project Technical Aspects DPerrin RSOC September 17, 2003
RAMSES ProjectRAMSES ProjectRAMSES ProjectRAMSES Project
Thank you for your attention !Thank you for your attention !
The project teamThe project team
Luigi Scibile
Doris Forkel-Wirth
Daniel Perrin
Pavol Vojtyla
Gustavo Segura
Roberto Bartolome