RAIL LAND DEVELOPMENT AUTHORITY

Status of Commercial Sites06.08.2018

Page 2: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites   2

PROJECT: RaxaulDATE OF ENTRUSTMENT : 30.08.2007Availability of Land Records (Yes/No) : YesSTATE: BiharRLY: ECRDIVISION: Samastipur

AREA (Ha): 1.20

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: Valuation approved. NIT target‐ June’17 end.   Bids opened on 25.08.2017,2 Bids received.  Awarded for Rs. 6.86 Crore.  LOA issued on 27.09.2017. 1st installment  (of Rs. 2.74 crore) + (interest) Rs. 3.365 cr. has been received.CONSTRAINTS/ ISSUES IF ANY: NOC issued by Nagar Parishad on 15.12.2014 subject to keeping the roads passing through the site intact. TIMELINES: REUP: ‐

VALUATION: Approved.  10.10.2009BIDDING/NIT: 25.08.2017.   (Opened)

RLDA....In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 3: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites3

PROJECT: Poornandampet (Vijaywada)DATE OF ENTRUSTMENT : 25.04.2007Availability of Land Records (Yes/No) : Yes

STATE:  Andhra PradeshRLY: SCRDIVISION: Vijayawada

AREA (sqm) 1272

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: Work started at site by Railways before opening of Bids. During last twobids in Feb 2018 & June 2018, No bids received. Site visit and discussion with LocalDeveloper with CPM/ SCB is on scheduled. The RFP shall be issued accordingly.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING:

Available13.02.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 4: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites  4

PROJECT: Maula Ali Flyover, HyderabadDATE OF ENTRUSTMENT :Availability of Land Records (Yes/No) : YesSTATE: TelenganaRLY: SCRDIVISION: Hyderabad

AREA (Ha):8.99

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: RFP document for urban designing and master planning of the land has beenissued on 02.11.2017. Scheduled date of opening 14.12.2017. 4 BIDS RECD.Three qualified, presentation of concept plan held on 31.01.2018. feedback submitted.Revised valuation submitted. N.I.T. issued on 28.02.2018. CMC report submitted.Date of bid submission – 28.08.2018. GMs Committee report submitted.

CONSTRAINTS/ ISSUES IF ANY:TIMELINES: REUP: Ist Phase ‐15.02.2018

VALUATION: Ist Phase‐ valuation‐15.02.18.      

BIDDING/NIT:LOA :

Ist Phase 28.02.201831.05.18

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 5: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites5

PROJECT: NizamabadDATE OF ENTRUSTMENT : 25.01.2008Availability of Land Records (Yes/No) : YesSTATE: TelanganaRLY:  SCRDIVISION: Hyderabad

AREA (Ha): 0.24

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: RFP issued on 16.07.2018. Bids invited with opening on 28.03.2018, revisedvide corrigendum with new date of Bid Opening as 28.08.2018.

CONSTRAINTS/ ISSUES IF ANY: Revaluation to be done as the existing valuation  is old.

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING/NIT :4. LOA:

18.02.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 6: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites6

PROJECT: GuntakalDATE OF ENTRUSTMENT : 12.05.2009Availability of Land Records (Yes/No) : Yes

STATE: A.P.RLY:SCRDIVISION: Guntakal

AREA (Ha): 0.48

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: Consultancy (Architectural) in progress. CLU recommended by municipality,the application in turn sent by T&CP dept. to state govt. for approval. Valuation willbe done after CLU. CLU under process for Comm use against RailwayLand/Use presently prescribed. Guntakal Municipal Comm. has sent proposalto Director Town & Country Panning on 11.01.2018.

CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:JGM/ Mktg.3. BIDDING:

30.05.201830.05.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 7: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites7

PROJECT: AurangabadDATE OF ENTRUSTMENT : 25.04.2007Availability of Land Records (Yes/No) : Yes

STATE: MaharashtraRLY:SCR DIVISION:  Aurangabad (Nanded)

AREA (sqm) 35127

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: Land use commercial. Earlier valuation approved . No bid receivedduring last bid invitation 31.01.2017. Valuation more than 3 year old.

Revaluation under process.CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING/ NIT :

30.01.2018.  31.05.2018.

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 8: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites8

PROJECT: Gautam Budh Institute GayaDATE OF ENTRUSTMENT : 23.02.2007Availability of Land Records (Yes/No) :STATE: BiharRLY: ECRDIVISION: Mugal Sarai

AREA (Ha): 0.57

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: The developer (M/s Amrapali Buddha Developers Pvt. Ltd.) could not

complete the 1st phase of the project in time. Notice of intention to terminate issued

on 11.05.2015 due to non completion of phase 1 by the 28.02.2015. The developer

filed the petition in High Court which has granted status Quo on notice of intention to

terminate issued till adjudication by Arbitral Tribunal. Under arbitration. Developer

has requested to RLDA for settlement out of Court which is under consideration.

CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING:

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 9: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites9

PROJECT: SilliguriDATE OF ENTRUSTMENT : 25.04.2007 (De‐entrustment June 2018)Availability of Land Records (Yes/No) :

STATE:W.B.RLY:NFRDIVISION: Katihar

AREA (Ha): 1.20 Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: Land use commercial confirmed by local authority. Earlier valuation approvedand tenders invited excluding encroachment portion. Financial bid not opened as perdirection of Rly. Bd. and bids returned unopened. CMC done.N.I.T. Issued. Bid opening date – 25.06.2018. (De‐entrustment done inJune 2018)CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING/NIT: 16.05.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 10: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites10

PROJECT: Ambedkar Circle, VishakhapattnamDATE OF ENTRUSTMENT : 23.02.2007Availability of Land Records (Yes/No) : Yes

STATE: UPRLY: ECoR (NCR)DIVISION: VSKP

AREA (Ha): 0.14

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: RFP issued. Four bids received. LoA issued on 23.07.2018 for Rs.1242.99 LakhCONSTRAINTS/ ISSUES IF ANY: Reasons for backing out by the developers have to be ascertained before rebidding. Valuation to be completed at earliest.

TIMELINES: REUP: ‐

VALUATION: To be done again. Consultant to be fixed. Target‐Dec’17

BIDDING/NIT: 12.04.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 11: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

COMMERCIAL SITESPROJECT: Delhi Sarai RohillaDATE OF ENTRUSTMENT: 23.02.2007      Availability of Land Records (Yes/No) : Yes

STATE:  DelhiRLY:  NorthernDIVISION:  Delhi

AREA (Ha): 15.27 Project Incharge: 1.DGM ‐ Sh. Jatinder Kumar2.Manager‐ None

STATUS: RLDA Board approved the valuation on 30.11.2017. NIT under Re‐development schemeissued on 30.11.2017. Pre‐Bid conference also held on 27.12.2017. e‐Bid submission was scheduledon 25.04.2018.

CONSTRAINTS/ISSUES IF ANY: (1) Shifting & vacation of staff 89 Nos. Allotment letters has beenissued by DLI divn. 39 staff has already shifted so far. Likely to be completed before BidFinalization.(2) Plan for shifting of service buildings e.g. Rly. Hospital, SSE (P.Way) Office, Store & Plan foralternate location for RPF Barrack has been approved by DLI division.(3) Technical Bids Opened on 02.05.2018, two bids received and are under evaluation

TIMELINES: REUP: Land papers Available

VALUATION: 30.11.2017 30.12.17

BIDDING/NIT: E‐Bid submission : 09.03.2018 /25.04.2018Opening : 16.03.2018/02.05.2018   31.01.18

Page 12: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

2. PROJECT: Bandra (East)DATE OF ENTRUSTMENT:    07.02.2008                                                                                           

STATE: MaharashtraRLY:  WRDIVISION: Mumbai Central

AREA (Ha):   4.3 Project Incharge:DGM‐ Sh. Jatinder Kumar

STATUS: Tender was invited & opened on 25.08.2017 but no bid was received. Revaluationapproved by RLDA Board on 02.01.2018. Bids invited on 15.01.2018 . Pre‐ Bid meetingheld on 07.02.2018 at Mumbai. E‐Bid is scheduled for submission on 28.03.2018 & Bidopening scheduled on 04.04.2018. Revised vide corrigendum with new date of BidOpening as 23.04.2018.MOU & Lease deed signed with IRCON on 26/3 & 28/3/18 respectively.

CONSTRAINTS/ISSUES IF ANY: 1. Ban on fresh construction imposed by Bombay HighCourt due to pending of dumping ground. Case is in Supreme Court & next date ofhearing is 15.3.2018.2. Presently, NOC from NMRDA for obtaining direct access from Western ExpressHighway is awaited.

TIMELINES: REUP ‐‐‐‐

Valuation: 02.01.2018.        

Bidding/ NIT: 15.01.2018.  

Page 13: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

PROJECT:   Shimla (Railway Godown below Winter Field)DATE OF ENTRUSTMENT:  03.10.2016            Availability of Land Records (Yes/No) : Yes

STATE: Himachal PradeshRLY:  NRDIVISION:  Shimla

AREA (Ha):   0.35 Project Incharge:1.DGM‐ Sh. Jatinder Kumar2.Manager‐ None

STATUS: Concept plan prepared. Financial & Marketing consultant appointed on20.01.2017. The site is coming in green zone. NOC from Shimla local authorities received.Developer fixed earlier had defaulted. His LOA has been cancelled, fresh bidsinvited opened and LOA at NPV of 11.56 Cr. issued on 17.07.2018.CONSTRAINTS/ISSUES IF ANY:   The Selected bidder sought cumulative extension of time up to 29.04.2018 (Maximum permissible under RFP) for deposit of 1st installment of Lease Premium with interest. 

TIMELINES: REUP Land Papers Available

Valuation: Available.       

Bidding/NIT:LOA:

06.10.1730.11.17 17.07.2018

Page 14: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

PROJECT:   KatraDATE OF ENTRUSTMENT:    03.09.2007       Availability of Land Records (Yes/No) : Yes                                                     

STATE: Jammu & KashmirRLY:  NRDIVISION:  Firozpur

AREA (Ha): 1.52 Project Incharge:1.DGM‐ Sh. Jatinder Kumar2.Manager‐ None

STATUS: Tender was invited & opened on 08.03.2017 but no bid was received. Fresh Bid hasbeen invited on 26.04.2018. Bids opened on 23.07.2018 are under evaluation.CONSTRAINTS/ISSUES IF ANY: (1) Katra is a very small town having a population ofapprox. 9000 only and is dependent on Pilgrimage to Mata Vaishnodevi.(2) Due to shifting of train operations from Jammu to Katra & convenient train timingsavailable to the passengers, demand for hospitality segment at Katra is reduced. Inaddition, IRCTC has budget accommodation in the station building & construction of MFCawarded by RLDA has also started. As such, Consultant was advised to give currentmarket trends and have advised that due to excess inventory of hospitality relatedaccommodation in budget segment there is no fresh demand in the market for the entireland parcel of 1.5 Ha. Therefore bid has been invited offering only 5000 Sqm of landparcel as of now which can accommodate about 75 room inventory.

TIMELINES: REUP Land Papers Available

Valuation: Completed.       23.08.16

Bidding/NIT: 15.01.18     NIT‐26.04.2018 Opening – 11.07.2018

Page 15: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

PROJECT: G.T. Road, AmritsarDATE OF ENTRUSTMENT:13‐02‐2009 Availability of Land Records (Yes/No) : Yes

STATE:  PunjabRLY:   NRDIVISION:  Firozpur

AREA (Ha):  0.59 Project Incharge:1.DGM‐ Sh. Jatinder Kumar2.Manager‐ NONE

STATUS : Bids invited twice on 24.08.2016 & 03.04.2017 but no bid received. Tenders to bere‐invited. Re‐valuation under process.

CONSTRAINTS/ISSUES IF ANY: 1. Plenty of private land is available in & around ASR so thereis very less demand of Leasehold land. Earlier demand of Hospitality sector has also nullifieddue to purchase of free hold land by the prospective developer. There is overall slowdown ofReal Estate market in ASR. CMC report for Revised valuation is being deliberated by GM’sCommittee.2. Bid will be re‐invited after approval of revised valuation.

TIMELINES: REUP:  Land Papers Available

VALUATION: 25.12.2017  

BIDDING/NIT: 20.12.17

Page 16: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

PROJECT: Bandra (E)‐IIDATE OF ENTRUSTMENT : 03.03.2016Availability of Land Records (Yes/No) : STATE: MaharashtraRLY:WRDIVISION: Mumbai Central

AREA (Ha):  0.11 Project Incharge: DGM/BD –Sh. Rakesh Kumar Gupta

STATUS CONSTRAINTS/ISSUES IF ANY: Bids were opened on 20.09.2017. Financial Bidsof both the bidders were opened on 30.10.2017. Site awarded at lease premiumof Rs. 6,51,01,099/‐ and 0.5% lease rent. Developer has deposited success fees of Rs.1.6 lakhs. First installment of Rs. 3.07 cr. received. Joint site measurement on 05.02.2018.The encroachments from the site, except 04 shops, have been removed by Rly. SelectedBidder is demanding removal of all encroachments from site. Selected Bidder hasdeposited additional sum of Rs. 1.0 Cr. on 14.06.2018 while seekingpermission for soil testing which has been granted on 26.06.2018. DATarget 17.07.2018. Soil testing report submitted by Developer. SPV approved byCompetent Authority.TIMELINES: REUP: 

VALUATION: Approved

BIDDING/NIT: 20.09.2017.  (opened) 

LOA 15.11.17

Page 17: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites 17PROJECT: On Platform Road, Bangalore CityDATE OF ENTRUSTMENT : 23.02.2007Availability of Land Records (Yes/No) :

STATE: KarnatakaRLY: SWRDIVISION: Bangalore

AREA (Ha): 1.01

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD –Sh. Rakesh Kumar GuptaManager‐

STATUS: : The developer M/s Yantti Buildcon Pvt. Ltd. did not paid 3rd & 4th installment oflease premium and obtained stay order against encashment of B.G. from city Civil Court,Bangalore. Appeal filed by RLDA against the same in Bangalore High Court which ispending. The developer claimed Rs. 145 Cr. during arbitration proceedings. At awarded Rs.97 Cr. against RLLDA. RLDA challenged. The award before High Court of Delhi Last hearingwas on 12.04.2017 Claimant side argument was held next date of hearing 19.05.2017.Agreement terminated on 08.01.2014 due to non completion of the project withinguaranteed date possession of sight taken by RLDA. Hon’ble High Court has decided thematter in favour of RLDA on 02.05.2018. Consultation for Financial & Marketing hasbeen fixed on 01.08.2018. appeal has been filed by developer in the Double bench DelhiHigh Court. Target NIT 10.08.2018CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING:

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 18: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites18

PROJECT: Ashok ViharDATE OF ENTRUSTMENT : 25.09.2007Availability of Land Records (Yes/No) :STATE: DelhiRLY: NRDIVISION: Delhi

AREA (Ha):13.2 Ha. Net Areato lease 7.29 Ha.

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD –Sh. Rakesh Kumar GuptaManager‐

STATUS: Valuation Approved by RLDA Bd on 25.05.2018 with caveatto invite the bids after resolving land title issue. Comments onlegal/finance vetting have been received on 20.06.2018.LoA has issued. No objection for re‐development of Ashok ViharColony on 01.08.2018 after incorporation of appeals suggestion offinance / legal, the RFP will be submitted for approval ofCompetent Authority. Date of NIT is 08.08.2018CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/NIT:

10.01.2018

15.05.2018 RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 19: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites19

PROJECT: Mahalaxmi, MumbaiDATE OF ENTRUSTMENT : 12.02.2014Availability of Land Records (Yes/No) :

STATE:    MaharashtraRLY: CRDIVISION:    Mumbai

AREA (Ha): 0.95 Ha

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD –Sh. Rakesh Kumar GuptaManager‐

STATUS: 1. Development Plan 2034 has been approved by MCGM but yet to beuploaded/published.2. MCGM requested to relocate proposed Homeless Shelter at one corner of the plot (notagreed for deletion). Matter taken up with MCGM & objection to the reservation hasbeen raised by RLDA.3. Valuation Tender finalized. Consultant has been asked to submit valuation report.4. Objection has been raised for removal of house less shelter on 18.06.2018.CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING/NIT: 31.08.2018

RLDA....In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 20: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites20

PROJECT: Lokmanya Tilak Terminus (LTT)DATE OF ENTRUSTMENT : 06.03.2014Availability of Land Records (Yes/No) :STATE: MaharashtraRLY: CRDIVISION: Mumbai

AREA (Ha): 10.4 Ha

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD –Sh. Rakesh Kumar GuptaManager‐

STATUS: Financial Bid was opened on 08.09.2014. Tender hasbeen discharged. LTT station is included in the list of StationRedevelopment as per Railway Board Policy. Site was demandedback by Railways.NIT for Architectural Consultancy being planned in July‐2018

CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING: 28.02.2019

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 21: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites  21PROJECT: Gwaltoli, Kanpur DATE OF ENTRUSTMENT : 30.08.2007Availability of Land Records (Yes/No) : YesSTATE: UPRLY: NER (NCR)DIVISION: Lucknow (ALD)

AREA (Ha): 1.52

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Architectural consultant fixed and report is to be finalized. Present land use isResidential. Meeting with CTCP office LKO fixed regarding land use and NOC. The site issuitable for commercial/residential development.2 Bids received and discharged due to non‐fulfillment of financial eligibility andstipulations of LDHB‐1 by the bidders. Bids re‐invited on 17.05.2018 with e‐bidsubmission by 20.06.2018 and opening on 27.06.2018. Two bids received andare in process of Evaluation. (Target LOA 16/7/2018). Bids are still in process ofEvaluation.

CONSTRAINTS/ ISSUES IF ANY: Commercial use permitted under “residential “ land use entails impactfee thereby reducing valuation of the site for 45 years period. Valuation done for 99 yearsResidential.TIMELINES: REUP: ‐

VALUATION: To be done‐21.09.17 by CMC. 30.09.17 by GM committee.15.12.17

BIDDING/ NIT: 27.03.2018RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 22: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites 22

PROJECT: Kampu Kothi, GwaliorDATE OF ENTRUSTMENT : 25.04.2007Availability of Land Records (Yes/No) : YesSTATE: MPRLY:  NCRDIVISION: Gwalior

AREA (Ha): 0.60

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Valuation approved in May 2015 for an area of 4513 sqm excluding the templearea 306 sq.m Tender opened on 17/10/2016, discharged due to low bid. Third time On7/12/17 no valid bid recd. Tender re‐invited and opened on 23.01.2018. LOA forLease Premium of Rs. 13.355 cr. issued on 19.02.2018. Selected bidder was givenextended time up to 18.07.2018 to deposit 1st installment of L.P. The bidder got failed indepositing the same by due date and thus, LoA has been cancelled on 24.07.2018 withforfeiture of Bid Security of Rs. 27.45 Lakh. Re‐bidding to be done in Aug 2018 with afterreconsideration of Guidance Value of land.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING/ NIT:

15.06.201713.12.2017

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 23: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites 23

PROJECT: Jhansi (E)DATE OF ENTRUSTMENT : 26.07.2012Availability of Land Records (Yes/No) : YesSTATE:U.P.RLY:NCRDIVISION: Jhansi

AREA (Ha): 0.66

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Consultancy (Architectural) in progress. Clarification letter to Secy. JhansiDevelopment Authority written for applicable charges for commercial developmentthrough private developer. In the Meeting with CTCP office LKO regarding land use andNOC, it was clarified that the subject land is outside jurisdiction of JDA. GMs Appraisalcommittee submitted report for Valuation. Valuation approved. RFP issuedand BID opening on 06.02.2018. Financial Bid opened on 23.02.2018. LOA forLP of Rs. 30.56 Cr issued on 14.03.2018. 1st Installment of L.P. from selectedbidder awaited.CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING/ NIT:

15.07.201715.11.1727.11.17

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 24: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites 24PROJECT: Jhansi (W)DATE OF ENTRUSTMENT : 26.07.2012Availability of Land Records (Yes/No) : YesSTATE:U.P.RLY:NCRDIVISION: Jhansi

AREA (Ha): 2.16

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Consultancy (Architectural) in progress. Clarification letter to Secy. JhansiDevelopment Authority written for applicable charges for commercial developmentthrough private developer. In the Meeting with CTCP office LKO regarding land use andNOC, it was clarified that the subject land is outside jurisdiction of JDA. Plans are to beapproved by RLDA. Valuation Report received & under process. VC Sir visited siteon 04.03.2018 and efforts being made to take extra land. Division has requestedfor joint Survey of the land. Survey Consultant has been selected and shall startthe Survey from 07.08.2018. After the completion of Survey the decision ofactual area of the site to be leased shall be taken.CONSTRAINTS/ ISSUES IF ANY: CMC report referred back by GM/BD to CMC .TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/NIT:

15.07.2017 (completed)28.02.201830.07.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 25: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites 25PROJECT: Sawai Madhopur, Near GRP Thana.DATE OF ENTRUSTMENT : 13.01.2016Availability of Land Records (Yes/No) : YesSTATE: RajasthanRLY:WCRDIVISION: Kota

AREA (Ha): 0.40

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Application for CLU submitted by REUP wing on 30.05.16. Report from SWMsent to T&CP/Kota for further action. In meeting between GM/BD and Secy. Govt. ofRajasthan, it was decided to send letter to state govt. with facts that ban on CLU by HighCourt is not applicable to railway land. The govt. will issue letter to concernedmunicipality for allowing CLU. Letter written by RLDA on 11.06.17. Bid opened on21.03.2018. LOA for L.P. of Rs. 13.5 Cr issued on 26.03.2018 extension given upto23.08.2018 for deposition of 1st installment. In compliance of order dated 21.06.2018 ofUrban Development Department, Govt. of Rajasthan the Road Network Plan has beensubmitted to UIT/SWM on 23.07.2018 by RLDA and the same has been forwarded by UITto Regional Town Planning Office – Kota on 30.07.2018 for approval.CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:JGM/SW3. BIDDING/NIT:4. LOA:

30.11.1716.12.1705.02.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 26: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites26

PROJECT: Kota (Near PF 1, Cycle stand)DATE OF ENTRUSTMENT : 13.01.2016Availability of Land Records (Yes/No) : YesSTATE: RajasthanRLY:WCRDIVISION: Kota

AREA (Ha):0.21

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Application for CLU submitted by REUP wing on 30.05.16. Proposal fromlocal authorities sent to state government. In meeting between GM/BD and Secy, govt.of Rajasthan, it was decided to send letter to state govt. with facts that ban on CLU byHigh Court is not applicable to railway land. The govt. will issue letter to concernedmunicipality for allowing CLU. Letter written by RLDA on 11.06.17. Final Valuationreport submitted by Consultant. JGM/Mktg., DGM/PI, Manager/Mktg. went for sitevisit on 07.09.2017 for Activity 4 & 5. Proposal under reexamination in light ofStation Redevelopment.CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:JGM/SW3. BIDDING/NIT:

RLDA....In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 27: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites27

PROJECT: Loco Colony, JaipurDATE OF ENTRUSTMENT : 27.02.2014Availability of Land Records (Yes/No) : Yes

STATE: RajasthanRLY:NWRDIVISION: Bikaner

AREA (Ha): 2.17

Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: CLU from “Circulation” to “Residential/Mix use” is being processed. ConcernedTown planning authority. Fin & Mktg. consultant appointed on 22.11.17 andConsultancy work under progress. Bids to be invited by 31.08.2018. RoadNetwork Plan submitted to Division by RLDA on 06.06.2018 for their consent buttheir reply is still awaited. The matter is to be examined with Re‐developmentof Loco Area Railway Staff Colony case as the entrusted site is situated in thesame area.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING/NIT: 31.08.2018

RLDA I it f E ll i C i l D l t f R il L d/Ai S

Page 28: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites28

PROJECT: Johnsganj, AjmerDATE OF ENTRUSTMENT : 27.02.2014Availability of Land Records (Yes/No) : YesSTATE: RajasthanRLY:NWRDIVISION: Ajmer

AREA (Ha): 0.86 Project Incharge: CPM/JP‐ Shri M.L. MeenaDGM/Tender ‐ Shri Neeraj Kr. GuptaManager –Abhay Kumar Thakur

STATUS: Consultant not engaged as site is suitable for residential development.GM/Jaipur & DGM/P‐I visited the site on 05.09.2017 with prospective bidders. Selectionof valuation Consultant in process. Tender for financial and marketing consultant invitedand opened on 28.12.2017. LOA issued on 02.02.2018. Evaluation Report still awaited.Bids to be invited by 25.06.2018. NIT withheld due to nearby Hazari Bagh site under bid(02.07.2018). (CMC Target 20.07.18. GM valuation committee 27.07.2018, NIT31.07.2018). Presentation of valuation was made by Consultant on 18.07.2018. Finalvaluation incorporating the suggestion of RLDA shall be made available on 08.08.2018 byConsultant.CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/NIT:

CMC Target 20/7/18  GM valuation committee 27/7/18 NIT 31/7/201825.04.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 29: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites29

PROJECT: EtawahDATE OF ENTRUSTMENT : 26.07.2012Availability of Land Records (Yes/No) : Yes

STATE:U.P.RLY:NCRDIVISION: Jhansi

AREA (Ha): 0.30

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS:    1. Architectural Consultancy work is in progress. 2.2. In the Meeting with CTCP office LKO on 22.5.17 regarding land use and NOC, it was

clarified that CLU will be required as the land is marked as railway land.3. Valuation report awaited from M/s. JLL.4. Revised CLU application submitted in the office of Housing and Town Planner,

Lucknow on 15.02.2018 and matter being pursued.5. Town planner visited the site on 16.04.2018.6. Required Land papers have been collective for Patwari & send to P. S. UP Govt.

CONSTRAINTS/ ISSUES IF ANY: Issue regarding Khasra No. is being sorted out. To be given by 3/7/18TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/NIT:

15.07.201831.07.2018.RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 30: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites30

PROJECT: Alam Bagh Diesel Shed, LucknowDATE OF ENTRUSTMENT : 07.04.2008Availability of Land Records (Yes/No) : YesSTATE: U.P.RLY:NRDIVISION: Lucknow

AREA (Ha): 0.44

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: It has been decided that the development will be taken up for the site leavingthe portion of the land under dispute. Application for CLU Submitted on 09.11.17 butas per LDA letter dated 28.12.2017 CLU is not required. Tender for financial andmarketing consultant awarded on 25.9.17 to PDMAG .The Consultant has submitted valuation report.RFP for bidding uploaded on Website. Bids invited but NIT cancelled due toongoing Court Case regarding Land.

CONSTRAINTS/ ISSUES IF ANY:  1. Addl. Land to be allotted to RLDA.  

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING/NIT: 25.04.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 31: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites31

PROJECT: Aishbagh, LucknowDATE OF ENTRUSTMENT : 07.04.2008Availability of Land Records (Yes/No) : Yes

STATE: U.P.RLY:NRDIVISION: Lucknow

AREA (Ha): 3.54

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: Existing land use “light and small industry”. NOC applied on 01.10.2018. NOCissued by LDA on 15.11.17. Applied for CLU for “Residential” use vide letter dt.16.05.2018.• Competent Authority Approved Residential use for 99 years Lease Period.•NIT of leasing out of plot invited & Bid opened on 10.07.2018•Tenders are at GMs level Committee for Evaluation.

CONSTRAINTS/ ISSUES IF ANY: CLU to be obtained. TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/NIT: 30.04.2018

Page 32: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites32

PROJECT: Hazaribagh, AjmerDATE OF ENTRUSTMENT : 27.02.2014Availability of Land Records (Yes/No) : Yes

STATE: RajasthanRLY:NWRDIVISION: Ajmer

AREA (Ha): 3.63 (orig)7.84 (Ha)

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: Existing land use ‘Residential’.Bids opened on 12.07.2018. Tenders are at GMs level Committee forEvaluation.

CONSTRAINTS/ ISSUES IF ANY: 

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING/NIT:

31.01.201815.02.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 33: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites33

PROJECT: Lalgarh, BikanerDATE OF ENTRUSTMENT : 27.02.2014Availability of Land Records (Yes/No) : YesSTATE: RajasthanRLY:NWRDIVISION: Bikaner

AREA (Ha): 3.60Revised 6.0

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: For demarcation of site Letter has been sent to Principal Chief Engineer,Jaipur on 25.01.2018. Consultant has submitted valuation calculation sheet only.N.I.T. for leasing out 6.00 Ha area considering Residential mix land use was publishedon 28.02.2018, but NIT cancelled due to non‐confirmity of land.

CONSTRAINTS/ ISSUES IF ANY: 1. CLU as per revised decision.

TIMELINES: 1. REUP:2. VALUATION: 3. BIDDING/NIT:  31.05.2018

f ll l l f l d/

Page 34: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites34

PROJECT: Shamatganj, BareillyDATE OF ENTRUSTMENT : 05.11.2009Availability of Land Records (Yes/No) : YesSTATE: Uttar PradeshRLY: NERDIVISION: Izzatnagar

AREA (Ha):  14.68Site A‐6.61Site B‐8.07 

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: 1. Application for CLU part B (8.07 Ha) has been sent to BDA on 05.10.2017.2. Consultant has submitted valuation report.3. Tender for leasing out the Site‐B has been invited on 07.12.2017 and bids to be

opened on 28.02.2018, cancelled for CLU not processed in BDA Board Meeting.4. Fresh proposal for CLU submitted for Site – A & Site‐B on 20.06.2018.

CONSTRAINTS/ ISSUES IF ANY:1. Encroachment to be removed for Site‐B.2. CLU for Site‐A & Site‐B.TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/NIT 30.08.2018 (Site‐B) 

28.02.2019 (Site‐A) 

Page 35: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites35

PROJECT: Nirala Nagar, KanpurDATE OF ENTRUSTMENT : 23.02.2007Availability of Land Records (Yes/No) : YesSTATE:  Uttar PradeshRLY: NERDIVISION:  Allahabad

AREA (Ha): 39.0

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: 1. Tender for  Master Planning & Marketing Valuation awarded on 01.11.2017 and work of Master planning and valuation is under progress.2 Decision for CLU has been taken as Residential and accordingly applied on 02.02.2018.CONSTRAINTS/ ISSUES IF ANY: 1. Entrustment of additional 4.5 Ha land by Railway Boardto RLDA is awaited. 2. Approval for 99 years’ lease period (Decision for ResidentialDevelopment has already accorded from Rly Board on 16.01.2014).3. Decision for development model is to be taken (Consultant’s final report is awaited).TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING/ NIT:

31.12.201731.08.2018

Page 36: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites36

PROJECT: Kakapallam, ICF (Padi)DATE OF ENTRUSTMENT : 30.04.2007Availability of Land Records (Yes/No) : YesSTATE: TamilnaduRLY:ICFDIVISION: ICF

AREA (Ha): 2.25

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: Site has been awarded to M/s. Pothy’s Pvt. Ltd. at L.P. of Rs. 43crore for 45 years lease period vide LOA dated 22.02.2018. Developerdeposited 1st installment along with interest in RLDA account on23.07.2018.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:JGM/Marktg3. BIDDING:

30.11.2017

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 37: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites37

PROJECT: NagapattinamDATE OF ENTRUSTMENT : 03.09.2007Availability of Land Records (Yes/No) :STATE:TamilnaduRLY:SRDIVISION: Trichy

AREA (Ha): 0.40

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: Consultancy (Architectural) in progress. CLU in advance stage. Publication in

local and English Dailys done during 1st week of March, 2018 for objection, if any. NOC

expected shortly. Valuation is under process for 45 years lease by Spot

Committee. Site to be inspected by CMC Member.

CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:JGM/SW3. BIDDING/NIT: 30.07.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 38: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites 38PROJECT: VillupuramDATE OF ENTRUSTMENT : 03.09.2007Availability of Land Records (Yes/No) : STATE: TamilnaduRLY:SRDIVISION: Trichy

AREA (Ha): 0.71 (2 plots)

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS:   i. Consultancy in progress. CLU in advance stage.ii. NIT issued on 19.04.2018.iii. Pre‐Bid Meeting hold on 22.05.2018 at Chennai attended by 13 parties.iv. Bid Opened on 27.06.2018. Only one bid received.v. Site has been awarded to Consortium of J. Kuber, KJ Ramesh, J Prakash &

J Venkateshat L.P. of Rs. 4.91 & 1.71 Crore for 45 years lease period vide LOAdated 31.07.2018.

CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING:

01.02.201831.05.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 39: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites39

PROJECT: Pallanthurthy (Island)DATE OF ENTRUSTMENT : 29.09.2014Availability of Land Records (Yes/No) : STATE: KeralaRLY:SRDIVISION: Thiruvanthapuram

AREA (Ha): 1.7

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: Marketing and valuation consultant engaged. Valuation reportwith CMC. Visit of CMC Committee to site is required.

CONSTRAINTS/ ISSUES IF ANY: 

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING/NIT:

30.09.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 40: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites40

PROJECT: SalemDATE OF ENTRUSTMENT : 03.09.2007Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY:  SRDIVISION: Salem

AREA (Ha): 1.05

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS:    The Tender was opened on 15.03.2017 but no bid is received. 

CONSTRAINTS/ ISSUES IF ANY: DRM/Salem has requested for de‐entrustment of thesite for their own use. Letter written to DRM/Salem on 15.02.2017with copy to PCE/SRthat the site can be de‐entrusted by Rly. Bd. only. Reminder to PCE/SR again issued on20.02.2018 that if land not got de‐entrusted by Railway Board in one month time, thenRLDA is going ahead for re‐invitation of Bid. Railway Board has de‐entrustedthe site.TIMELINES: 1. REUP:

2. VALUATION:3. BIDDING:

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 41: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

New Commercial Sites

Entrusted to RLDA vide Rly Board letter no. 2017/LML‐II/2/4(103) dated 

15.12.2017

41

RLDA....In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 42: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites42

PROJECT: Victoria Cresent, adjacent to Ethiraj CollegeDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 0.43

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: i. Land Records, Market Plan Provision, Permissible Land Use and other basic details

such as set‐back, Height restriction, FAR has been established.ii. Actual site survey has also been conducted in past and survey plan is available.iii. LOA issued on 21.05.2018 to M/s JLL for evaluation of the site.iv. Draft report received on 19.06.2018. Valuation done by all method for

Commercial Development only, Consultant M/s JLL is requested to dovaluation for Residential also. Matter pursued with M/s JLL.

v. Visit of CMC to site is required.CONSTRAINTS/ ISSUES IF ANY:  Abandoned Old RCT Building and Court  Bldg. to be demolished.TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3 BIDDING: (Tentative date)/ NIT

Not requiredAugust, 201831 08 2018

Page 43: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites43

PROJECT: Poes GardenDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 0.53

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: i. Land Records, Market Plan Provision, Permissible Land Use and other basic details

such as set‐back, Height restriction, FAR has been established.ii. Actual site survey has also been conducted in past and survey plan is available.iii. LOA issued on 21.05.2018 to M/s JLL for evaluation of the site. Report is

yet to be received.

CONSTRAINTS/ ISSUES IF ANY:    TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Not requiredAugust, 201831.08.2018.

Page 44: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites44

PROJECT: Waltax Road near Basin BridgeDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 0.12

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS:i. Contract for Architectural & Real Estate Consultancy has been awarded on 18.01.2018.ii. Joint Inspection with Consultant done on 05.02.2018.iii. Final Report of the Consultant is reviewed and under process of obtaining need full

clarification from CMDA regarding Land ownership.iv. Land use – Commercial CLU not required.v. However RFP for engagement of valuation consultant has been invited , date of

opening is 16.08.2018 but In house valuation is to be done.vi. Visit of CMC to is required.

CONSTRAINTS/ ISSUES IF ANY:    Plot at crossing, Parking problem, plot size very small with small temple at corner.TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/NIT

September, 2018October, 2018November, 2018

Page 45: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites45

PROJECT: PulianthopeDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 0.74

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS:  i. Contract for Architectural & Real Estate Consultancy has been awarded on

18.01.2018.ii. Joint Inspection with Consultant done on 05.02.2018.iii. Final Report of the Consultant is receivediv. Land use – Residential, CLU not required.v. RFP for engagement of valuation consultant has been invited .vi. Visit of CMC to site is required.CONSTRAINTS/ ISSUES IF ANY:   Site in congested area with LIG Housing nearby, also one Nalah is flowing nearby causing foul smell.

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/NIT

September, 2018October, 2018November, 2018

Page 46: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites46

PROJECT: TambaramDATE OF ENTRUSTMENT : 15.12.2017STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 1.65

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: i. Land Records, Market Plan Provision, Permissible Land Use and other basic details

such as set‐back, Height restriction, FAR has been established.ii. Actual site survey has also been conducted on 11.04.2018 and survey plan is

available.iii. Out of the total area of 1.65 Ha 0.528 Ha is in encroachment and under Court Case

as per the communication received from SSE/Works/TBM dated 04.11.2016.iv. Valuation consultant has been finalized. LOA issued to PDMAG on 29/7/2018.

Consultant required report of activity 1 ‐2.v. Visit of CMC to site is required.CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Not requiredJuly, 201831.08.2018.

Page 47: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites47

PROJECT: Park StationDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 0.33

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: i. Only Part Information is available for this site authentification,  which could not be 

ascertained with CMDA Website.  ii. Land Use is not assigned for this site as per Master Plan of CMDA. And CLU may 

require based on assessment of site.iii. LOA issued on 23.05.2018 for providing architectural & Real Estate Consultancy. 

Report from consultant is awaited.  CONSTRAINTS/ ISSUES IF ANY:  There are existing ADEN/Building, ADEN Bridge and SSE/Works Offices and Store etc.  Their shifting is required to be planned along with Railways. TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)

December, 2018February, 2019February, 2019

Page 48: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites48

PROJECT: Perambur Pananthope ColonyDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 2.00

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS:i. Only Part Information is available for this site authentification of which could not

been ascertained with CMDA Website.ii. Land Use is assigned for this site as per Master Plan of CMDA is primary

residential.iii. LOA issued on 23.05.2018 for providing architectural & Real Estate Consultancy.

Report from consultant is awaited.

CONSTRAINTS/ ISSUES IF ANY:    422 Qrtrs. in 28 blocks to be reconstructed.  Planning to be done in consultation with Railways.

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)

December, 2018February, 2019February, 2019

Page 49: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites49

PROJECT: Chennai ChetpetDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 0.76

Project Incharge: GM/CD ‐ Y.S. HoodaDGM/CD  Shri Sandeep KumarManager – Shri H.K. Srivastava

STATUS: i. Only Part Information is available for this site authentification of whichcould not been ascertained with CMDAWebsite.

ii. Land Use is not assigned for this site as per Master Plan of CMDA. And CLU mayrequire based on assessment of site.

iii. LOA issued on 23.05.2018 for providing architectural & Real Estate Consultancy.Report from consultant is awaited

iv. Possibility of acquiring private land for creating direct access/ approachto Mc. Nichols Road is being explored.

CONSTRAINTS/ ISSUES IF ANY:   Very poor approach to site with narrow roadsthrough hutments and LIG houses.TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)

December, 2018February, 2019March, 2019

Page 50: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites50

PROJECT: TiruvottiyurDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : YesSTATE: Tamil NaduRLY:SRDIVISION: Chennai

AREA (Ha): 19.43

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS:  i. Big site, Master Planning is required to see that we go for single phase or multi‐

phase development.ii. Joint Inspection with Consultant done on 05.02.2018. iii. Architectural Consultancy work already awarded and first report submitted by 

consultant on 25.05.2018.iv. Go ahed given for Activity‐2 work. CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)

Sept., 2018Oct., 201830.11.2018

Page 51: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites51

PROJECT: Chennai Egmore (Poonnamallee High Road)

DATE OF ENTRUSTMENT : 15.12.2017STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 2.00

Project Incharge:JGM/Planning‐I – Shri Parvendra KumarManager – R. Chaturvedi

STATUS:i. File processed for calling quotations for Arch. Consultancy work.  Land Use yet not 

established.ii. Planning for shifting of Offices and vacation of staff quarters needs to be done for 

which meeting with Railway officers planned in 2nd or 3rd week of April.iii. De‐entrusted on 03.04.2018.CONSTRAINTS/ ISSUES IF ANY:  54 type –II old Qrtrs., GE Lab, Supervisor and Officers Rest House, Telephone Exch. etc. Needs to be shifted with re‐construction, planning with Railways is required.TIMELINES: 1. REUP:

2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)

Sep., 2018Oct., 2019Nov, 2019

Page 52: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites52

PROJECT: Ayanavaram ColonyDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : Yes

STATE: Tamil NaduRLY: SRDIVISION: Chennai

AREA (Ha): 3.50

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS:i. The work be carried out on the deviation for work already awarded for

three sites of Chennai i.e. Tiruvottiur, Wall Tax Road & Pulianthope.Activity –I consultancy work in progress.

ii. Land record being collected by Consultant.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)

Sept., 2018Oct., 2018Nov., 2018

Page 53: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites53

PROJECT: Bandra (W)DATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : Yes

STATE: MaharashtraRLY: WRDIVISION: Mumbai

AREA (Ha): 1.03 Ha

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD – Shri Rakesh Kumar GuptaManager‐

STATUS: (i) The entire Colony has entrusted vide RB Letter dated 20.07.2018about 50000 Sqm.(ii) Activity – 1 Report of earlier entrusted 1.03 Ha has submitted by theConsultant.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING:

30.10.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 54: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites54

PROJECT: Lokgram KalyanDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : 

STATE: MaharashtraRLY: WRDIVISION: Mumbai

AREA (Ha): 3.65 Ha

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD – Shri Rakesh Kumar GuptaManager‐

STATUS: There are multiple land usage allocated on this land parcel. Part site , asper existing land use (Residential) is being considered for bidding in consultationwith Architect.Architectural Consultant made presentation on 25.06.2018.CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING:

31.07.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 55: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites55

PROJECT: Kurla (West)DATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : YesSTATE: MaharashtraRLY: WRDIVISION: Mumbai

AREA (Ha): 0.13 Ha

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD – Shri Rakesh Kumar GuptaManager‐

STATUS: Architectural Consultant has submitted draft report . Final report tobe submitted shortly after presentation. However, NIT for fixing ofvalutaion consultant has been issued on 27.06.2018. Presentation to beplanned on 05/7/2018. Consultation for Financial & Marketing has been fixedon 01.08.2018.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:JGM/SW3. BIDDING:

31.07.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 56: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites56

PROJECT: Khar ColonyDATE OF ENTRUSTMENT : 15.12.2017Availability of Land Records (Yes/No) : YesSTATE: MaharashtraRLY: WRDIVISION: Mumbai

AREA (Ha): 0.33 Ha

Project Incharge: GM/BD – Shri Virender Kr.DGM/BD – Shri Rakesh Kumar GuptaManager‐

STATUS: Architectural Consultant to submit its report in this week itself CONSTRAINTS/ ISSUES IF ANY: The site as a whole has good potential for Residentialdevelopment. Land use is Residential. Railway may be asked to entrust whole plot byremoving the encroachments.However, the shape & size of the entrusted land parcel will be suitable for commercialdevelopment. (CLU Required)Activity‐1 report has submitted by Consultant. Observations have beenraised , not complied till date.TIMELINES: 1. REUP:

2. VALUATION:JGM/SW3. BIDDING:

31.07.2018

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 57: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

New Commercial Sites

Entrusted to RLDA vide Rly Board letter No. 2017/LML‐II/2/4(103) dated 

15.05.2018

57

RLDA....In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 58: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites58

PROJECT: Shakurbasti (Old Rohtak Road), DelhiDATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : Yes

STATE: DelhiRLY: NRDIVISION: 

AREA (Ha):17.90

Project Incharge: GM/BD – Shri Virender Kr.DGM/P‐II – Shri Jatinder KumarManager‐ None

STATUS: (i) Bid for appointment of architectural consultant for master planning for thesite has been opened on 25.07.2018. 04 Bids received are under evaluation byJGM/Planning‐I.(ii) Bid for appointment of Financial and Marketing consultant invited on 31.07.2018and due for opening on 23.08.2018.CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT4. LoA

25.09.2018 10.11.201830.11.201815.03.2019

Page 59: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites59

PROJECT: MTS Colony, Karwar Road, HubliDATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : STATE: KarnatakaRLY: SWRDIVISION:

AREA (Ha):6.00

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS: Site is to be inspected.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Page 60: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites60

PROJECT: Park (Millennium Park) Opp. Rail Kalyan near Mettuguda Metro Station.DATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : STATE: RLY: SCRDIVISION:

AREA (Ha):0.96

Project Incharge: CPM/SC – Shri V.S. RajuJGM/Planning‐II  ‐ Shri J.S. MishraManager ‐ None

STATUS:  Site Visit with CPM/SCB on 23rd to 24th Aug 2018.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Page 61: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites61

PROJECT: Bijoli Quarters area, Liluah.DATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : NoSTATE:  WBRLY: ERDIVISION: Howrah

AREA (Ha):1.66

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: Tender for Architectural work awarded on Activity‐I work in progress.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Page 62: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites62

PROJECT: Strachey Road Colony, Liluah.DATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : NoSTATE: WBRLY: ERDIVISION: Howrah

AREA (Ha):0.93

Project Incharge: CPM/LKO‐ Shri S.K. SahuJGM/Planning ‐ I  – Shri Parvendra Kumar Manager ‐ R. Chaturvedi

STATUS: Tender for Architectural work awarded on Activity‐I work inprogress.

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Page 63: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites63

PROJECT: Boulevard Colony, DIVISION: DelhiDATE OF ENTRUSTMENT : 09.07.2018STATE: DelhiRLY: NR

AREA (Ha):2.18

Project Incharge: GM/ProjectDGM/Project‐II – Shri Jatinder Kumar

Existing  Quarters & Service Bldg Proposed Quarters & Service Bldg

Ty‐II: 54 Ty‐III: 6 & Ty‐IV: 4 Total = 64  & Serv. B: NIL Sqm

Ty‐II: 54 Ty‐III: 6 & Ty‐IV: 4 Total = 64  & Serv. B: NIL Sqm

STATUS: 1. Initial inspection done by GM/Project and his team & 1st round Phaseworking in Two phases planned.2. (i) Area proposed for Railway re‐development 1.50 Ha,

(ii) Area proposed for Commercial Development 0.91 Ha,(iii) Area proposed for Developers Residential Development 6.73 Ha,

3. Expected earning Rs. 275 Crore, 4. Architectural Consultancy – NIT issued on 31.07.2018.CONSTRAINTS/ ISSUES IF ANY:TIMELINES: 1. Arch. Consl. Award Under Process 

2. MoU with Railway  15.10.2018

3. Valuation  ‐‐

Page 64: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites64

PROJECT: Patukotai

DATE OF ENTRUSTMENT : 03.09.2007

STATE: TamilnaduRLY:SRDIVISION: Trichy

AREA (Ha): 0.80 (3 plots)

Project Incharge:DGM/CD‐ Shri SandeepManager /Project‐II ‐ Shri H.K. Srivastava

STATUS: Consultancy (Architectural) in progress. CLU application to be filed. Siteis commercially not viable. Population of 70,000. Site not commercially viable.Letter written to Railway Board for De‐entrustment on 04/10/2017

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING:

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 65: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites65

PROJECT: Gola ka Mandir, GwaliorDATE OF ENTRUSTMENT : 25.04.2007

STATE: MPRLY:  NCRDIVISION: Gwalior

AREA (Ha): 1.30Effective after road widening‐0.85

Project Incharge:DGM/Tender ‐ Shri Neeraj Kr. GuptaManager – Abhay Kumar Thakur

STATUS: Financial & Marketing Consultant engaged in June 2016. Financial consultant  has asked for the available area for development in view of the Gwalior Vikas Yojna 2021. Utilisation of FAR possible even after reduction  of width for road widening. Letter written to Railway Board on 04.10.2017  for De‐entrustment and consequently de‐entrustment done by Railway Board vide letter dated 15.12.2017. 

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: JGM/Mktg3. BIDDING:

31.10.201715.11.2017

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 66: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites66

PROJECT: Diesel Shed, Jodhpur

DATE OF ENTRUSTMENT : 27.02.2014

STATE: RajasthanRLY:NWRDIVISION: Bikaner

AREA (Ha): 2.19

Project Incharge:DGM/Tender ‐ Shri Neeraj Kr. GuptaManager – Abhay Kumar Thakur

STATUS:    Land papers/title not available. The division is doing needful for recasting of land papers/title.  Letter written to Railway Board on 04.10.2017  for De‐entrustment and consequently de‐entrustment done by Railway Board vide letter dated 15.12.2017

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING:

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 67: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites67

PROJECT: Phoos Ka BunglowDATE OF ENTRUSTMENT : 27.02.2014

STATE: RajasthanRLY:NWRDIVISION: Jaipur

AREA (Ha):0.14

Project Incharge:DGM/Tender ‐ Shri Neeraj Kr. GuptaManager – Abhay Kumar Thakur

STATUS: NWR vide letter dated 03.03.2016 requested Rly Bd for de‐entrustment. Kept in abeyance. Letter written to Railway Board on4.10.2017 for De‐entrustment and consequently de‐entrustment done byRailway Board vide letter dated 15.12.2017.CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION:3. BIDDING:

RLDA In pursuit of Excellence in Commercial Development of Railway Land/Air Space

Page 68: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites68

PROJECT: Lakdi Ka PulDATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : 

STATE: Hyderabad RLY: SCRDIVISION:

AREA (Ha):0.74

Project Incharge:JGM/Project ‐Manager ‐

STATUS: Entrusted on 20.07.2018. Tender call for Activity 1 & 2 has been processed. 

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT

Page 69: RAIL LAND DEVELOPMENT AUTHORITY - rlda.indianrailways.gov.in · During last two bids in Feb 2018 & June 2018, No bids received. Site visit and discussion with Local DeveloperwithCPM/SCB

Commercial  Sites69

PROJECT: Sanjeevaiah Park SiteDATE OF ENTRUSTMENT : 15.05.2018Availability of Land Records (Yes/No) : STATE: Hyderabad RLY: SCRDIVISION:

AREA (Ha):0.4

Project Incharge:JGM/Project ‐Manager ‐

STATUS: NIQ for Architectural Consultancy issued. 

CONSTRAINTS/ ISSUES IF ANY:

TIMELINES: 1. REUP:2. VALUATION: (Tentative date)3. BIDDING: (Tentative date)/ NIT